CHAPTER 3
p. 163
SECTION II 3-i SECTION II
CHAPTER 3
REFERENCES
REFERENCE INSTRUCTION NO. SUBJECT
(a) OPNAVINST 3120.33B SERIES SUBMARINE EXTENDED OPERATING CYCLE (SEOC) PROGRAM (b) OPNAVINST 4790.16
CONDITIONED-BASED MAINTENANCE (CBM) POLICY (c) CINCLANTFLT/CINCPACFLT INST 4790.3 SERIES JOINT FLEET MAINTENANCE MANUAL
Downloaded from https://www.everyspec.com
p. 164
NAVSEAINST 4790.8B 3-ii
SECTION II CHAPTER 3 SUBMARINE PERFORMANCE MONITORING TEAM (PMT) MAINTENANCE AND INSPECTION PROCEDURES TABLE OF CONTENTS
Paragraph Title Page
3-1 PURPOSE...................................................3-1 3-2 PMT MISSION...............................................3-1 3-3 MAINTENANCE RESPONSIBILITY AND SCHEDULING.................3-1 3-4 PMT DOCUMENTATION AND REPORTING...........................3-2 3-4.1 PMT CBM Deficiency Reports..............................3-2 3-4.2 End of Monitoring Period (EMP) Reporting................3-2 3-5 DATA COLLECTED & TRENDED..................................3-2 Downloaded from https://www.everyspec.com
p. 165
Downloaded from https://www.everyspec.com
p. 166
NAVSEAINST 4790.8B 3-1 SECTION II CHAPTER 3 SUBMARINE PERFORMANCE MONITORING TEAM (PMT) MAINTENANCE AND INSPECTION PROCEDURES
3-1 PURPOSE
This chapter describes the Maintenance and Material Management (3-M) related actions required prior to, during, and following an inspection and other maintenance monitoring conducted by the submarine Performance Monitoring Teams (PMT). 3-2 PMT MISSION
The Submarine Performance Monitoring Team (PMT) Program was established by the Chief of Naval Operations, per reference (a), as a method of collecting objective engineering evidence of ship system performance. This data was then used to allow the extension of shipyard overhauls to extend the operational cycle and useful life of the vessels, and align major maintenance. While this mission is still applicable today with the PMT’s ensuring safe and reliable Extension of Operating Cycles (EOC’s), the maintenance has also evolved into using Conditioned Based Maintenance (CBM) techniques to assess the performance of many critical submarine systems, primarily the submarine Hull, Mechanical, and Electrical Systems (HM&E). The inspections conducted by PMT aid in improving the submarine fleet’s material condition and operational readiness. They do this by aiding in early identification of system deficiencies and/or predicting failures before they occur and avoid more critical mission- limiting failures. The PMT Program also assists NAVSEA 07T in identifying and resolving fleet material issues, improving system reliability, reducing Total Ownership Cost (TOC), and assessing system health across the fleet. Other products of the program include major shipyard availability inputs for work package definition, special inspection programs defined in reference (c) like the Vibration Analysis Program, and other fleet assistance. NAVSEA 07T provides the technical oversight, technical documentation, requirements, and analysis for the PMT Program. 3-3 MAINTENANCE RESPONSIBILITY AND SCHEDULING The maintenance requirements and inspections that are monitored by PMT are fully integrated in the ship’s PMS system. These Maintenance Requirement Cards (MRC’s) are coded with a “K” in Downloaded from https://www.everyspec.com
p. 167
SECTION II 3-2 the “Other” column on the MIP. The scheduling and performance of this maintenance is the responsibility of the ship. PMT, using an advanced engineering data collection and analysis information system, will aid in the scheduling of this maintenance. It is recommended that the ship frequently bring a copy of the PMS cycle for the applicable work centers to the PMT to update their system. When an inspection is required, contact the local PMT site to schedule. 3-4 PMT DOCUMENTATION AND REPORTING 3-4.1 PMT CBM Deficiency Reports The deficiencies and recommendations that result from a PMT inspection and monitored maintenance are published in an engineering memorandum called an On Site Analysis Report (OSAR). This material deficiency report is passed to the ship for corrective action and maintenance planning where applicable. In some cases, no repair action is required if a condition exists which is starting to degrade, yet does not meet repair conditions, so the OSAR is provided for information or other action like increased monitoring frequency. These OSAR’s are also uploaded to NAVSEA 07T’s database for advanced analysis and to aid in overall system health determination. 3-4.2 End of Monitoring Period (EMP) Reporting Periodically, PMT will provide a summary report of the monitored maintenance for a summary closeout of the services and deficiencies provided and to aid in the planning of the next monitoring period. The ship’s “monitoring period” is a finite period of time usually corresponding to a patrol period for SSBN’s or aligned with maintenance availabilities taking the IDTC into account for the SSN’s. This monitoring period mirrors the ship’s PMS cycle. 3-5 DATA COLLECTED & TRENDED The data collected per the datasheets attached to the “K” MRC’s, as well as the deficiency reports is entered into the PMT’s engineering analysis system and typically uploaded nightly to a main database. Over 5 years of data exists for the data that is collected. The website provides the ability to retrieve the data and export to excel spreadsheets as well as on line graphing of data that behaves in a predictable fashion. Ship’s Force and other organizations may request historical data through the local PMT site. Downloaded from https://www.everyspec.com
p. 168
MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL
SECTION III
Chapter 1
REPORTS AND SERVICES AVAILABLE FROM THE NAVAL SEA LOGISTICS CENTER (NAVSEALOGCEN)
Downloaded from https://www.everyspec.com
p. 169
SECTION III 1-i SECTION III
REFERENCES
REFERENCE INSTRUCTION NO. SUBJECT
None. No instructions referenced in SECTION III.
Downloaded from https://www.everyspec.com
p. 170
NAVSEAINST 4790.8B 1-ii
SECTION III
REPORTS AND SERVICES AVAILABLE FROM THE NAVAL SEA LOGISTICS CENTER (NAVSEALOGCEN) TABLE OF CONTENTS
Paragraph Title Page
1-1 3-M SYSTEM DATABASE.......................................1-1 1-2 DATA COLLECTED............................................1-1 1-3 USES OF THE DATA..........................................1-2 1-4 DATA ELEMENTS AVAILABLE IN THE 3-M SYSTEM.................1-3 1-5 SHIPS' 3-M ON-LINE SYSTEM.................................1-3 1-6 THE OPEN ARCHITECTURAL RETRIEVAL SYSTEM (OARS)............1-3 1-7 ON-LINE SYSTEMS TRAINING COURSE...........................1-4 1-8 REPORT PRODUCTS...........................................1-4 1-9 OTHER PRODUCTS............................................1-4 1-10 REQUESTING 3-M SYSTEM DATA...............................1-5
Downloaded from https://www.everyspec.com
p. 171
Downloaded from https://www.everyspec.com
p. 172
NAVSEAINST 4790.8B 1-1 SECTION III
REPORTS AND SERVICES AVAILABLE FROM THE NAVAL SEA LOGISTICS CENTER (NAVSEALOGCEN)
1-1 3-M SYSTEM DATABASE Ships' maintenance information is reported by fleet personnel to the Naval Sea Logistics Center (NAVSEALOGCEN), Mechanicsburg, PA, for processing into the Ships' Maintenance and Material Management (3-M) System Database. This database provides a single source of 3-M data available to NAVSEASYSCOM Program and Equipment Managers, In-Service Engineering Activities, TYCOMS, Ships, NAVSUPSYSCOM and government sponsored contractors. 1-2 DATA COLLECTED Maintenance data reported and retained in the 3-M system database includes:
a. Completed maintenance
b. Deferred maintenance
c. Planning and Estimating information for shipboard and IMA
d. Repair parts
e. Configuration data
f. Intermediate Maintenance Activity data from:
(1) Tenders
(2) Repair shops
(3) Type Commander (TYCOM) Support Units
(4) Shore Intermediate Maintenance Activities (SIMAs)
g. Reactivated ships CSMPs
It must be recognized that the integrity of the database is relevant only to the accuracy of the data reported. Downloaded from https://www.everyspec.com
p. 173
SECTION III 1-2 1-3 USES OF THE DATA Information available from the 3-M Maintenance Data System can be of value in:
a. Scoping and quantifying data for engineering and logistics analyses.
b. Providing management resource information to higher authority to support the decision making process.
c. Planning and allocating resources for logistics support.
d. Analyzing maintenance/reliability problems.
e. Determining adequacy of equipment specifications.
f. Analyzing life cycle and other costs.
g. Determining equipment effectiveness.
h. Preparing and/or updating technical manuals/directives.
i. Providing work center equipment maintenance history.
j. Providing data assist provisioning.
k. Overhaul planning.
l. Analyzing repair parts usage.
m. Updating allowance lists and the Coordinated Shipboard Allowance List (COSAL).
n. Providing data for ship design.
o. Shipboard management including determination of problem equipment and providing data for availability and overhaul.
p. Analyzing part failures.
q. Displaying labor hours, parts cost, maintenance action count and the calculated ownership cost value for ships and equipment. Downloaded from https://www.everyspec.com
p. 174
NAVSEAINST 4790.8B 1-3 1-4 DATA ELEMENTS AVAILABLE IN THE 3-M SYSTEM The MDS data elements, which are stored in the database are listed and defined in the Ships' 3-M Database Reference Manual, which can be downloaded from the NAVSEALOGCEN home page (http://nslc.navsea.navy.mil). The OPNAV 4790/2K, OPNAV 4790/CK, OPNAV 4790/2F, OPNAV 4790/2P, DD 1348 and NAVSUP 1250-1 Forms and 3-M ADP programs are used to report these data elements. 1-5 SHIPS' 3-M ON-LINE SYSTEM The Ships' 3-M On-line database is a historical repository of corrective maintenance actions spanning 1990 through current date. It contains maintenance, supply and IMA data and allows the user to select, sort and/or process data as well as create reports. It provides the means to plan, acquire, organize, direct, control and evaluate manpower and material resources in support of maintenance. The Ships' 3-M On-line database is used to predict failure rates of components, determine areas that need improvement and track equipment performance. Access to 3-M data allows the user to research equipment history, perform trend analysis and provide a tool to the fleet that can provide information concerning fleet maintenance and maintenance support experience to organizations responsible for logistics support to the fleet. On-line access is available through NAVSEALOGCEN. 1-6 THE OPEN ARCHITECTURAL RETRIEVAL SYSTEM (OARS) All members of the NAVSEA community, the Fleet, and others with access to SMARTLINK or TCP/IP telecommunications protocol, can access the database from their desktop computers by using OARS, a client software tool developed by the Naval Sea Logistics Center. OARS, an intuitive, flexible tool that operates in a Windows environment was designed to make retrieving maintenance and material management information quick and easy.
OARS generates most standard 3-M reports, such as Parts Issued For Maintenance Detailed Report and the 4790.S5019 Ships' 3-M History Report. Also, new reports are available now as standard reports, such as: 4790.L0103, 4790.L0104, 4790.L0105 Ownership Cost Reports, and 4790.L0300 Selected Level Reporting (SLR) Reports. The application can produce Ad Hoc reports, as well as import text, and download data. One can run reports in immediate or batch mode and save reports in various file formats, such as: Excel, text, dBase, etc.
To find out more about this tool, or to become an OARS user, visit the OARS web site at www.oars.navsea.navy.mil. Downloaded from https://www.everyspec.com
p. 175
SECTION III 1-4 1-7 ON-LINE SYSTEMS TRAINING COURSE The Ships' 3-M/OARS Basic Training Course is a two day course designed to introduce and train individuals on the basic usage of Ships' 3-M data as well as the OARS Retrieval Tool. This course is essentially broken into two main topic areas, Introduction and Overview of Ships' 3-M, and Introduction of the OARS Retrieval Tool. This training places an emphasis on hands- on computer lab time. Upon completion, students should have obtained a knowledge level, which will enable them to retrieve the data necessary for the specific functions desired. The course is conducted by NAVSEALOGCEN. 1-8 REPORT PRODUCTS The Ships' 3-M Standard Reports Manual , available from NAVSEALOGCEN, displays samples and descriptions of the Ships' 3- M reports available through OARS. Potential users of ships' maintenance data should contact NAVSEALOGCEN for assistance if a desired product format is not listed in the Ships' 3-M Standard Reports Manual. If you have specific needs, which are not met within the standard reports, OARS provides the capability of developing customized ADHOC reports. 1-9 OTHER PRODUCTS There are various products, which are available through the NAVSEALOGCEN Homepage, which provide valuable tools to the customer. These include:
a. Ships' 3-M Manual - OPNAVINST 4790.4D
An online version of the OPNAVINST 4790.4D. This instruction establishes CNO's policy, requirements, and responsibilities for the Ships' 3-M System. Instructions contained in this manual supersede any other directives, which may be in conflict
b. Ships' 3-M Reference
An online means to access reference information. This site offers users ability to access thirty-nine 3-M reference code tables. Each code table provides the definition and code translation for each entry in the table. The user has the ability to search each table by code, definition, or keyword. Additionally the user may use the “list” option to display the entire list of codes for a particular table. Where appropriate a hierarchical breakdown of the code is available.
Downloaded from https://www.everyspec.com
p. 176
NAVSEAINST 4790.8B 1-5 c. The Maintenance Modernization Business Unit (MMBU) Standard Codes Forum
Standard Codes Forum contains a mirror image of all code tables implemented within the current releases of the Organization Maintenance Management System - Next Generation (OMMS-NG) and the Maintenance Resource Management System (MRMS), and the Regional Maintenance Automated Information System (RMAIS). It also serves as a communications link within the Naval Community where recommended changes, modifications and deletions are submitted, discussed and approved/disapproved prior to release version implementation.
d. Ships' 3-M Data Record Layout
Describes the format of all data records processed through the legacy Shipboard Non-Tactical ADP Program (SNAP) systems, which are found within Ships' 3-M.
e. Ships' 3-M Data Record Layout - 120 Card Format
Specifies the card format for all data records found within Ships' 3-M.
Additionally, for those customers not having accessibility to the Internet, a Ships' 3-M Reference CD, which contains some of the more significant reference tables, is available. The reference information available via the CD includes; Equipment Identification Codes (EIC), Allowance Parts List population(APL), Activity Status File/Steaming Hours, and Expanded Ship Work Breakdown Structure (ESWBS). 1-10 REQUESTING 3-M SYSTEM DATA Data requests may be submitted by telephone to the customer support help desk, email, letter or message directly to NAVSEALOGCEN.
Information concerning Ships' 3-M as well as access to various Ships' 3-M products can be obtained through the NAVSEALOGCEN Homepage.
Any written correspondence to the NAVSEALOGCEN Customer Support Help Desk may be forwarded to:
Downloaded from https://www.everyspec.com
p. 177
SECTION III 1-6 Naval Sea Logistics Center ATTN: N60 Logistics Data Systems Department 5450 Carlisle Pike P.O. Box 2060 Mechanicsburg PA 17055-0795
Correspondence may be passed to NAVSEALOGCEN via the Internet by accessing the Customer Support Feedback Form.
To receive Ships' 3-M information via the telephone, contact should initiate with the Customer Support Help Desk:
Commercial DSN
Telephone (717) 605-2043 430-2043 FAX (717) 605-2669 430-2669
Downloaded from https://www.everyspec.com
p. 178
MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL
SECTION IV
Chapter 1
3-M SYSTEMS TRAINING
Downloaded from https://www.everyspec.com
p. 179
SECTION IV 1-i SECTION IV
REFERENCES
REFERENCE INSTRUCTION NO. SUBJECT
None. No instructions referenced in Section IV.
Downloaded from https://www.everyspec.com
p. 180
NAVSEAINST 4790.8B
1-ii
SECTION IV
3-M SYSTEMS TRAINING TABLE OF CONTENTS
Paragraph Title Page
1-1 INTRODUCTION..............................................1-1 1-2 3-M SYSTEM AND 3-M SYSTEM SUPPORT ASHORE TRAINING.........1-1 1-3 OTHER 3-M SYSTEM TRAINING.................................1-3 1-3.1 Naval Sea Logistics Center (NAVSEALOGCEN)...............1-3 1-4 SHIPBOARD TRAINING........................................1-4 1-4.1 3-M System Team Assist Visits...........................1-4 1-4.2 Training Sources/Aides Available........................1-4
Downloaded from https://www.everyspec.com
p. 181
Downloaded from https://www.everyspec.com
p. 182
NAVSEAINST 4790.8B
1-1 SECTION IV
3-M SYSTEMS TRAINING
1-1 INTRODUCTION The ships' 3-M System consists of the Planned Maintenance System (PMS) and Maintenance Data System (MDS) and is the nucleus for managing maintenance aboard all ships and shore stations of the Navy. Personnel must have a clear understanding of: (1) how to effectively manage maintenance, configuration and logistics support appropriate to their position; (2) how PMS is essential to sustaining material readiness; and (3) how and why managers at the systems command level are dependent upon the 3-M System for information to identify and correct Fleet material problems.
The Naval Education Training Command (NETC) is responsible for maintaining a 3-M System training plan designed to meet the needs of the Fleet.
TYCOMs must ensure adequate 3-M Program training for all personnel within the command associated with maintenance, configuration and logistics support management. The TYCOMs are required to monitor and take corrective action to ensure ship compliance with 3-M policy and procedures, including a continuing quality review of 3-M data submitted by each ship.
Shipboard on-the-job training represents the cornerstone of Fleet operational readiness and provides the optimum method of acquiring hands-on training. On-the-job training will be relied upon to sustain that level of knowledge and awareness received during formal training. Training should be continuous as new methods, procedures or features are introduced. 1-2 3-M SYSTEM AND 3-M SYSTEM SUPPORT ASHORE TRAINING The Center for Service Support (CSS) is the program manager for fleet-wide 3-M training. Feedback or requests for information should be sent to: Commanding Officer Center for Service Support (CSS) ATTN: FIM Directorate 1425 Prince Avenue Athens, GA 30677
Downloaded from https://www.everyspec.com
p. 183
SECTION IV 1-2 cssfim@cnet.navy.mil Commercial (706) 355-7501 DSN 354-7501
3-M System training is additionally provided in the curricula of Class A schools, United States Naval Academy (USNA), Officer Candidate School (OCS) and Naval Reserve Officer Training Candidate (NROTC) courses to introduce students to 3-M system concepts, operation applications and benefits.
Other training is available upon request. Information on courses available, course descriptions, quota controls and school locations can be obtained from the Catalog of Naval Training Courses (CANTRAC). The following are 3-M courses currently available and reflect the course number, course name, number and target audience:
NAVY TACTICAL COMMAND SUPPORT SYSTEM (NTCSS) II MANAGER A-531-0021 To train personnel in common software services that provide interface between client/server application programs and the operational environment.
SNAP 3-M SYSTEMS COORDINATOR/INSPECTOR J-500-0029 This course trains TYCOM-GROUP-SQUADRON personnel and Ships 3-M Coordinators in the responsibilities associated with verification, update and inspection of the ships 3-M Systems. Personnel applying for this training must be billeted to either a 3-M Coordinator or 3-M Inspector Billet.
UNIT LEVEL RSUPPLY A-551-0026 Relational Supply Unit Technical Specialist
STOCK CONTROL SUPERVISOR/RSUPPLY FORCE LEVEL A-551-0027 Provides leading Storekeepers assigned to RSupply (Force) equipped ships with the required knowledge and skills to perform duties.
RELATIONAL SUPPLY (UNIT) STOCK CONTROL SUPERVISOR A-551-0028 To provide leading Storekeepers assigned to RSupply (Unit)- equipped ships with the required knowledge and skills to perform duties.
Downloaded from https://www.everyspec.com
p. 184
NAVSEAINST 4790.8B
1-3 RSUPPLY (FORCE LEVEL) OPERATIONS TECHNICIAN A-551-0029 To provide knowledge and skills training for Storekeepers assigned to or in transit to RSupply (Force Level) -equipped ships. Petty Officers will be assigned access within one or more functional systems and with specific responsibilities within a particular functional area. These individuals will be able to perform add/change/delete records, suspend transaction processing, queries, issues, requisition and receipt processing. Submit batch jobs for generation of management reports, and process Defense Finance and Accounting Service (DFAS) financial feedback reconciliations.
SNAP II LEADING STOREKEEPER AFLOAT A-551-0093 The SNAP II Leading Storekeeper Afloat will be responsible for the performance of the automated procedure required by Leading Storekeepers Afloat on a Shipboard Non-Tactical Automated Data Processing Program II (SNAP II) ship in accordance with applicable documentation.
SNAP II SUPPLY FINANCIAL MANAGEMENT SUPERVISOR A-551-0094 This course is designed to provide enlisted personnel ordered to leading storekeeper billets on SNAP II equipped ships with the knowledge and skills necessary to perform all duties required of the leading storekeeper in supervising the operation and management of the SNAP II SFM System.
SHIPBOARD UNIFORM AUTOMATED DATA PROCESSING SYSTEM-RT MANAGER A-551-0096 The SUADPS-RT course is designed to provide senior enlisted E6-E9 Storekeepers and Officers CWO-04 with the knowledge and skills required to perform the duties of Logistics Primary Assistant, Stock Control, Material, Stores, Cargo and QA billets aboard SNAP I platforms (T-AFS, AS, CV, CVN, LHA, LHD, LPH).
1-3 OTHER 3-M SYSTEM TRAINING 1-3.1 Naval Sea Logistics Center (NAVSEALOGCEN) Available from NAVSEALOGCEN is the Ships' 3-M On-line System Training Course. The course sponsored and conducted by NAVSEALOGCEN is a 2 day program designed to introduce and train individuals on the usage of OARS and the 3-M database. This course essentially encompasses two major areas, Introduction and Downloaded from https://www.everyspec.com
p. 185
SECTION IV 1-4 Overview of Ships’ 3-M and Introduction to the OARS Retrieval Tool. It provides both instruction and hands-on lab time. Upon completion of this course, individuals should possess enough knowledge to enable them to retrieve data necessary for their specific functions.
Target audience includes military and civilian, equipment life cycle managers, system managers and engineers with a need to work with Ships' 3-M data. Requests for information and course dates should be addressed to:
Commanding Officer Naval Sea Logistics Center Attn: Code N60 5450 Carlisle Pike P. O. Box 2060 Mechanicsburg, PA. 17055-0795
Commercial (717) 605-4734 DSN 430-4734
Navy Integrated Call Center Commercial 1-877-418-6824 DSN 510-428-6824 1-4 SHIPBOARD TRAINING The commanding officer establishes and maintains a viable 3-M system training program to sustain that level of knowledge and awareness received during formal training. 1-4.1 3-M System Team Assist Visits Periodic assistance is provided upon request. 1-4.2 Training Sources/Aides Available The following 3-M System training courses and aids are available to assist in shipboard training:
a. 3-M PQS (NAVEDTRA 43241F), and provides the 3-M knowledge and fundamentals required for workstations with both PMS and automated MDS requirements.
Downloaded from https://www.everyspec.com
p. 186
MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL
APPENDIX A
DATA ELEMENT DESCRIPTIONS AND VALIDATION SPECIFICATIONS
Downloaded from https://www.everyspec.com
p. 187
APPENDIX A-i APPENDIX A
DATA ELEMENT DESCRIPTIONS AND VALIDATION SPECIFICATIONS TABLE OF CONTENTS
Paragraph Title Page
A-1 PURPOS E............................................ A-1 A-2 OBJECT IVE.......................................... A-1
Data Element
ACCEPTED BY................................................. A-13 ACTION TAKEN (ACT. TKN.).................................... A-13 ACTIVE MAINTENANCE TIME..................................... A-15 AILSIN...................................................... A-16 ALLOWANCE PARTS LIST/ALLOWANCE EQUIPAGE LIST (APL/AEL)...... A-16 ALTERATION IDENTIFICATION (CONFIGURATION CHANGES)........... A-16 ASSIST REPAIR WORK CENTER (ASST. REPAIR W/C)................ A-17 ASSIST REPAIR WORK CENTER ESTIMATED MAN-HOURS (ASST EST MHRS)A-17 AUTOMATED INTEGRATED LANGUAGE SYSTEM IDENTIFICATION NUMBER (AILSIN).................................................... A-17
BLUEPRINTS, TECHNICAL MANUALS, ETC.......................... A-17
CAUSE (CAS)................................................. A-18 COMMANDING OFFICER'S SIGNATURE ............................. A-19 COMPLETED BY................................................ A-19 COMPLETED DEFERRAL (COMP DEFL).............................. A-19 COMPLETED MAINTENANCE ACTION, NO DEFERRAL (COMP M/A NO DEFL) A-19 COMPLETION DATE............................................. A-19 COMPONENT ACTION (CA)....................................... A-19 COMPONENT APL/AEL........................................... A-19 COMPONENT IDENTIFICATION.................................... A-19 COMPONENT NOUN NAME......................................... A-20 COMPONENT SERIAL NUMBER/IDENTIFICATION/EQUIPMENT SERIAL NUMBER...................................................... A-20 CONFIGURATION FILE CORRECTION (CONF FILE CORR).............. A-20 CONTINUATION FOR............................................ A-20 CONTINUATION SHEET.......................................... A-20 CSMP SUMMARY................................................ A-20
DATE ....................................................... A-21 DATE COMPLETED.............................................. A-21 DATE OF ESTIMATE ........................................... A-21 DEADLINE DATE .............................................. A-21 Downloaded from https://www.everyspec.com
p. 188
NAVSEAINST 4790.8B A-ii DEFERRAL DATE (DEFER. DATE) ................................A-21 DEFERRAL REASON (DFR) ......................................A-21 DEPARTMENT INITIALS ........................................A-22 DIVISION INITIALS ..........................................A-22
ENGINEERING OPERATIONAL SEQUENCING SYSTEM (EOSS) ...........A-22 EQUIPMENT IDENTIFICATION CODE (EIC) ........................A-22 EQUIPMENT NOUN NAME ........................................A-23 ESTIMATED MAN-DAYS .........................................A-23 ESTIMATED MAN-DAYS COST ....................................A-23 ESTIMATED MAN-HOURS (EST. MHRS.) ...........................A-23 ESTIMATED MATERIAL COSTS ...................................A-24 ESTIMATED TOTAL COST .......................................A-24
FINAL ACTION ...............................................A-24 FIRST CONTACT/MAINTENANCE (MAN) ............................A-24
HULL NUMBER ................................................A-24
IDENTIFICATION/EQUIPMENT SERIAL NUMBER .....................A-24 IMA REPAIR WORK CENTER ......................................A-25 IN PROGRESS ................................................A-30 INSURV NUMBER ..............................................A-31 INTEGRATED PRIORITY ........................................A-31 IUC/REPAIR ACTIVITY/TYCOM REMARKS ..........................A-31 IUC SCREENING ..............................................A-31 IUC SIGNATURE ..............................................A-32
JOB CONTROL NUMBER (JCN) ...................................A-32 JOB DESCRIPTION/REMARKS ....................................A-32 JOB ORDER NUMBER (en ........................................A-32 JOB SEQUENCE NUMBER ........................................A-32 JULIAN DATE ................................................A-32
KEY EVENT ..................................................A-32 KEY OPERATION (KEY OP) .....................................A-33
LEAD PLANNING & ESTIMATING CODE ............................A-33 LEAD REPAIR WORK CENTER (LWC) ..............................A-33 LOCATION ...................................................A-34
MAINTENANCE INDEX PAGE NUMBER (MIP) ........................A-34 MAN-HOURS EXPENDED .........................................A-34 METER READING (M/R) ........................................A-34 METER READING (M/R) ........................................A-34
NAMEPLATE DATA ..............................................A-35 Downloaded from https://www.everyspec.com
p. 189
APPENDIX A-iii NEXT HIGHER ASSEMBLY ....................................... A-35 NORMALLY DONE BY ........................................... A-35
PERIODICITY ................................................ A-35 PERIODIC MAINTENANCE REQUIREMENT ........................... A-35 PRE ARRIVAL/ARRIVAL CONFERENCE ACTION/REMARKS .............. A-36 PRIORITY (PRI) (enter....................................... A-36
QUALITY ASSURANCE REQUIREMENTS ............................. A-37 QUANTITY ................................................... A-37
RATE ....................................................... A-37 RECORD IDENTIFICATION NUMBER (RIN) ......................... A-37 REMARKS/DESCRIPTION ........................................ A-37 REMARKS/SKETCHES ........................................... A-38 REPAIR ACTIVITY UIC (e...................................... A-38 REPAIR WORK CENTER (RWC) ................................... A-39 R/M (Maintenance Indicator) ................................ A-39
S (Safety Identifier) ...................................... A-39 SAFETY HAZARD .............................................. A-39 SCHEDULED COMPLETION DATE .................................. A-40 SCHEDULED START DATE ....................................... A-40 SCREENING ACTION ........................................... A-40 SCREENING (IUC) ............................................ A-41 SCREENING (TYCOM) (ent...................................... A-41 SECAS OFFICE USE (en........................................ A-42 SECOND CONTACT/SUPERVISOR .................................. A-42 SELECTED EQUIPMENT LIST .................................... A-42 SERVICE APPLICATION CODE (SAC) ............................. A-42 SHIP'S FORCE MAN-HOURS (S/F MHRS) .......................... A-42 SHIP'S FORCE MAN-HOURS EXPENDED (S/F MHRS. EXP.) ........... A-42 SHIP'S FORCE MAN-HOURS REMAINING (S/F MHRS. REM.)........... A-43 SHIP'S NAME ................................................ A-43 SHIP'S UNIT IDENTIFICATION CODE (UIC)....................... A-43 SPECIAL DATA ............................................... A-43 SPECIAL PURPOSE ............................................ A-43 SPECIAL REQUIREMENTS ....................................... A-44 STATUS (STA) ............................................... A-45 SUFFIX ..................................................... A-45
TASK ....................................................... A-45 TECHNICAL DOCUMENTATION (en................................. A-45 TECHNICAL MANUAL (TM) NUMBER ............................... A-45 TROUBLE ISOLATION (TI) ..................................... A-46 TYCOM AUTHORIZATION ........................................ A-46 TYCOM (SCREENING) .......................................... A-46 Downloaded from https://www.everyspec.com
p. 190
NAVSEAINST 4790.8B A-iv TYCOM SIGNATURE ............................................A-46 TYPE OF AVAILABILITY (T/A) .................................A-46
U (Mission Degrading) ......................................A-46 UNIT IDENTIFICATION CODE (UIC) .............................A-46
WHEN DISCOVERED (WND) ......................................A-47 WHEN DISCOVERED DATE .......................................A-47 WORK CENTER (WC) ...........................................A-47 WORK REQUEST ROUTINE .......................................A-47
YYMM ISSUED ................................................A-48
Downloaded from https://www.everyspec.com
p. 191
Downloaded from https://www.everyspec.com
p. 192
NAVSEAINST 4790.8B A-1 APPENDIX A
DATA ELEMENT DESCRIPTIONS AND VALIDATION SPECIFICATIONS
A-1 PURPOSE This appendix identifies the data elements used for 3-M documentation and reporting, and provides a complete listing of the data elements and their descriptions. This appendix also includes the data element specifications used for 3-M reporting. Only the core 3-M data elements have been included; however, the use of additional data elements may be allowed if they support specific TYCOM, Program Manager, or OPNAV requirements. A-2 OBJECTIVE The objective of this appendix is to ensure that 3-M data requirements are explicitly understood and followed. Divided into two sections, the validation specification portion can be used to:
a. Provide a means for organizational and intermediate level personnel to document information that is correct and complete.
b. Establish data element requirements for all 3-M ADP systems, including systems that interface with 3-M.
c. Provide a means for personnel conducting 3-M validations to ensure that 3-M data specifications are being followed.
d. Establish requirements for reporting 3-M maintenance data.
Downloaded from https://www.everyspec.com
p. 193
DATA ELEMENT DEN MAINTENANCE TYPE LENGTH ENTRY TYPE VALIDATION SPECIFICATIONS Action Taken F968 2K 2 E 1. Mandatory 2. Must be left-justified. 3. For 4790/2K, first character must be 0, 1, 2, 3, 4, 7, 8, or 9. For action taken codes 1, 2, and 3, the second character codes A, B, C, M, or T can be used. For action taken code 7, the second character codes A, B, C, D, or E can be used. For action taken code 9, the second character codes A, B, C, D, E, F, G, H, I, or J can be used. Action Taken F968 CK 2 E 1. Mandatory. 2. Must be left-justified. 3. For 4790/CK, must be 1, 2, 3 with or without the second character A, B, C, M, or T.4. For Alteration CK, must be 5A, 5B, 5C, or 5D. Active Maintenance Time F943 2K/CK 3 N 1. Optional. 2. Mandatory for SEL reporting Allowance Parts List/Allowance Equipage List (APL/AEL) D008G 2K/CK 11 E 1. Mandatory. 2. Must not be blank, not all zeros, and no imbedded blanks. 3. Must be the APL/AEL Number, "NOTLISTED", or "NA". Downloaded from https://www.everyspec.com
p. 194
DATA ELEMENT DEN MAINTENANCE TYPE LENGTH ENTRY TYPE VALIDATION SPECIFICATIONS Alterations (Configuration Changes) E319 2K/CK 14 E 1. Optional. 2. For SHIPALT, pos. 1 & 2 must be SA. Pos. 3-6 is ship type. Pos. 7-13 is alteration number. Pos. 14 is title code. 3. For all other alteration types, pos. 1 & 2 must be OA, BA, FC, MA, SI, EC, HI, TY, TD, SP, SC, TR, EP, MO, or AR. Pos. 3 is blank. Pos. 4-14 is alteration number. Assist Repair Work Center E902A 2K/2P 4 E 1. Optional. Assist Repair Work Center Estimated Man- Hours (Asst. Est. MHRS) E902A 2K/2P 4 E 1. Optional. Automated Integrated Language System Identification Number (AILSIN) E129 2K/CK 12 E 1. Optional. Available on Board(Yes/No) --- 2K 1 A 1. Mandatory only if the "Blueprints, Technical Manuals, etc." data element is filled. 2. Must be an "X". Blueprints, Technical Manuals, etc. --- 2K 32 E 1. Optional. Cause F964C 2K 1 N 1. Mandatory. 2. Must be 1, 2, 3, 4, 5, 6, 7, or 0.
Downloaded from https://www.everyspec.com
p. 195
DATA ELEMENT DEN MAINTENANCE TYPE LENGTH ENTRY TYPE VALIDATION SPECIFICATIONS Completion Date --- 2K/CK * N 1. Mandatory. 2. Must be greater than deferral date.* Length is determined by the date format. Component Action F968C CK 1 A 1. Mandatory. 2. If reporting a configuration maintenance action, must be R, I, or M. 3. If reporting a configuration file correction, must be A, D, or C. Component Identification F940B CK 15 E 1. Optional. Component Noun Name --- CK 26 E 1. Mandatory. 2. For HM&E equipment, enter the noun name. 3. For electronics equipment, enter the AN type designator or commercial model number. 4. For ordnance equipment, enter the system/equipment nomenclature, followed by the Mark and Mod numbers. Component Serial Number --- CK 15 E 1. Mandatory. 2. For equipment without a serial number, enter "NONE". CSMP Summary F905D 2K 30 E 1. Mandatory Date Completed --- 2K * N *. Length is determined by the date format Date of Estimate --- 2K * N *. Length is determined by the date format Deadline Date F964F 2K * N 1. Optional. 2. Length is determined by the date format. Downloaded from https://www.everyspec.com
p. 196
DATA ELEMENT DEN MAINTENANCE TYPE LENGTH ENTRY TYPE VALIDATION SPECIFICATIONS Deferral Date F964E 2K * N 1. Mandatory. 2. Length is determined by the date format. Deferral Reason F964D 2K 1 N 1. Mandatory. 2. Must be 1, 2, 3, 4, 5, 6, 7, 8, 9, or 0. Departure Test Required --- 2P 1 A 1. Optional. 2. If used, must be an "X". Dry Dock Required --- 2P 1 A 1. Optional. 2. If used, must be an "X". Engineering Operational Sequencing System (EOSS) --- CK 15 E 1. Optional. 2. Not required for Electronics or Ordnance configuration change actions. Equipment Identification Code D008D 2K/CK 7 E 1. Mandatory. Downloaded from https://www.everyspec.com
p. 197
DATA ELEMENT DEN MAINTENANCE TYPE LENGTH ENTRY TYPE VALIDATION SPECIFICATIONS Equipment Noun Name F940 2K/CK 16 E 1. Mandatory. 2. If the maintenance action is a SHIPALT, enter the equipment noun name from the SHIPALT record. Otherwise, enter the equipment nomenclature/description of the equipment or system on which the maintenance was performed. 3. For HM&E equipment, enter the noun name. 4. For electronics equipment, enter the AN type designator or commercial model number. 5. For ordnance equipment, enter the system/equipment nomenclature, followed by the Mark and Mod numbers. Estimated Man- Days --- 2K/2P 5 N 1. If the estimate is less than one, enter "1". Estimated Man- Days Cost --- 2K/2P 7 N 1. If no estimate, enter "0". Estimated Man- Hours G902A 2K/2P 4 N 1. If no estimate, enter "0". Estimated Material Costs G902M 2K/2P 6 N 1. If no estimate, enter "0". Estimated Total Cost --- 2K/2P 7 N 1. If no estimate, enter "0". Downloaded from https://www.everyspec.com
p. 198
DATA ELEMENT DEN MAINTENANCE TYPE LENGTH ENTRY TYPE VALIDATION SPECIFICATIONS Final Action (IMA only) --- 2K 2 E 1. Mandatory. 2. Must be left-justified. 3. First character must be 0, 1, 2, 3, 4, or 7. For action taken codes 1, 2, and 3, the second character codes A, B, C, M, or T can be used. For action taken code 7, the second character codes A, B, C, D, or E can be used. 4. For alteration reporting, must be 5A, 5B, 5C, or 5D. 5. For rejected work request, must be 6A- 6I. First Contact F804 2K 18 E 1. Mandatory. Hull Number --- 2K/CK/2P 11 E 1. Optional.
Identification/ Equipment Serial Number --- 2K 15 E 1. Mandatory. INSURV Number D912 2K 7 E 1. Optional. Integrated Priority F802 2K 5 N 1. Optional.
IUC Screening F949 2K 2 E 1. Optional. 2. If used, must be 1, 2, 3 with or without the second character A, S, or M; 4; 5, 5A-5F; 6, 6A-6E; or 8. IUC/Repair Activity/TYCOM Remarks --- 2P 180 E 1. Optional. Downloaded from https://www.everyspec.com
p. 199
DATA ELEMENT DEN MAINTENANCE TYPE LENGTH ENTRY TYPE VALIDATION SPECIFICATIONS Job Control Number (JCN) E349 2K/CK/2P 13 E 1. Mandatory. 2. This data element is made up of the UIC (A002), Work Center (E128), and JSN (E349C). Job Description/ Remarks --- CK 120 E 1. Mandatory. Job Order Number G679 2K 10 E Job Sequence Number (JSN) E349C 2K/CK/2P 4 N 1. Mandatory. Key Event F934 2P 4 E 1. Optional. Key Operation F939 2P 2 N 1. Optional. Lead Planning &Estimating Code --- 2K 4 E 1. Optional. Lead Repair Work Center (LWC) E902D 2K/2P 4 E 1. Mandatory. Location E900A 2K/CK 20 E 1. Mandatory. Maintenance Index Page Number (MIP) E130 CK 15 E 1. Optional. Man-Hours Expended --- 2K 4 N 1. Mandatory. 2. Cannot be blank. Meter Reading --- 2K 5 N 1. Optional. Meter Reading Indicator D916G CK 1 A 1. Optional. 2. If used, must be "X". Nameplate Data F940C CK 120 E 1. Mandatory for installation, and addition. 2. Optional for removal, modification, change, and deletion. Next Higher Assembly F940D CK 21 E 1. Optional. Normally Done By --- 2P 1 A 1. Optional. Downloaded from https://www.everyspec.com
p. 200
DATA ELEMENT DEN MAINTENANCE TYPE LENGTH ENTRY TYPE VALIDATION SPECIFICATIONS Periodic Maintenance Requirement --- 2P 12 E 1. Optional. Periodicity --- 2P 3 E 1. Optional. Post-Overhaul Test Required --- 2P 1 A 1. Optional. 2. If used, must be an "X". Pre Arrival/Arrival Conference Action/Remarks --- 2K 56 E 1. Optional. Pre-Overhaul Test Required --- 2P 1 A 1. Optional. 2. If used, must be an "X". Priority C904A 2K 1 N 1. Mandatory. 2. Must be 1, 2, 3, or 4. Quality Assurance Requirements --- 2P 12 A 1. Optional. Quantity --- CK 3 N 1. Mandatory. R/M (Maintenance Indicator) D912E 2K 1 A 1. Optional. 2. If used, must be "M" or "R". Rate F804A 2K 4 E Mandatory. Record Identification Number (RIN) E221 CK 5 E 1. Mandatory for deletion, removal, and modification. 2. Optional for installation and addition. Remarks/ Description F905 2K/CK 1200 E 1. Mandatory. Repair Activity UIC A002P 2K 5 E 1. Optional. Repair Work Center E902A 2K 4 E 1. Optional. Downloaded from https://www.everyspec.com
p. 201
DATA ELEMENT DEN MAINTENANCE TYPE LENGTH ENTRY TYPE VALIDATION SPECIFICATIONS S (Safety Identifier) D912B 2K 1 A 1. Optional. 2. If used, must be "S". Safety Hazard C921A 2K 1 E 1. Optional. 2. Must be 1, 2, 3, 4, 5, 0. Code 6 thru 9 may be locally assigned by TYCOMs for additional safety codes required. Scheduled Completion Date --- 2K/2P * N 1. Optional. *. Length is determined by the date format. Scheduled Start Date --- 2K/2P * N 1. Optional. *. Length is determined by the date format. Second Contact/ Supervisor F804B 2K 18 E 1. Optional. Service Application Code E010A CK 10 E 1. Optional. Ship's Force Man-Hours (S/F MHRS) F808B 2K 4 N 1. Mandatory. Ship's Force Man-Hours Expended (S/F MHRS EXP) F808 2K/CK 4 N 1. Mandatory. Ship's Force Man-Hours Remaining (S/F MHRS REM) F808A 4 N(*) 1. Optional. *. If TYCOM allows an automatic close out of the deferral by the IMA, enter "AUTO". Special Interest --- 2P 1 A 1. Optional. 2. If used, must be an "X". Special Purpose A F801 2K 2 E 1. Optional. 2. If used, enter the Key Event code. Downloaded from https://www.everyspec.com
p. 202
DATA ELEMENT DEN MAINTENANCE TYPE LENGTH ENTRY TYPE VALIDATION SPECIFICATIONS Special Purpose B F801 2K 2 A 1. Optional. 2. If used, must be SS. Special Purpose C F801 2K 2 E 1. Optional. 2. If used, must be L1. Special Purpose D F801 2K 2 N 1. Optional. 2. If used, must be 08. Special Purpose E F801 2K 2 A 1. Optional. 2. If used, must be RC Special Purpose F F801 2K 2 A 1. Optional. 2. If used, must be DD. Special Purpose G F801 2K 2 A 1. Optional. 2. If used, must be NC or NP. Special Purpose H F801 2K 2 E 1. Reserved for future use. Special Purpose I F801 2K 2 E 1. Reserved for future use. Special Purpose J F801 2K 2 E 1. Reserved for future use. Special Purpose K F801 2K 2 E 1. Reserved for future use. Special Purpose L F801 2K 2 E 1. Optional. 2. If used, enter the code assigned to the visiting activity. Downloaded from https://www.everyspec.com
p. 203
DATA ELEMENT DEN MAINTENANCE TYPE LENGTH ENTRY TYPE VALIDATION SPECIFICATIONS Special Requirements --- 2P * E 1. Optional. 2. If used, refer to Key Event, Special Interest, Dry Dock Required, Pre- Overhaul Test Required, Post-Overhaul Test Required, or Departure Test Required Codes for allowable codes and values. *. Length is determined by the codes entered. Status F964B 2K 1 N 1. Mandatory. 2. Must be 1, 2, 3, or 0. Suffix D912D 2K 2 E 1. Optional. Task --- 2P 12 E 1. Optional. Technical Documentation --- 2P 28 E 1. Optional. Technical Manual Number --- CK 32 E 1. Optional. Trouble Isolation F980 2K 1 N 1. Optional. TYCOM Screening F949A 2K 2 E 1. Optional. 2. If used, must be 1, 2, 3, with or without the second character A, S, or M; 4; 5A-5F; 6, 6A-6E; 8; or 9. Type Availability F927 2K 1 N 1. Mandatory. 2. Must be 1, 2, 3, 4, or 0. U (Mission Degrading) D912C 2K 1 A 1. Optional. 2. If used, must be "U". Unit Identification Code (UIC) A002 2K/CK/2P 5 E 1. Mandatory. 2. No imbedded blanks. Downloaded from https://www.everyspec.com
p. 204
DATA ELEMENT DEN MAINTENANCE TYPE LENGTH ENTRY TYPE VALIDATION SPECIFICATIONS When Discovered Code F964 2K 1 N 1. Mandatory. 2. Must be 1, 2, 3, 4, 5, 6, 7, 8, 9 or 0. When Discovered Date F964A 2K * N Mandatory. *. Length is determined by the date format. Work Center E128 2K/CK/2P 4 E Mandatory for installation or addition. Optional for removal, modification, deletion, or change. Work Center Responsible for Equipment (WCRE) E128 CK 4 E 1. Mandatory for installation or addition. 2. Optional for removal, modification, deletion, or change. Work Request Routine --- 2K 5 E 1. Optional. 2. If used, must be either the Expanded Ship Work Breakdown Structure, Ship Work Breakdown Structure, Ship Work Authorization Boundary, or Ship Work Line Item Number as directed by the TYCOM. YYMM Issued --- 2P 4 N 1. Optional.
Downloaded from https://www.everyspec.com
p. 205
Downloaded from https://www.everyspec.com
p. 206
NAVSEAINST 4790.8B A-13 DATA ELEMENT DESCRIPTIONS
Following the validation specification section is an alphabetical listing of the authorized 3-M data elements. This listing provides a short definition of each data element along with allowable codes and values where applicable.
DATA ELEMENTS
ACCEPTED BY (entered on 2K) The signature/name and rank/rate of the person authorized by the tended ship to verify the acceptability of work performed. This entry is mandatory when reporting completion of a previously deferred maintenance action. The work center supervisor must approve all maintenance actions not requiring assistance from an outside work center; the work center supervisor's approval will be recorded when the maintenance action is documented. ACTION TAKEN (ACT. TKN.) (entered on 2K and CK) A code to describe the maintenance action taken. Select the code which best describes the action taken to complete the maintenance. When recording these codes, start in the left- justified position of the field. The first character is to be chosen from the list below; the second character is free-form and is to be recorded as specified by the TYCOM.
MAINTENANCE ACTION: For maintenance action reporting, the following action codes can be used:
Code Description
1 Maintenance Action Completed; Parts Drawn from Supply 2 Maintenance Action Completed; Required Parts Not Drawn from Supply (local manufacture, pre-expended bins, etc.) 3 Maintenance Action Completed; No Parts Required
NOTE:
The following second character codes can be used with the above Action Taken codes 1, 2, or 3 as directed by the TYCOM:
A Maintenance Requirement Could Have Been Deferred B Maintenance Requirement Was Necessary C Maintenance Requirement Should Have Been Done Sooner M High Cost Repairs Downloaded from https://www.everyspec.com
p. 207
APPENDIX A-14 T The Equipment Being Reported Had a Time Meter
Code Description
4 Canceled (When this code is used, the deferral will be removed from the CSMP. This code is not to be used with INSURV, safety, or priority 1 or 2 deferrals screened for accomplishment by the TYCOM or IUC.) 7 Maintenance Action Completed; 2-M (Miniature/Microminiature Electronic Modules) Capability Utilized.
NOTE:
The following second character codes can be used with Action Taken Code 7 to better describe the action taken:
A Parts Drawn from Supply Utilized B Parts Not Drawn from Supply Utilized C Automatic Test Equipment (ATE) Utilized D ATE and Parts Drawn from Supply Utilized E ATE and Parts Not Drawn from Supply Utilized
Code Description
8 Periodic Time Meter/Cycle Counter reporting. (This code is not applicable to the "FINAL ACTION" code reported by the repair activity.) 9 Maintenance Action Completed; 3M Fiber Optic Repair
NOTE:
The following second character codes can be used with Action Taken Code 9 to better describe the action taken:
A FOTE, multimode ST MQJs utilized B FOTE, multimode heavy duty MQJs utilized C FOTE, multimode rotary mechanical splice MQJs utilized D FOTE, single mode ST MQJs utilized E FOTE, single mode heavy duty MQJs utilized F FOTE, multimode specialty MQJs utilized G FOTE, single mode specialty MQJs utilized H FOTE, not available Downloaded from https://www.everyspec.com
p. 208
NAVSEAINST 4790.8B A-15 I Standard MQJs not available J Specialty MQJs not available
Code Description
0 None of the Above
CONFIGURATION CHANGE: For configuration change reporting, the following action codes can be used:
Code Description
1 Maintenance Action Completed; Parts Drawn from Supply 2 Maintenance Action Completed; Required Parts Not Drawn from Supply (local manufacture, pre-expended bins, etc.) 3 Maintenance Action Completed; No Parts Required
NOTE:
The following second character codes can be used with the above Action Taken codes 1, 2, or 3 as directed by the TYCOM:
A Maintenance Requirement Could Have Been Deferred B Maintenance Requirement Was Necessary C Maintenance Requirement Should Have Been Done Sooner M High Cost Repairs T The Equipment Being Reported Had a Time Meter 5A Partially Completed Alteration 5B Fully Completed Alteration 5C Fully Completed Equivalent to Alteration 5D Alteration Directive Not Applicable
NOTE:
If there is an entry in the Alterations field of a deferred maintenance action (2K), a code "5", including the applicable suffix ("A-D"), must be entered in the "FINAL ACTION" field. ACTIVE MAINTENANCE TIME (entered on 2K and CK) The total clock hours, to the nearest whole hour, during which ship's force maintenance was performed. This should show actual time for troubleshooting, but not include delays. Downloaded from https://www.everyspec.com
p. 209
APPENDIX A-16 AILSIN (see data element "AUTOMATED INTEGRATED LANGUAGE SYSTEM IDENTIFICATION NUMBER (AILSIN))" ALLOWANCE PARTS LIST/ALLOWANCE EQUIPAGE LIST (APL/AEL) (entered on 2K and CK) The APL/AEL relates to a set of characteristics which identify a particular system, equipment, or component. The Master Index of APLs/AELs (MIAPL) lists what APLs/AELs are available and cross references various equipment identification numbers to an existing APL/AEL (e.g., "992179236" for an APL, and "2- 260034096" for an AEL).
For manual reporting, on equipment not listed in the Coordinated Shipboard Allowance List (COSAL), enter "NOT LISTED" in the APL/AEL field. For maintenance actions that are not equipment related (e.g., requests for cruise box manufacture, printing services, etc.), enter "NA" in this field. ALTERATION IDENTIFICATION (CONFIGURATION CHANGES) (entered on 2K and CK) An alteration is a change in design, material, number, location, or relationship of an assembly's component parts. Some alteration categories are:
SHIPALT. Enter the alteration identification exactly as it appears on the Ship Alteration (SHIPALT) Record (i.e., SA, ship type, and SHIPALT number). The alteration prefix code "SA" is entered in the first two positions, followed by the ship type, with the alteration number beginning in the 7th position. Enter the title code shown in the authorizing directive in the right- justified position of the field.
ORDALT. Enter and left-justify the alteration identification code "OA". Leave position 3 blank; follow with the alteration number in position 4. Record the ORDALT number from the upper right-hand corner of the authorizing directive.
FIELD CHANGE. Enter "FC" in the two left-justified positions. Leave position 3 blank; place the numeric characters listed in the FC Bulletin in positions 4 and 5.
ALTERATION REQUEST. May be originated by a ship to request an alteration design. Enter and left-justify "AR", then a blank space, then any number the ship assigns for its own control.
Downloaded from https://www.everyspec.com
p. 210
NAVSEAINST 4790.8B A-17 OTHER ALTERATIONS. Enter the appropriate alteration prefix from the following list in the two left-justified positions, leave position three blank, and identify the alteration directive in the remaining positions:
BA = BOAT ALTERATION MA = MACHINERY ALTERATION SI = SYSCOM COMMAND INSTRUCTION EC = ENGINEERING CHANGE HI = HABITABILITY TY = TYCOM DIRECTION TD = TECHNICAL DIRECTIVE SP = STRATEGIC SYSTEMS PROJECT OFFICE ALTERATION SC = SERVICE CHANGE TR = TRIDENT ALTERATION EP = ENGINEERING CHANGE PROPOSAL MO = CRYPTO EQUIPMENT MODIFICATION ASSIST REPAIR WORK CENTER (ASST. REPAIR W/C) (entered on 2K and 2P) The 3- or 4-character code of the first work center assigned to assist the lead work center on the job being planned. The code is always left justified in the field. On the 2K, if more than one assist work center is required, fill in another 2K. Only two assist work centers (two supplemental 2K continuation sheets) can be accommodated when a 2K is used as a planning document by an IMA. ASSIST REPAIR WORK CENTER ESTIMATED MAN-HOURS (ASST EST MHRS) (entered on 2K) The total number of estimated man-hours required by the assist work center of the repair activity to complete its portion of the job. AUTOMATED INTEGRATED LANGUAGE SYSTEM IDENTIFICATION NUMBER (AILSIN) (entered on CK) The number used to identify the functional/hierarchical relationship of the ship, system, and equipment configuration records. Current numbering schemes are AILSIN, Configuration Identification Number (CIN) and Functional Group Code (FGC). BLUEPRINTS, TECHNICAL MANUALS, ETC. (entered on 2K) Used to list technical material (blueprints, technical manuals, plans, etc.), that might be of assistance to the repair activity providing assistance. Downloaded from https://www.everyspec.com
p. 211
APPENDIX A-18 CAUSE (CAS) (entered on 2K) The code best describing the cause of the failure or malfunction when need for maintenance was first discovered. When more than one cause contributed to the failure or malfunction, select the primary or overriding one (this field provides valuable data to the equipment manager; without it, only the fact that the equipment failed is known). Maintenance personnel must use their best judgment in determining the cause of failure.
Code Descriptions
1 ABNORMAL ENVIRONMENT. Exposure to conditions more extreme than those reasonably expected in the normal shipboard environment (e.g., electrical equipment sprayed by salt water, or compartment flooded). 2 MANUFACTURER/INSTALLATION DEFECTS. Material not assembled or manufactured per specifications, or installed improperly by IMA or Depot (e.g., motor with open circuit armature). 3 LACK OF KNOWLEDGE OR SKILL. Failure or malfunction of the equipment due to insufficient training, experience, or physical coordination of the operator, maintainer, or other personnel (e.g., not knowing equipment limitations such as the danger of a low speed wheel on a high speed grinder). 4 COMMUNICATIONS PROBLEM. A breakdown in the passing, receiving, or understanding of information (e.g., failure to hear or receive a complete message due to noise or mechanical or electrical interference). 5 INADEQUATE INSTRUCTION/PROCEDURE. The instruction or procedures guide has omissions, errors, ambiguities, or other deficiencies (e.g., technical manual omits lubricant type). 6 INADEQUATE DESIGN. Material manufactured and installed per specifications failed prematurely during normal usage under normal environmental conditions (e.g., steam piping orientation precludes adequate draining during warm-up). 7 NORMAL WEAR AND TEAR. Material requires replacement after long service and/or as a result of PMS (e.g., pump wear rings replaced during PMS). 8 CORROSION CONDITION. 0 OTHER OR NO MALFUNCTION. Needs to be explained in the "Remarks" field. Examples: 1) Fatigue or physical stress brought on by prolonged work periods or excessive heat, humidity, or noise. 2) Desire to save time and effort by taking shortcut and jury-rigging equipment. 3) Malfunction occurred when installing a field change to improve Downloaded from https://www.everyspec.com
p. 212
NAVSEAINST 4790.8B A-19 Code Descriptions
equipment effectiveness, or when the cause resulted from a personnel oriented deficiency affecting safety due to fatigue, etc. COMMANDING OFFICER'S SIGNATURE (entered on 2K) Shows approval by the commanding officer or authorized representative. Required on all deferrals for outside assistance. COMPLETED BY (entered on 2K) The signature and rate of the senior person actively engaged in the job at the lead work center. The senior person on the job will be identified for all maintenance actions not requiring assistance from an outside work center. COMPLETED DEFERRAL (COMP DEFL) (entered on CK) Indicates the completion of a previously deferred job. COMPLETED MAINTENANCE ACTION, NO DEFERRAL (COMP M/A NO DEFL) (entered on CK) Indicates a completed maintenance action with no prior deferral. COMPLETION DATE (entered on 2K and CK) The Julian date the maintenance action was completed. COMPONENT ACTION (CA) (entered on CK) Indicates if the identified component was removed (R), installed (I), or modified (M). Use the codes R, I, or M as appropriate. If reporting a configuration record change, use the code "A" for addition, "D" for deletion, and "C" for correction. COMPONENT APL/AEL (entered on CK) The APL/AEL of the component or equipment identified. If unsure of the correct APL/AEL for the equipment, entry may be left blank, and assistance requested by the supply department. COMPONENT IDENTIFICATION (entered on CK) The local numbering system used to identify equipment, (e.g., Station Number: "1A BOILER" or Valve Mark: "ASW 25"). A description of the component may be entered.
For electronic and combat systems equipment, the entry is optional if the component serial number field has an entry. Downloaded from https://www.everyspec.com
p. 213
APPENDIX A-20 COMPONENT NOUN NAME (entered on CK) Identifies the component. If the action being reported is the accomplishment of an equipment alteration (Field Change, Engineering Change, etc.), the component is defined as the equipment level addressed in the alteration directive, usually the major equipment or system level; otherwise, the component is defined as the lowest unit, type designator, or assembly that has its own configuration identity. This component may or may not have its own APL. Example of an equipment and related components:
System or Equipment: AN/WRT-2 Component: PP-2222/WRT-2 Component: C-2764/WRT-2
If several components are removed and installed in a single maintenance action (identified by one JCN), continuation pages may be used to report the component changes. If necessary, overflow data from the component noun name can be placed in the nameplate data field. COMPONENT SERIAL NUMBER/IDENTIFICATION/EQUIPMENT SERIAL NUMBER (entered on CK) Serial number of the component. If a serial number is entered, the QUANTITY field must be one ("1"). For equipment without a serial number, enter "NONE". CONFIGURATION FILE CORRECTION (CONF FILE CORR) (entered on CK) A data element field that indicates that the report is being submitted to correct erroneous configuration records (no equipment maintenance action involved). CONTINUATION FOR (entered on 2L) Identifies the maintenance action to which the supplemental information pertains. CONTINUATION SHEET (entered on 2K) Indicates remarks are continued on a second, third, or fourth form (2K). For manual reporting enter an "X". CSMP SUMMARY (entered on 2K) A condensed description of the problem. This entry is limited to 30 characters. The CSMP summary conveys to management the significance of the JCN (maintenance action). The CSMP summary is displayed on management reports, as opposed to the entire Downloaded from https://www.everyspec.com
p. 214
NAVSEAINST 4790.8B A-21 narrative of the "REMARKS" field which is not. If continuation sheets are used, the summary line will appear on the first page. DATE (entered on 2L) The Julian date the document is prepared. DATE COMPLETED (entered on 2K) The Julian date the work request is completed and signed off by the requesting ship. DATE OF ESTIMATE (entered on 2K) The Julian date the assisting activity completed the planning of the maintenance action. DEADLINE DATE (entered on 2K) The latest possible Julian date that outside assistance and ship's force work must be completed as determined by the originator. This entry may be used to indicate a completion date required to meet an operational commitment, or to allow another job to start. This is an optional entry. DEFERRAL DATE (DEFER. DATE) (entered on 2K) The Julian date of when the maintenance action was deferred. An example of a deferral action on 22 April 1994 would be: "4112". DEFERRAL REASON (DFR) (entered on 2K) A code which best describes the reason maintenance could not be performed at the time of deferral. Acceptable codes are:
Code Deferral Reason
1 DUE TO SHIP'S FORCE WORK BACKLOG/OPERATIONAL PRIORITY. Within capability of ship's force to accomplish, but unable to do so because of ship's overall workload or operations. 2 LACK OF MATERIAL. Within capability of ship's force, but unable to accomplish due to lack of parts, tools, test equipment, etc., that are specified for use in repair work by the technical manual or drawing. NOTE: List the unavailable parts, tools, or test equipment and the technical manual and/or equipment drawing in Remarks. 3 NO FORMAL TRAINING ON THIS EQUIPMENT. Should be within capability of ship's force, but personnel responsible have no formal training in the maintenance of the equipment. 4 FORMAL TRAINING INADEQUATE FOR THIS EQUIPMENT. Should be Downloaded from https://www.everyspec.com
p. 215
APPENDIX A-22 Code Deferral Reason
within capability of ship's force, and personnel responsible have received formal training, but the training is considered inadequate. 5 INADEQUATE SCHOOL PRACTICAL TRAINING. Should be within capability of ship's force, and personnel responsible have received formal training, but practical maintenance aspects of training are considered inadequate. 6 LACK OF FACILITIES/CAPABILITIES. The ship is not allowed shop equipment or other facilities to accomplish; work is otherwise beyond expected capability of ship's force to accomplish. 7 NOT AUTHORIZED FOR SHIP'S FORCE ACCOMPLISHMENT. Directives of higher authority specify that the job will be done by other than ship's force. 8 FOR SHIP'S FORCE OVERHAUL OR AVAILABILITY WORK LIST. For jobs to be done by ship's force during forthcoming overhaul or availability. 9 LACK OF TECHNICAL DOCUMENTATION. Should be within capability of ship to accomplish but unable to do so because technical manuals, blueprints, drawings, etc., are not available. 0 OTHER - OR NOT APPLICABLE. Explain in Remarks. DEPARTMENT INITIALS (entered on 2K) The initials of the department head indicating the document was screened. DIVISION INITIALS (entered on 2K) The initials of the division officer indicating the document was screened. ENGINEERING OPERATIONAL SEQUENCING SYSTEM (EOSS) (entered on CK) The Document Code and Control Number of the primary EOSS procedure that is affected by the configuration change. EQUIPMENT IDENTIFICATION CODE (EIC) (entered on 2K and CK) A 7-character code that identifies the equipment. The first position identifies the system; the first and second characters together identify the subsystem; the third and fourth together identify the equipment category in that system. The remaining three digits provide greater definition of the applicable equipment part and are useful to the engineer. Where the EIC is known to more than four digits, it should be recorded at that Downloaded from https://www.everyspec.com
p. 216
NAVSEAINST 4790.8B A-23 level. EICs are listed in the SCLSIS Index Report or Ships' 3-M Reference CD.
If an equipment is not listed in the SCLSIS Index Report or the Ships' 3-M Reference CD, but it can be identified to the subsystem, use the subsystem identification, followed by two zeros. Example: An equipment identified as TRANSCEIVERS- COMMUNICATIONS, but not in the SCLSIS Index Report or the Ships' 3-M Reference CD, would be reported as "QD". If the equipment is identified only to the system, use the system identification, followed by three zeros. EQUIPMENT NOUN NAME (entered on 2K and CK) The nomenclature/description of the equipment. This is the same nomenclature assigned to the equipment EIC. Standard abbreviations may be used. When recording the accomplishment of a SHIPALT, use the noun name from the record. If the maintenance action affects several components or systems, enter the name/designator of the highest assembly affected.
For HM&E, use the noun name (e.g., "MOTOR GENERATOR").
For electronics equipment, use the Army/Navy (AN) designation, or commercial model number (e.g., "AN/SPS-40D", "CY-4727/SPA- 25", and "403-B").
For combat systems equipment, enter the nomenclature followed by the Mark (MK) and Modification (MOD), separated by "/" (e.g., "LAUNCH SYSTEM 36/1"). ESTIMATED MAN-DAYS (entered on 2K and 2P) Used by the repair activity, the total man-day estimate for all involved work centers to complete the job (if estimate is less than 1, enter "1"). ESTIMATED MAN-DAYS COST (entered on 2K and 2P) Used by the repair activity, the total man-day cost estimate for all involved work centers to complete the job (Estimated Man-Day entry x man-hour rate x 8 (working hours per day)). ESTIMATED MAN-HOURS (EST. MHRS.) (entered on 2K and 2P) The man-hours estimated by the lead work center of the repair activity to complete the job. Downloaded from https://www.everyspec.com
p. 217
APPENDIX A-24 ESTIMATED MATERIAL COSTS (entered on 2K and 2P) Used by the repair activity, the total material costs estimated to complete the job. ESTIMATED TOTAL COST (entered on 2K and 2P) Used by the repair activity, the total cost estimated to complete the job (Estimated Man-Day Cost + Estimated Material Costs = Estimated Total Cost). FINAL ACTION (entered on 2K) A code that describes the final action taken by the repair activity to complete the job. Refer to the data element "ACTION TAKEN" used for maintenance action reporting for a complete list of codes. Action Taken code "8" is not applicable. In addition, the following codes can be used:
Code Descriptions
5A Partially Completed Alteration 5B Fully Completed Alteration 5C Fully Completed Equivalent to Alteration 5D Alteration Directive Not Applicable 6 Rejected Work Request (add suffix below for reason) A Ship's Force/Standard Stock Item B Excessive Shop Workload/Insufficient Availability C Lack of Skills D Lack of Facilities E Lack of Test or Calibration Equipment F Lack of Parts/Material G Lack of Documentation H Lack of Funds I Other (record the explanation in "Remarks") FIRST CONTACT/MAINTENANCE (MAN) (entered on 2K and 2L) The name of the senior person engaged in the maintenance action. HULL NUMBER (entered on 2K, CK, 2P and 2L) The ship type and hull number of the activity originating the maintenance action. Not required by activities other than ships. IDENTIFICATION/EQUIPMENT SERIAL NUMBER (entered on 2K) The identification or serial number (up to 12 characters) of the equipment or system on which maintenance is being deferred.
Downloaded from https://www.everyspec.com
p. 218
NAVSEAINST 4790.8B A-25 a. For electronics and combat systems equipment, use the Serial number from the equipment nameplate (e.g., for AN/SPS-10C Radar with serial number 48, use "48").
b. For HM&E, enter the ship's numbering system (e.g., for number 1A boiler, use "1A").
c. Where no specific identification or equipment serial number is given, or for photographic services, plaques, printing, cruise boxes, etc., enter "NA" (Not Applicable).
d. On items such as phones and fans, etc., list more than one item of the same type on a maintenance action; enter "VARIOUS".
e. If the serial number exceeds 12 characters, enter the words "SERIAL NUMBER" in the narrative, followed by the applicable number. IMA REPAIR WORK CENTER The lead work center at the IMA involved in the accomplishment of the maintenance. A 3- or 4-character code is used to uniquely identify the lead work center. Following is a list of the authorized IMA work center codes:
Repair W/C Code
Name
Abbreviated Name
Supply ID Code
01A MDCO MDCO 6D 01B ARRS ARRS 6D 01E SRA OIC SRA OIC Z0 02A Crane Services Crane Services 2S 03A OSH Office OSH Office 3H 03T Tender Repair Team Tender Repair Team 06A Tool Room Tool Room 6A 06B Portable Tools Portable Tools 6B 06M Preventive Maintenance Group Preventive Maint 6H 06N Nuclear Temp Services Nuclear Temp Serv 2T 08A Floating Dry Dock Floating Dry Dock DA 10A Repair Office/ARRS/MCO Repair Office 6D 10B Weapons Repair Office Weapon Rep Office AR 10C Non-Nuclear Planning Non-Nuclear Planning 6E 10D Nuclear Planning Nuclear Planning 6F Downloaded from https://www.everyspec.com
p. 219
APPENDIX A-26 Repair W/C Code
Name
Abbreviated Name
Supply ID Code
10E Technical Library Technical Library 6G 10J RO Non-IMA GT30 RO Non-IMA GT30 6D 10K WR Non-IMA GT30 WR Non-IMA GT30 AR 10L ROVSS ROVSS 6D 10N Nuclear Tech Library AW 10S Submarine Monitoring Maintenance and Support (SMMS) Performance Monitoring Team (PMT) SMMS (NAVSEA) 6J 11A Shipfitter Shipfitter 7A 17A Sheetmetal Sheetmetal 7B 25A Gas Manufacturing Gas Manufacturing 5A 25C CO2 Recharge and Repair CO2 Recharge/Repr 5C 25D General Engineering Service General Engnrg Svc 5D 26A Welding Shop Welding 7E 26B Nuclear Welding Nuclear Welding 7F 30A Contracted Planning & Estimating P&E 3D 31A Inside Machine Inside Machine 2A 31B Engraving Engraving 2B 31C Governor Injector Governor Injector 2C 31D Valve Repair and Test Valve 2D 31E Internal Combustion Engine Repair Intrnl Cmbstn Eng 2E 31F Hydraulics Repair Hydraulics 2F 31G Pump Repair Pump 2R 31H ACFT L & R ACFT L & R AX 31M Machinery R & R Machinery R & R AY 31T Gas Turbine Gas Turbine 2Q 31Z Metal Build-up Metal Build-up 2H 35A Optical Repair and Overhaul Optical 5E 35D Watch and Clock Shop Watch & Clock 5H 35E Typewriter Shop Typewriter 5J 37A Print Shop Print 31 38A Outside Machine Shop Outside Machine 2G 38B Ordnance Repair, Test, and Align Ordnance 5K 38C P-250 Pump Shop P-250 Pump Shop 1G 38D Valve Barge Valve Barge 1H 38N Nuclear Repair Nuclear Repair 2J Downloaded from https://www.everyspec.com
p. 220
NAVSEAINST 4790.8B A-27 Repair W/C Code
Name
Abbreviated Name
Supply ID Code
39A Photographic Shop Photographic 32 41A Boiler Inspection and Repair Boiler 2K 41B Boiler-Outside Repair Boiler-Outside Rpr 2L 51A Electrical Repair Electrical Repair 33 51B Outside Electrical Outside Electrical 34 51C Meter Calibration Meter Calibration 35 51E Battery Shop Battery 36 51F Gyro Inspection and Repair Gyro 37 51G Interior Communication Test and Repair IC Interior Commun 38 51H Cable Shop Cable 39 51N Nuclear Instruments Nuclear Instruments AU 56A Pipe Shop Pipe 7H 56B Refrigeration and Air Conditioning Repair and Test Refrig & Air Cond 2M 56C Flexible Hose Test and Repair Flexible Hose 7J 56N Nuclear Piping Nuclear Piping 7X 57A Lagging and Pipe Covering Inspection and Repair Lagging/Pipe Cover 7K 57B Rubber and Plastic Forming Shop Rubber and Plastic 7L 64A Woodworking and Pattern Making Shop Woodworking & Pattern 7M 64D Drafting Shop Drafting 7Q 64E Key and Lock Shop Key and Lock 5M 67A Electronics Test, Repair, and Alignment Electronics 41 67B Electronics Calibration Lab Electronic Cal Lab 42 67C Crypto Repair and Test Crypto Repair 43 67D Teletype Repair Teletype Repair 44 67E Fire Control Test and Repair Fire Control AD 67F Radiac Calibration and Repair Radiac Calibration 5N 67G Sonar Test, Repair, and Alignment Sonar 5P 67H Antenna Test, Repair, and Install Antenna 45 67I MSRA MSRA Z0 Downloaded from https://www.everyspec.com
p. 221
APPENDIX A-28 Repair W/C Code
Name
Abbreviated Name
Supply ID Code
67J Digi Inert Nav Aid Test and Repair Digi Inert Nav Aid AQ 67K Weapons Test Equipment, Repair and Calibrate Weapons Test Equip AP 67L ADP/PC Repair ADP/PC Repair 46 67M PCB Repair PCB Repair 47 67W SLQ Repair SLQ Repair 48 68A Boat Repair Boat Repair 7R 68B Small Craft Support Small Craft 7W 68C Life Boat Repair (Inflatable) Life Boat Repair 9N 71A Paint and Sandblast Paint and Sandblst 66 71B Corrosion Control Corrosion Control 7Y 71T Tile & Plate Setter Tile & Plate Setter 6M 72A Riggers Support Activity Riggers 7S 72B Divers Support Activity Divers 7T 72C General Deck Service General Deck Service 7U 72D Weight Testing Weight Testing 5Q 72E Transportation Transportation 6L 74A Sail Loft and Canvas Shop Sail Loft & Canvas 5R 81A Foundry Operations Foundry 2P 82A Missile and Guidance Storage and Checkout Missile/Guidnc Chk AB 83A Weapons Handling Inspection and Repair Wpn Hndlg Insp & Rep AJ 83B Weapons Handling Weapons Handling AT 84A Module Test and Repair Shop Module Test & Repair AC 84B Ballistic FC Repair and Calibration FC Ballistic Repr AK 85A Re-entry Body Receipt, Storage, and Maintenance (REB) Re-entry Body (REB) AL 91B ASROC Overhaul, Test, Repair, and Stow ASROC & ASTOR AF 91C Torpedo Mk 44, Mk 46, Mk 48, Test, Repair, and Stow Torpedo AA 91D SUBROC/TOMAHAWK Land Attack Missile System Nuclear SUBROC Mk-14 AG 91E Mk 48 Torpedo/Cruise Missile Mk 48 AH Downloaded from https://www.everyspec.com
p. 222
NAVSEAINST 4790.8B A-29 Repair W/C Code
Name
Abbreviated Name
Supply ID Code
91Q Weapons Quality Assurance Wpns Quality Assur AM 92A Sound Analysis Service Sound Analysis 5S 93A Non-Destructive Testing Non-Destructive, QA 62 93B Quality Assurance Service Qlty Assur Svc 63 94A Nucleonics and Radcon Service Nucleonics, Radcon 5T 95A Water Chemical Lab Water Chemical Lab 5V 95B Spectrometer Lab Service Test/Spectromtr Lab 5W 96A Mechanical Standard Mechanical Standards 5Y 97B Aircraft Launch & Recovery (for SIMA Portsmouth use only) ACFT L&R 1B 97C Non-Skid Service Shop Non-Skid Shop 1C 97D Ground Support Equipment Support Eqpt 1D 97E Aviation Ordnance Shop Aviation Ordnance 1E 97F Aviation Fuels Shop Aviation Fuels 1F 97J Manlifts Manlifts 4B 97M Contractor Support Yellow Gear 3D 97R Helo Landing Syst Recovery Assist, Secure, Traverse HLST/RAST 1R 97W Weapons Elevator Support Unit WESU 1W 970 Public Works Public Works Z0 973 Comm Elec Safety Comm Elec Safety Z0 974 Eng Elec Safety Eng Elec Safety Z0 981 Tiger Team Tiger Team Z0 982 Depot Tiger Team Depot Tiger Team Z0 983 DIRSSP DIRSSP Z0 990 Other Department Other Dept ZZ 991 Ship's Force (S/F) Ships Force (S/F) Z0 993 Commercial Industrial Services (CIS) CIS Z0 999 Other (Non-IMA) Other (Non-IMA) ZZ 99B Paint Locker Paint Locker 6K FCA Field Calibration Facility (Gauge/Meters) FCA Z0 RD00 Repair Department (10A) R00 DJ RD01 Hull Systems Repair & Services R01 DK RD02 Mechanical Systems Repair Division R02 DL Downloaded from https://www.everyspec.com
p. 223
APPENDIX A-30 Repair W/C Code
Name
Abbreviated Name
Supply ID Code
RD03 Electrical Systems Repair Division R03 DM RD04 Electronic Systems Repair Division R04 DN RD05 Combat Systems Repair Division R05 DP RD06 Nuclear Service and Reoaur Division R06 DQ WI05 ARMORY ARMORY DR WR00 Weapons Repair Administration W00 DC WR01 Torpedo Repair W01 DD WR02 Fire Control Repair W02 DE WR03 Special Weapon Repair Ord Services at NSSF W03 DF WR04 Missile and Launcher Repair W04 DG WR05 Navigation Repair W05 DH WR06 Weapons Quality Assurance W06 DI IN PROGRESS (entered on site-specific detail work sheet) Coded information that indicates the progress of the job at different stages of accomplishment. Standard job progress reporting and monitoring is performed by each work center at the outside repair activity involved in the repair. Reported information includes "in-progress" information, which is coded as follows:
Code Description
A AWAITING PARTS/SUPPLIES/TOOLS B AWAITING TRANSPORTATION C AWAITING QA INSPECTOR D AWAITING NDT E AWAITING FIREWATCH F AWAITING ACCESS TO SHIP (QUARTER-DECK CLEARANCE) G AWAITING RIGGERS/CRANE SERVICES/SCAFFOLDING BARGE H MAKING SPECIAL TOOL/PART I AWAITING AWC/OTHER CRAFT J AWAITING TAG OUT K AWAITING ADDITIONAL REFERENCE MATERIAL L AWAITING SHIPS FORCE M SHIP'S DRILLS Downloaded from https://www.everyspec.com
p. 224
NAVSEAINST 4790.8B A-31 N SHOP EQUIPMENT INOPERATIVE O CHANGE IN WEATHER
Rework. Unplanned delay caused by the need to repeat previously accomplished work due to poor workmanship or the omission of work steps:
Code Description
P1 FAILED TEST P2 RE-LAP-RE-GRIND P3 WRONG MATERIAL P4 WRONG MEASURE P5 MISCELLANEOUS
Change of Normal Method/Tools Not Used. Unplanned delay caused by the need to correct a deficiency that the normal shop method of repair could not or did not correct:
Code Description
Q1 NEW SET-UP Q2 PARTS FROZEN Q3 DEPARTURE FROM SPECIFICATIONS Q4 PART BUILD-UP Q5 MISCELLANEOUS R OTHER THAN THE ABOVE INSURV NUMBER (entered on 2K) Number assigned by INSURV to the applicable deficiencies identified during the INSURV inspection. (Refer to Chapter 9) INTEGRATED PRIORITY (entered on 2K) A sequential number to indicate its priority relative to other deferred work for an availability. IUC/REPAIR ACTIVITY/TYCOM REMARKS (entered on 2P) Remarks relating to the repair job by the IUC, the repair activity, or the TYCOM. IUC SCREENING (entered on 2K) Recommendation by the IUC or designated representative indicating the action to be taken using one of the screening codes listed under the data element "SCREENING (TYCOM)". Downloaded from https://www.everyspec.com
p. 225
APPENDIX A-32 IUC SIGNATURE (entered on 2P) The initials of the IUC indicating the document was screened and is recommended for accomplishment. JOB CONTROL NUMBER (JCN) (entered on 2K, CK, 2P and 2L) Consists of the Unit Identification Number (UIC), the Work Center (WC), and the Job Sequence Number (JSN). It is the key identification for maintenance actions and their related supply documents. The JCN is used to identify the maintenance action and to relate all of the parts used when a ship reports a maintenance action. It is also the link for associating upline reporting of a maintenance action when more than one activity is involved. It is important that all activities involved continue to use the same JCN on all maintenance and supply documents that apply to that particular maintenance action. JOB DESCRIPTION/REMARKS (entered on CK) Any remarks relating to the accomplishment of the maintenance action being reported. In some cases, the alteration directive will specify that certain information be documented. JOB ORDER NUMBER (entered on 2K) The job order number assigned by the activity performing work. JOB SEQUENCE NUMBER (entered on 2K, CK, 2P, and 2L) A 4-character number assigned by the work center to the maintenance action, or assigned by the outside activity performing the work. This is a number assigned sequentially from the Ship's Force Work List (SFWL)/Job Sequence Number (JSN) Log. JULIAN DATE (entered on 2K, CK, 2P, and 2L) A 4-character entry composed of the last digit of the calendar year followed by the numerical day of the year (e.g., 1 January 1994 is "41" and 31 December 1993 is "3365"). KEY EVENT (entered on 2P) An occurrence during a tended unit's availability which affects or is affected by the repair activity's productive effort; e.g., docking, undocking, boiler light-off, weapons handling, fuel/defuel, etc. Key events are to be identified by assigning a 2-digit numeric code to each event and assigning an abbreviation of 15 characters maximum to that code. When more than 99 key events are required, the code can be assigned using alphanumeric combinations. The Key Event code and definition is Downloaded from https://www.everyspec.com
p. 226
NAVSEAINST 4790.8B A-33 assigned and managed by TYCOM instruction. Repair activities must ensure continuity of schedules by using codes mutually agreed to by TYCOM representatives. Note: some automated systems allow for a four-digit code to be entered (refer to the TYCOM instruction). KEY OPERATION (KEY OP) (entered on 2P) Assigned numbers indicating the logical sequence of the task identified. For example:
Key Operation (K/O) Task
01 Disconnect & Deliver 02 Disassemble 03 Replace Bearings Etc. Etc. LEAD PLANNING & ESTIMATING CODE (entered on 2K) The code assigned to the lead planning and estimating organization. LEAD REPAIR WORK CENTER (LWC) (entered on 2K and 2P) The code of the lead repair work center assigned to the job. The first character of the code is left-justified.
The following codes indicate the IMA department to which the action work center is assigned; they are used to process IMA Performance Summaries at both IMA and TYCOM levels:
Department Key
A = Dry Dock B = Other Departments F = Special K = Temporary IMA L = Reservist P = Civilians R = Repair Department Z = Other Activities
NOTE:
Variable department names may be assigned as directed by the TYCOM using the letters "G", "H", and "J".
Downloaded from https://www.everyspec.com
p. 227
APPENDIX A-34 Refer to data element "IMA Repair Work Center" for a list of authorized IMA repair work center codes. LOCATION (entered on 2K and CK) The location of the equipment on which maintenance is required or was performed.
a. COMPARTMENT. Enter the compartment number identified on the compartment check-off list.
b. DECK-FRAME-SIDE. Enter the deck, frame, and side that best describes the location of the equipment.
c. If neither the compartment nor the deck-frame-side is appropriate, enter the name of the location (e.g., "FANTAIL", "FLIGHT DECK").
d. For submarines use standard abbreviation for locations (e.g., "OPSUL").
For shipboard locations, see General Specification for Ships of the U.S. Navy (NAVSEA PUB-AA-SPN 010/GEN SPEC) (NOTAL). MAINTENANCE INDEX PAGE NUMBER (MIP) (entered on CK) The MIP number covering the affected equipment. For like equipment installations, i.e., exchanges, enter the MIP covering the deleted equipment. For new installations, enter the MIP number when available; if not available, enter "NA". MAN-HOURS EXPENDED (entered on 2K) The man-hours expended on the last day the repair work center is involved in the work request (NOT the total man-hours of the work request). METER READING (M/R) (entered on CK) Used to indicate if the equipment or any of the equipment components/subunits of the equipment being reported have time meters installed. METER READING (M/R) (entered on 2K) (An expected entry for Selected Level Reporting (SLR) Level 1/Level 2 equipment.) The meter reading (to the nearest whole hour) at the time of failure. If the equipment has more than one meter, designate the meter being recorded in "REMARKS" using the letters "METRED" followed by the meter designator. An asterisk (*) must precede and follow meter designation as shown Downloaded from https://www.everyspec.com
p. 228
NAVSEAINST 4790.8B A-35 in the example below. The required meter is that associated with the functional major unit that failed.
Example: *METRED-1A2M1* NAMEPLATE DATA (entered on CK) Data that helps identify the equipment. Enter information available from the following list:
a. Contract Number or Procurement Document Number.
b. Part Number/Model Number/Drawing Number.
c. Commercial and Government Entity (CAGE) code, or if not available, the name and address of the manufacturer.
d. Any additional information, such as physical characteristics and manufacturer's identification, that is readily available and provides a description of the use or operation of the component. NEXT HIGHER ASSEMBLY (entered on CK) The nomenclature and serial number (SN) of the Next Higher Assembly (NHA) in which the equipment/component identified is a part of. If the SN is unavailable, use the locally assigned NHA number. The NHA is usually identified in the technical manual and the COSAL. NORMALLY DONE BY (entered on 2P) Indicates where this particular type maintenance is normally performed (S/F, IMA, Depot), which allows the collection of data for evaluation of IMA costs relative to other maintenance activities. PERIODICITY (entered on 2P) Identifies the number of months between which periodic maintenance requirements are to be performed. PERIODIC MAINTENANCE REQUIREMENT (entered on 2P) The code of a specific periodic maintenance requirement (e.g., "MRC-G40 A1"), a Planning and Engineering for Repairs and Alterations (PERA) code, or a Metrology Automated System for the Uniform Recall and Reporting (MEASURE) code identifying a periodic maintenance requirement. Downloaded from https://www.everyspec.com
p. 229
APPENDIX A-36 PRE ARRIVAL/ARRIVAL CONFERENCE ACTION/REMARKS (entered on 2K) Remarks provided by the repair activity determined necessary to facilitate repairs or that would require attention of the originating activity. PRIORITY (PRI) (entered on 2K) Identifies the priority of the deferred maintenance action:
Code Description
1 MANDATORY. Critical safety or damage control item. Required for performance of ship's mission. Required to sustain bare minimum acceptable level of human needs and sanitation. C-4 CASREP (Casualty Report) on equipment. 2 ESSENTIAL. Extremely important safety or damage control item. Required for sustained performance of ship's mission. Required to sustain normal level of basic human needs and sanitation. Required to maintain overall integrity of ship or a system essential to ship's mission. Will contribute so markedly to efficient and economical operation and maintenance of a vital ship system that the pay-off in the next year will overshadow the cost to accomplish. Required for minimum acceptable level of preservation and protection. C-3 CASREP on equipment. 3 HIGHLY DESIRABLE. Important safety or damage control item. Required for efficient performance of ship's mission. Required for normal level of human comfort. Required for overall integrity of equipment or systems that are not essential, but are required as backups in case of primary system failure. Will contribute so markedly to efficient and economical operation and/or maintenance of a vital ship system that the payoff in the next year will at least equal the cost to accomplish. Will effect major reduction in future ship maintenance in an area or system that presently cannot be maintained close to acceptable standards. Required to achieve minimum acceptable level of appearance. C-2 CASREP on equipment. 4 DESIRABLE. Some contribution to efficient performance. Some contribution of normal level of human comfort and welfare. Required for overall integrity of other than an essential system or its backup system. Will contribute to appearance in an important area. Will significantly reduce future maintenance. Downloaded from https://www.everyspec.com
p. 230
NAVSEAINST 4790.8B A-37 QUALITY ASSURANCE REQUIREMENTS (entered on 2P) Identifies the specific planning actions, work controls, and auditable records in support of individual TYCOM management needs. These special requirements are indicated by an "X" placed in the appropriate reporting field. QUANTITY (entered on CK) The number of like equipment identified in the work center that was removed, installed, or modified to accomplish the maintenance action. If the Component Serial Number field has an entry, the quantity entered must be "1". Only one piece of equipment can be uniquely identified by a single serial number. RATE (entered on 2K) The rank/rate of the first contact/maintenance person. The following examples apply:
Rank/Rate Code Entry
Officers OFF ET1 ET1 Civilian CIV GMG2 GMG2 FTGSN FTGN EMFN EMFN FN FN RECORD IDENTIFICATION NUMBER (RIN) (entered on CK) Identifies a specific equipment record within the SNAP, WSF, and SCLSIS databases. For deletions, removals, and modifications, enter the RIN for the component as listed in Part I, Section C of the COSAL. For installations and additions, leave applicable fields blank. REMARKS/DESCRIPTION (entered on 2K and CK) FOR A MAINTENANCE ACTION (2K). Provide information that describes the problem and what caused the failure (if known); followed by what needs to be done to correct the problem. Separate the problem description and corrective action entries with three X's (i.e., "WHAT IS WRONGXXXWHAT MUST BE DONE"). If reporting the completion of a maintenance action, the field should describe the trouble and the corrective action. If necessary, this field is used to record safety related data and for expected SLR Level 2 data.
Downloaded from https://www.everyspec.com
p. 231
APPENDIX A-38 For SLR Level 2 reporting the following narrative information is expected:
a. Any problems encountered which hindered or delayed completion of the maintenance action
b. Reference Designators/ Part Serial Numbers – Reference Designators and/or Serial Numbers of removed and installed parts
c. Symptoms of the failure
d. Logistics Deficiencies - part number(s) of parts replaced or causing logistic delays (if the part was obtained by cannibalization identify source)
e. Description of difficulties with or deficiencies of fault isolation procedures, maintenance documentation, or test equipment
f. Full description of multiple events within a maintenance action
g. Any other helpful information concerning the event
For SLR Level 3 Specialized Reporting the data will be in a structured-narrative format as designed in a unique template.
FOR A CONFIGURATION CHANGE (CK). Enter information that describes the accomplishment of the action. Occasionally, alterations specify that certain information be documented. If an "X" is entered in the M/R field, identify each equipment and enter "M/R" followed by the time meter reading. REMARKS/SKETCHES (entered on 2L) Required amplifying information related to a maintenance action. Include drawings and sketches, or multiple item serial numbers and locations for which identical maintenance requirements exist from an outside activity. REPAIR ACTIVITY UIC (entered on 2K) The UIC of the activity performing work for the originating ship. Downloaded from https://www.everyspec.com
p. 232
NAVSEAINST 4790.8B A-39 REPAIR WORK CENTER (RWC) (entered on 2K) Used by the repair activity for internal planning and scheduling, a 3 or 4-character code identifying the lead work center assigned to the job. R/M (Maintenance Indicator) (entered on 2K) Either an "R" or "M", used by INSURV, which identifies equipment that shows low reliability or unusual maintenance. "R" indicates low reliability, requiring frequent corrective maintenance; "M" indicates poor maintainability, requiring unusual maintenance efforts due to installation or design. S (Safety Identifier) (entered on 2K) The code "S", used by INSURV to identify those discrepancies which might cause injury to personnel or material damage. SAFETY HAZARD (entered on 2K) A code number selected from the Risk Assessment Codes (RAC) that describes a problem or condition which has caused, or has the potential to cause injury to personnel and/or damage to material, enter the applicable RAC described in codes "1" through "5". If the documented maintenance action is not safety related, enter "". RAC selections for the safety hazard entry are:
Code Risk Assessment Description
1 CRITICAL SAFETY OR HEALTH DEFICIENCY-CORRECT IMMEDIATELY. This category identifies deficiencies which present a critical safety hazard to personnel or machinery, or a health hazard to personnel, and which must be corrected immediately. This code is used for items such as electric shock hazards, inoperative interlocks or safety devices, missing or damaged lifelines, inoperable escape scuttles, refrigerants (air conditioning or refrigeration) leaking into confined spaces, leaking components containing PCBs, and the like. All efforts must be exerted to correct these items prior to any other maintenance deficiencies. Suspension of use of the equipment/system/space is mandatory. 2 SERIOUS SAFETY OR HEALTH DEFICIENCY-SUSPENSION OF EQUIPMENT/SYSTEM/SPACE USE IS REQUIRED. This category deals with serious safety hazards to personnel or machinery, or health hazards which must be corrected prior to resuming use of the equipment/system/space. Downloaded from https://www.everyspec.com
p. 233
APPENDIX A-40 3 MODERATE SAFETY OR HEALTH DEFICIENCY-WAIVER OF EQUIPMENT/SYSTEM/SPACE USE IS GRANTED PENDING CORRECTION OF THE ITEM. This category is used in cases where the equipment/system/space can be operated or utilized in a satisfactory manner without greatly risking physical injury, serious damage to the equipment/system/space, or greatly risking the health of personnel. 4 MINOR SAFETY OR HEALTH DEFICIENCY. This is a category of safety or health deficiencies which must be corrected when resources become available. 5 NEGLIGIBLE SAFETY OR HEALTH DEFICIENCY. This category identifies deficiencies which are noted for record purposes and may be corrected when other work is accomplished on the equipment/system/space. X SAFETY RELATED INDICATOR 0 MAINTENANCE ACTION IS NOT SAFETY RELATED.
NOTE:
Codes "6" through "9" may be locally assigned by TYCOMs for additional safety codes required.
A brief explanation must be included in the Remarks/ Description field. For example: "RE-INSPECTION OF SEPARATOR FOR PRESENCE OF OIL AFTER RINSE. MRC A-27 EVIDENTLY NOT DONE. PRESENCE OF OIL RESULTED IN FIRE IN HP AIR SYSTEMS WHEN COMPRESSOR OPERATED UNDER LOAD. FIRE BADLY BURNED VALVE AHP-287, REQUIRING REPLACEMENT." The ship's 3-M system coordinator will forward a copy of all OPNAV 4790/2K documentation having an entry in this field to the safety officer for review. SCHEDULED COMPLETION DATE (entered on 2K and 2P) The Julian date on which all work on the job is scheduled to be completed by the activity assisting the originating ship. SCHEDULED START DATE (entered on 2K and 2P) Used by the repair activity, the Julian date on which work on the job is to begin. SCREENING ACTION (entered on 2P) Appropriate action to be taken to accomplish the maintenance as directed by the TYCOM. The field may also be used by the IUC, but the TYCOM representative's decision has precedence. The IUC/TYCOM representative must indicate the level at which the maintenance, if approved, is to be done. Downloaded from https://www.everyspec.com
p. 234
NAVSEAINST 4790.8B A-41 SCREENING (IUC) (entered on 2K) The intermediate unit commander (IUC) or designated representative recommended action to be taken using one of the codes listed below under SCREENING (TYCOM). The IUC is that officer in the chain of command between the ship and the TYCOM. SCREENING (TYCOM) (entered on 2K) The action to be taken as determined by the type commander (TYCOM) or designated representative. Acceptable screening codes are:
Code Description
1 Depot (shipyard or ship repair facility) Accomplish 1A Depot Assisted by Ship's Force 1S Ship to Shop 1M Accomplish with Modification 2 Intermediate Maintenance Activity (IMA) (tender/repair ship, etc.) Accomplish 2A IMA Assisted by Ship's Force 2S Ship to Shop 2M Accomplish with Modification 3 TYCOM Support Unit (TSU) (floating dry dock, etc.) Accomplish or Technical Assistance from NAVUNDERSEAWARFARCENDET/FTSCLANT/FTSCPAC/Contractor Representative 3A TSU Assisted by Ship's Force 3S Ship to Shop 3M Accomplish with Modification 4 Ship's Force Accomplish 5 Deferred 5A Insufficient Time in the Availability to Complete the Task 5B Lack of Shipyard Capability 5C Lack of Material 5D Lack of Funds 5E Not Required During this Availability 5F General 6 Not Authorized 6A Not Technically Justified 6B Covered by an Existing Ship Alteration 6C Duplicate of Another Job Control Number (JCN) 6D Not Cost Effective 6E General 8* Disapproved 9** Remove from Current Ship's Maintenance Project (CSMP). Pass to history (to be assigned by TYCOM only) Downloaded from https://www.everyspec.com
p. 235
APPENDIX A-42
* This screening code disapproves the accomplishment of a work item by an outside activity. It does not prevent entry of the deferral into the CSMP, which is the decision of the commanding officer.
** This screening code is restricted to the removal of INSURV items from the CSMP for which, in the opinion of the ship's IUC and TYCOM, the ship has no responsibility for accomplishment. SECAS OFFICE USE (entered on CK) No longer in use. SECOND CONTACT/SUPERVISOR (entered on 2K and 2L) The supervisor of the first contact/maintenance person indicating he screened the maintenance action entry for completeness and accuracy. SELECTED EQUIPMENT LIST (entered on 2K) Selected equipment under an intensive management program requiring additional usage data to be collected. See data element "REMARKS/DESCRIPTION" for reporting requirements. SERVICE APPLICATION CODE (SAC) (entered on CK) A code used to group equipment, components, assemblies, etc., according to a particular system or service application on- board ship. This code is similar to the HSC in purpose, but does not provide a hierarchical structure. The SAC is a code assigned by the supply department. SHIP'S FORCE MAN-HOURS (S/F MHRS) (entered on 2K) The total man-hours (to the nearest whole hour) that ship's force used doing the maintenance after submitting the deferral. It includes witnessing of tests, and those man-hours expended in reinstallation, test, documentation, etc. Documentation time can not exceed "1" hour. SHIP'S FORCE MAN-HOURS EXPENDED (S/F MHRS. EXP.) (entered on 2K and CK) FOR A MAINTENANCE ACTION (2K). The total man-hours (to the nearest whole hour) used by all work centers in the maintenance action up to the deferral time; include documentation time (should not exceed 1 hour).
Downloaded from https://www.everyspec.com
p. 236
NAVSEAINST 4790.8B A-43 FOR A CONFIGURATION CHANGE (CK). The total number of man-hours expended by ship's force (and not previously reported) in completing and documenting the maintenance action (documentation time should not exceed 1 hour). Man-hours expended by other than ships force are to be documented separately. SHIP'S FORCE MAN-HOURS REMAINING (S/F MHRS. REM.) (entered on 2K) The ship's force man-hour estimate (to the nearest whole hour) remaining to complete the maintenance action. If TYCOM allows an automatic close out of the deferral by the IMA, enter "AUTO"; this is a request to the IMA to complete the maintenance action with no further documentation from the shop after the job has been accepted by the originator (authorized signature). If the originating ship does not receive CSMP support from the IMA doing the work, do not use the AUTO close out feature. SHIP'S NAME (entered on 2K, CK, 2P, and 2L) The name of the activity originating the maintenance action. SHIP'S UNIT IDENTIFICATION CODE (UIC) (entered on 2K, CK, 2P, and 2L) The 5-digit UIC of the activity initiating the maintenance action. The Navy Comptroller (NAVCOMPT) Manual, Volume 2, Chapter 5 lists UICs. For service craft or boats without a UIC use the UIC of the parent activity.
FOR OTHER THAN U.S. NAVY SHIPS - The UIC for other than U.S. Navy ships will have an "A" as the first character followed by a sequential number related to the number of foreign units in availability. SPECIAL DATA (entered on 2P) Data element currently not assigned for use. Available for future expansion. SPECIAL PURPOSE (entered on 2K) A code used to indicated that quality control and quality assurance standards are required. Refer to TYCOM instructions for additional information relative to these entries.
Enter the code in the designated field "A" through "L" as follows:
Field A The department head will enter the KEY EVENT code from the ISIC provided Key Event Schedule. Downloaded from https://www.everyspec.com
p. 237
APPENDIX A-44
Field B Enter the code "SS" if the job requires work within SUBSAFE boundaries or involves SUBSAFE materials. (Refer to COMSUBLANT/COMSUBPACINST 4855.2.)
Field C Enter the code "L1" if the job requires work within Level I boundaries or involves Level I material. (Refer to COMSUBLANT/COMSUBPACINST 4855.2.)
Field D Enter the code "08" if the job is associated with nuclear equipment. (Refer to NAVSEAINST 9210.4A (NOTAL).)
Field E Enter the code "RC" if the job requires radiological controls (RADCON). (Refer to NAVSEA technical publication 389-0153.)
Field F Enter the code "DD" if the job requires dry docking to accomplish.
Field G Enter the code "NC" for critical noise deficiencies or "NP" for potential radiated noise deficiencies.
Field H Reserved for future use.
Field I Reserved for future use.
Field J Reserved for future use.
Field K Reserved for future use.
Field L Enter the code assigned to the visiting activity. This will identify the visiting activity as the originator of the deferral. Information reported as directed by the cognizant TYCOM. SPECIAL REQUIREMENTS (entered on 2P) KEY EVENT. 2-digit number identifying an event which influences a job or is influenced by the completion of a job, (e.g., job requiring completion before undocking). Blank indicates that the job is not associated with a key event.
SPECIAL INTEREST. A field used to indicate the job has been selected for job management reports, and identifying the job as having significant management interest. An "X" is the common entry for this field.
Downloaded from https://www.everyspec.com
p. 238
NAVSEAINST 4790.8B A-45 DRY DOCK REQUIRED. A field used to show that the requested maintenance requires the ship to be dry docked. An "X" is the common entry for this field.
PRE-OVERHAUL TEST REQUIRED. A field used to identify a specific test required prior to an equipment or ship overhaul. An "X" is the common entry for this field.
POST-OVERHAUL TEST REQUIRED. A field used to identify that a test must be completed after equipment or ship overhaul. An "X" is the common entry for this field.
DEPARTURE REQUIRED. A field used to indicate that if the maintenance is not accomplished to specifications, notice of the departure must be sent to the TYCOM. An "X" is the common entry for this field. STATUS (STA) (entered on 2K) A code that describes the effect of failure or malfunction on the operational capability of the equipment or system when the need for maintenance was first discovered:
Code Description
1 Operational 2 Non-Operational 3 Reduced Capability 0 Not Applicable (use if reporting printing services, etc.) SUFFIX (entered on 2K) Used by INSURV to insert additional required numbers between sequential numbers. TASK (entered on 2P) The description(s) of the task(s) for which the "LEAD" and "ASSIST" repair work center(s) identified are responsible. TECHNICAL DOCUMENTATION (entered on 2P) Blueprints, technical manuals, etc., which may be useful to the IMA in providing required assistance. Indicate with an "X" if the publications are held by the tended unit or the IMA. TECHNICAL MANUAL (TM) NUMBER (entered on CK) The TM number covering the component. For removals and modifications enter the appropriate TM number for the equipment. For like equipment installations (i.e., exchanges), enter the TM Downloaded from https://www.everyspec.com
p. 239
APPENDIX A-46 number of the deleted equipment. For new installations, enter the TM number covering the component. If unavailable, enter "NA". TROUBLE ISOLATION (TI) (entered on 2K) A single numeral (1-9) to indicate, to the nearest 10 percent, the percentage of active maintenance expended in troubleshooting. If no troubleshooting is involved, enter "f". Examples: "2" = 20%, "3" = 30%, "7" = 70%, etc. TYCOM AUTHORIZATION (entered on 2K) Signature/entry of the TYCOM representative screening deferrals. TYCOM (SCREENING) (entered on 2K) Refer to data element SCREENING (TYCOM). TYCOM SIGNATURE (entered on 2P) Signature of the IUC and/or TYCOM representative indicating the maintenance request has been screened. TYPE OF AVAILABILITY (T/A) (entered on 2K) Type of availability recommended for performance of a deferral.
Code Description
1 Depot (shipyard or ship repair facility) 2 Intermediate Maintenance Activity (tender, repair ship, etc.) 3 TYCOM Support Unit (floating dry dock, etc., or technical assistance from NAVUNDERSEAWARCEN, DETACMENT FTSCLANT, FTSCPAC or contractor representative) 4 Ship's Force 0 Not Applicable U (Mission Degrading) (entered on 2K) Used by INSURV, field identifies certain deficiencies which are considered as preventing the ship from carrying out some part of its mission. UNIT IDENTIFICATION CODE (UIC) (entered on 2K, CK, 2P, and 2L) Identifies the Unit Identification Code of the activity originating the maintenance action. For service craft or other boats without their own UIC, use the UIC of the parent activity. Downloaded from https://www.everyspec.com
p. 240
NAVSEAINST 4790.8B A-47 WHEN DISCOVERED (WND) (entered on 2K) Identifies when the need for maintenance was discovered.
Code Description
1 Lighting Off or Starting 2 Normal Operation 3 During Operability Tests 4 During Inspection 5 Shifting Operational Modes 6 During PMS 7 Securing 8 During AEC (Assessment of Equipment) Program 9 No Failure, PMS Accomplishment Only 0 Not Applicable (use when reporting printing services, etc.) WHEN DISCOVERED DATE (entered on 2K) The Julian Date when the equipment of the system failure was discovered. WORK CENTER (WC) (entered on 2K, CK, 2P, and 2L) Two basic types of work center codes exist. Their definition and application are as follows:
SHIPS. Ships use a 4-position work center code. The first two positions identify the department and division. The last two positions identify the division work center.
REPAIR DEPARTMENTS OF TENDERS, SIMAs, AND OTHER IMAs. These organizations use a 3-position work center code to identify the repair shops (e.g., "10A", "67A", "91A", etc.).
See data element "IMA Repair Work Center" for a list of authorized IMA repair work center codes. WORK REQUEST ROUTINE (entered on 2K) The appropriate Expanded Ship Work Breakdown Structure (ESWBS), Ship Work Breakdown Structure (SWBS), Ship Work Authorization Boundary (SWAB), or Ship Work Line Item Number (SWLIN), as directed by the TYCOM. This entry is made to integrate the deferral into applicable work packages. Downloaded from https://www.everyspec.com
p. 241
APPENDIX A-48 YYMM ISSUED (entered on 2P) Four numbers used to identify the year and month during which the periodic maintenance requirement entered was issued. The first two digits identify the year and the last two digits identify the month.
Downloaded from https://www.everyspec.com
p. 242
MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL
APPENDIX B
SHIP'S 3-M FORM PREPARATION INSTRUCTIONS
Downloaded from https://www.everyspec.com
p. 243
APPENDIX B-i APPENDIX B
SHIP'S 3-M FORM PREPARATION INSTRUCTIONS TABLE OF CONTENTS
Paragraph Title Page
B-1 CONFIGURATION CHANGE FORM (NAVSEA 4790/CK) ............... B-1 B-1.1 Procedures for Reporting Configuration Change (NAVSEAINST 4790/CK Form) .......................................... B-2 B-1.2 Section II - Job Description/Remarks ................... B-5 B-1.3 Section III - Component Configuration Change Identification ......................................... B-6 B-1.4 Section IV - Special Purpose ........................... B-8 B-1.5 Procedures For Using CK Continuation Pages ............. B-8 B-1.6 Procedures for Reporting Configuration File Corrections, and Updating the Cosal ................................. B-8 B-1.7 Correct A Data Element Error in the Ship's Cosal or Cosal Indexes, or Other Such Documents ....................... B-9 B-1.8 Report an Equipment Record Addition/Deletion ........... B-9 B-1.9 Report the Turn-In/Receipt of Portable Electrical/ Electronic Test Equipment (Peete) ...................... B-9 B-1.10 Handling Procedures .................................. B-10 B-2 SHIP'S MAINTENANCE ACTION FORM (NAVSEA 4790/2K) ......... B-19 B-2.1 Procedures for Documenting A Deferred Maintenance Action ................................................ B-20 B-2.2 Procedures for Using NAVSEA 4790/2K Continuation Pages ................................................. B-27 B-2.3 Procedures for Documenting Internal Work Requests ..... B-29 B-2.4 Procedures for Documenting Screening Information On Deferred Maintenance Actions .......................... B-30 B-2.5 Procedures for Documenting A Completed Maintenance Action Previously Deferred ................................... B-34 B-2.6 Procedures for Documenting A Completed Maintenance .... B-38 Downloaded from https://www.everyspec.com
p. 244
NAVSEAINST 4790.8B
B-ii B-2.7 Procedures for Documenting Changes, Additions, and Deletions to Previously Submitted Maintenance Actions..B-45 B-2.8 Procedures to Add-On Remarks to the CSMP...............B-45 B-2.9 Handling Procedures....................................B-45 B-3 SUPPLEMENTAL FORM (NAVSEA 4790/2L).......................B-50 B-3.1 Special Application....................................B-50 B-4 MAINTENANCE PLANNING AND ESTIMATING FORM (NAVSEA 4790/2P).........................................B-54 B-4.1 Procedures For Documenting Planning & Estimating Data..B-54 B-4.2 Repair Officer Actions.................................B-58 B-4.3 Procedures for Documenting Changes, Additions, and Deletions..............................................B-58
Downloaded from https://www.everyspec.com
p. 245
APPENDIX B-iii APPENDIX B
SHIP'S 3-M FORM PREPARATION INSTRUCTIONS LIST OF FIGURES
Figure Title Page
Figure B-1: Ship’s Configuration Change Form For Component Removal Maintenance Action.................... B-11 Figure B-2: Ship’s Configuration Change Form For Component Install....................................... B-12 Figure B-3: Ship’s Configuration Change Form Resulting From An Alteration................................. B-13 Figure B-4: Ship’s Configuration Change Form For An Alteration Install (continuation)............. B-14 Figure B-5: Ship’s Configuration Change Form For A Correction To A Previously Submitted Change... B-15 Figure B-6: Ship’s Configuration Change Form For Location Correction.................................... B-16 Figure B-7: Ship’s Configuration Change Form for COSAL Add........................................... B-17 Figure B-8: Ship’s Configuration Change Form for COSAL Delete........................................ B-18 Figure B-9: Ships Maintenance Acton Form For A Deferred Maintenance Action............................ B-46 Figure B-10: Ships Maintenance Acton Form For A Completed Maintenance Action Without Prior Deferral..... B-47 Figure B-11: Ships Maintenance Acton Form Change To A Previously Submitted Deferred Maintenance Action........................................ B-48 Figure B-12: Ships Maintenance Acton Form Add-on Remarks To A Previously Submitted Deferred Maintenance Action........................................ B-49 Figure B-13: SUPPLEMENTAL FORM Containing an Equipment Listing....................................... B-52 Figure B-14: SUPPLEMENTAL FORM Containing a Sketch/Drawing. B-53 Figure B-15: Completed NAVSEA 4790/2P...................... B-60 Downloaded from https://www.everyspec.com
p. 246
NAVSEAINST 4790.8B
B-1 APPENDIX B
SHIP'S 3-M FORM PREPARATION INSTRUCTIONS
B-1 CONFIGURATION CHANGE FORM (NAVSEA 4790/CK) The NAVSEA 4790/CK Form is used to report completion (or partial completion) of alterations, maintenance actions that resulted in a configuration change, and to correct discrepancies and errors in the configuration files.
Three blocks at the top of the form are used to specify what type of action is being reported (a configuration file correction “CONFIG FILE CORR” a completed maintenance action that had no prior deferral “COMP M/A NO DEFL”). The rest of the form is separated in to four sections.
a. Section I – Job Identification. This section identifies the system or equipment involved in the configuration action. If a component/sub-unit are being reported, the Job Identification in this section must be that if the highest assembly. Components/sub-units are reported in Section III.
b. Section II – Job Description/ Remarks. This section contains remarks relating to the accomplishment of the action. In some cases, an alteration directive will specify that certain information be documented.
c. Section III – Component Configuration Change Identification. This section contains information on the component(s) affected by the maintenance (configuration change) action. The Job Identification Level (section I) will be completed to the highest assembly directly affected by the change. The sub-units (components) are reported to the individual APL level in SECTION III. A NAVSEA 4790/CK allows only one component (sub-unit) to be reported per form. When multiple sub-units need to be reported, “CONTINUATION SHEET (S)” NAVSEA 4790/CK(C), THAT CAN REPORT UP TO FOUR COMPONENTS PER Form can be attached. The same JCN as assigned to the higher level assembly maintenance action recorded in SECTION I is to be continued on each component reported.
d. Section IV – SPECIAL PURPOSE. This section is filled in onboard, with the exception of Block 30 (is no longer applicable).
Downloaded from https://www.everyspec.com
p. 247
APPENDIX B-2 NOTE:
Examples of completed NAVSEA 4790/CK forms for various reporting situations can be found following these written instructions. B-1.1 Procedures for Reporting Configuration Change (NAVSEAINST 4790/CK Form) a. Place an "X" in the appropriate block at top of form to indicate the type of action being reported, "COMP M/A NO DEFL" or "COMP DEFL".
b. SECTION I - JOB IDENTIFICATION
Block A Enter SHIP'S NAME
Block B Enter SHIP'S HULL NUMBER
JOB CONTROL NUMBER (Blocks 1 - 3):
Block 1 SHIP'S UIC: Enter the UIC of the activity receiving the maintenance action.
Block 2 WORK CENTER: Enter the code of the shipboard work center responsible for the equipment.
Block 3 JOB SEQ. NO.: Enter the four character job sequence number assigned by the work center supervisor. This is an entry assigned sequentially from the SFWL/JSN Log.
NOTE (Blocks 1, 2, 3):
If the configuration change being reported is not an alteration and closes a job previously deferred and on the CSMP, enter the JCN of the opening deferral. If the maintenance action is the accomplishment of an alteration, enter the JCN from the alteration record (EXSA2134, OXTY1016, WXSP1124).
Block 4 ALTERATIONS (SHIPALT, FLD. CHG., ETC.): If applicable, enter the alteration number from the authorizing directive.
For Ship Alterations (SHIPALTs), enter the alteration identification exactly as it appears on the Ship Alteration (SHIPALT) Record. Record the Downloaded from https://www.everyspec.com
p. 248
NAVSEAINST 4790.8B
B-3 alteration type "SA" in the first two positions, ship type starting in position three, and the alteration number starting in the 7th position of the block (i.e., SASSBNf342130). Enter the title code from the alteration record in the last right- hand position of the block.
For all other alteration types, enter the alteration type character code in the first two positions of the block. Enter the alteration number starting in position four (i.e., OA f96999, FC 29, TY 0132).
If an alteration identification number is not provided with the alteration record, leave blank. Following are the authorized alteration prefix codes:
SA = SHIP ALTERATION OA = ORDNANCE ALTERATION BA = BOAT ALTERATION FC = FIELD CHANGE MA = MACHINERY ALTERATION SI = SYSCOM COMMAND INSTRUCTION EC = ENGINEERING CHANGE HI = HABITABILITY TY = TYCOM DIRECTION TD = TECHNICAL DIRECTIVE SP = STRATEGIC SYSTEMS PROJECT OFFICE ALTERATION SC = SERVICE CHANGE TR = TRIDENT ALTERATION EP = ENGINEERING CHANGE PROPOSAL MO = CRYPTO EQUIPMENT MODIFICATION AR = ALTERATION REQUEST. May be originated by a ship to request an alteration design. Enter and left-justify the authorized prefix "AR" followed by a blank space, any number the ship assigns for its own control.
Block 5 EIC: Enter the Equipment Identification Code (EIC) for the equipment identified in the Equipment Noun Name field (Block 7). EIC's are listed in the SCLSIS Index Report or Ship's 3-M Reference Compact Disk (CD).
NOTE: Downloaded from https://www.everyspec.com
p. 249
APPENDIX B-4
When documenting 3-M requests for Fleet/Depot assistance, a special Equipment Identification Code (EIC) of “ZOZZ” for NAVSEA 08 and “ZOYY” for DIRSSP shall be used and the remaining data must be unclassified.
Block 6 ACT. TKN: Enter the appropriate Action Taken code from the lower section of the NAVSEA 4790/CK form or from the following list:
Code Descriptions
5A Partially Completed Alteration. The IMA must describe in the Job Description/Remarks section what was done and the O-level what remains to be done. 5B Fully Completed Alteration 5C Fully Completed Equivalent to Alteration 5D Alteration Directive Not Applicable
NOTE:
Use of a number 5( ) code requires an entry in Block 4 "Alteration Identification
1 Maintenance Action Completed; Parts Drawn from Supply 2 Maintenance Action Completed; Required Parts Not Drawn from Supply (local manufacture, pre-expended bins, etc.) 3 Maintenance Action Completed; No Parts Required
NOTE:
The following second character codes can be used with the above Action Taken codes 1, 2, or 3 as directed by the TYCOM:
A Maintenance Requirement Could Have Been Deferred B Maintenance Requirement Was Necessary C Maintenance Requirement Should Have Been Done Sooner M High Cost Repairs T The Equipment Being Reported Had a Time Meter Downloaded from https://www.everyspec.com
p. 250
NAVSEAINST 4790.8B
B-5
Block 7 EQUIPMENT NOUN NAME: If the maintenance action is the accomplishment of a SHIPALT, enter the equipment Noun Name from the SHIPALT record. Otherwise, enter the equipment nomenclature /description of the equipment or system on which the maintenance was performed. If the maintenance action affects several components, enter the name/designator of the highest assembly. For HM&E equipment, enter the noun name. For electronics equipment, enter the Army-Navy (AN) type designator or commercial model number. For ordnance equipment, enter the system/equipment nomenclature, followed by the Mark and Mod numbers, e.g., Launch System 36/1.
Block 8 S/F MHRS. EXP.: Enter the total number of man-hours expended by ship's force (and not previously reported) in completing and documenting the maintenance action. Man-hours expended by others tasked to perform equipment maintenance are to be documented separately.
Block 9 ACT. MAINT. TIME: Used for SEL equipment only. Enter the total number of clock hours expended to complete the maintenance.
Block 10 COMP. DATE: Enter the Julian date the maintenance action was completed.
Block 11 M/R (Meter Reading): Enter a "X" if the equipment or any of the equipment components / sub-units to be identified in Section III have time meters installed. B-1.2 Section II - Job Description/Remarks Block 12 JOB DESCRIPTION/REMARKS: Enter any information/remarks relating to the accomplishment of the action. In some cases, an alteration directive will specify that certain information be documented.
If an "X" is entered in Block 11, identify in Block 12 each equipment name followed by "M/R" and the time meter reading. Downloaded from https://www.everyspec.com
p. 251
APPENDIX B-6 B-1.3 Section III - Component Configuration Change Identification Block 13 COMPONENT NOUN NAME: Enter the noun name of the component removed, installed or modified. For HM&E equipment, enter the noun name. For electronics equipment, enter the “AN” type designator or commercial model number. For ordnance equipment, enter the system/equipment nomenclature, followed by the Mark and Mod numbers, e.g., Launch System 36/1.
Block 14 QUANTITY: Enter the number of like components/sub- units identified in Block 13 that were, removed, installed or modified. The quantity must be "001" if a component identification number is entered in Block 16, or a serial number is entered in Block 17 (see Step 17).
Block 15 CA (Component Action): Enter the code identifying whether the equipment in Block 13 was, removed (R), installed (I), or modified (M). When reporting a configuration file action vice a maintenance action enter for an Add (A), Delete (D), or Correction (C).
Block 16 COMPONENT IDENTIFICATION: Enter the local identification number(s) such as station number or valve mark of the equipment identified in Block 13. This information must be consistent with the quantity entered in Block 14. For electronic (ELEX) equipment, enter the model number, and if available, enter the serial number in Block 17.
Block 17 COMPONENT SERIAL NUMBER: Enter the manufacturer's serial number of the equipment identified in Block 13. If the serial number is not available enter "NONE".
Block 18 COMPONENT APL/AEL: Enter the Component Allowance Parts List/Allowance Equipage List (APL/AEL) of the component identified in Block 13. If not available, the unit's supply department should assign a temporary APL.
Block 19 LOCATION (DECK/FRAME/SIDE): Enter the location (compartment number, deck, frame, or side notation), that best describes the location of the equipment identified in Block 13. If none of the above mentioned location identifications are appropriate, Downloaded from https://www.everyspec.com
p. 252
NAVSEAINST 4790.8B
B-7 enter a descriptive term of the onboard location (e.g., FANTAIL, FLIGHT DECK, etc.).
Block 20 EIC: Enter the Equipment Identification Code that best describes the component identified in Block 13.
Block 21 NEXT HIGHER ASSEMBLY: Enter the nomenclature and serial number of the next higher assembly. No entry is required when the component identified in Block 13 is the highest assembly.
Block 22 SAC: Enter the Service Application Code of the component identified in Block 13. SAC codes can be obtained from the supply department.
Block 23 WORK CENTER: Enter the code (Work Center Responsible for Equipment (WCRE)) of the work center having primary maintenance responsibility for the component identified in Block 13.
Block 24 NAMEPLATE DATA: Enter the Contract Number or Procurement Document Number, Part Number/Model Number or Drawing Number, and if available, the Commercial and Government Entity (CAGE) (formerly called Federal Supply Code for Manufacturers (FSCM)). Additional information, if available, such as physical characteristics and manufacturer's identification is useful. No entry is required for modifications and deletions if an APL is listed in Block 13.
Block 25 MIP: Enter the Maintenance Index Page covering the component identified in Block 13 for removals, modifications, changes and deletions. If not available, enter "NA".
Block 26 EOSS: Entry not required when reporting Electronic or Ordnance Configuration Change actions. For HM&E equipment, enter the Engineering Operation Space Sequence (EOSS) Document Code and Control Number of the primary EOSS procedure affected. If more than a component level document is affected, enter only the EOSS component procedure.
Block 27 TM: For removal and modifications, enter the Technical Manual covering the affected component. For like equipment installations, enter the TM Downloaded from https://www.everyspec.com
p. 253
APPENDIX B-8 covering the equipment. For new installations, enter the TM when available; if not available, enter NA. B-1.4 Section IV - Special Purpose Block 28 RIN: Enter the Record Identification Number as listed in Part I, Section C of the COSAL, for deletions, removals, and modifications. For installations and additions, leave blank.
Block 29 AILSIN: Enter the Automated Integrated Language System Identification Number assigned by the Configuration Data Manager, Platform Manager, or Item Manager. For Electronic equipment, no entry is required unless directed by TYCOM.
Block 30 SECAS OFFICE USE: (Ship's Equipment Configuration Accounting System). Block no longer used. B-1.5 Procedures For Using CK Continuation Pages The JCN entry must be the same as on page 1. Up to four components can be reported on the same continuation form, with each separate component block considered a separate continuation page with its own page number. Page number consecutively. If applicable, check the block at the top of each component identification section to indicate that all data to be entered is the same as SECTION III, page 1, except for that data actually entered in the component identification section. An arrow pointing up (-) should be placed in the first block of each blank field to indicate that it is the same as page 1.
For each component reported, the required entries on the continuation pages are the JCN, page number, equipment alteration number (if applicable), and those component identification data elements which differ from SECTION III, page 1 (original CK). B-1.6 Procedures for Reporting Configuration File Corrections, and Updating the Cosal B-1.6.1 Correct Errors in A Previous Submission
Print in large letters the word "Correction" at the top of the form. Check the block "CONFIG FILE CORR" at the top right portion of the CK form. Enter the exact JCN (Blocks 1, 2, and 3) and page number of the CK which was submitted in error. Enter action code "C", which indicates "correction" in Block 15. If Downloaded from https://www.everyspec.com
p. 254
NAVSEAINST 4790.8B
B-9 the entire configuration data submitted on the previous CK is in error, fill in ALL the blocks with the corrected data and circle the entire form. Otherwise, fill in only the applicable blocks with the correct data and draw a circle around that block. B-1.7 Correct A Data Element Error in the Ship's Cosal or Cosal Indexes, or Other Such Documents Check the block (CONFIG FILE CORR) at the top right portion of the CK form. In SECTION I, enter a new JCN in Blocks 1, 2, and 3. In SECTION I, enter a new JCN in Blocks 1, 2, and 3. In SECTION II, Block 12 for "JOB DESCRIPTION" insert the words "CORRECTION OF COSAL", or a description of the type of correction. If the APL is to be corrected, enter the words "CHANGE APL FROM ______" and enter the incorrect APL number. In SECTION III, enter in Block 13 the component noun name from the SCLSIS Index report, COSAL, etc…. Enter in Block 15 code "C" for "correction". Enter the EIC of the component in Block 20. If the correction is for HM&E equipment, also enter the APL in Block 18. Enter the applicable RIN in Block 28. These are the only required data elements that need to be reported along with the corrected information. Next, fill in any other applicable blocks with data. Draw a circle around all blocks with changed information. B-1.8 Report an Equipment Record Addition/Deletion Complete the CK as described for "CORRECTING A DATA ELEMENT IN THE SHIP'S COSAL" in the above paragraph, with the following exceptions: In SECTION II, Block 13 enter the words "ON BOARD - NOT COSAL SUPPORTED" or "NOT ON BOARD - COSAL SUPPORTED", as appropriate. In SECTION III Block 15, enter action code "A" for equipment on board but not COSAL supported, or action code "D" for equipment that is not on board but is COSAL supported. For an equipment "ADD", also provide as much additional information as possible (e.g., Serial Number, Next Higher Assembly, if applicable, Location, Work Center, EIC, Nameplate Data, MIP, TMs, etc.). For equipment DELETE, provide the RIN in Block 28 if applicable. B-1.9 Report the Turn-In/Receipt of Portable Electrical/ Electronic Test Equipment (Peete) Check the CK Block for "CONFIG FILE CORR" and then follow standard procedures described for "CORRECTING A DATA ELEMENT IN THE SHIP'S COSAL" in the above paragraph. Downloaded from https://www.everyspec.com
p. 255
APPENDIX B-10 B-1.10 Handling Procedures An original and three copies each of the basic CK and related continuation pages are required for documentation. The completed forms are submitted to the work center supervisor and then to the division officer, each of whom reviews the forms for completeness and accuracy and initials in the appropriate blocks at the bottom of each form.
The division officer then forwards all copies of the forms to the supply department. Supply department personnel verify/enter data such as APL/AEL, SAC, and RIN and will resolve any discrepancies noted with the maintenance work center supervisor prior to further routing. Supply department personnel will initial the appropriate block at the bottom of the forms and fill in the sequence number first digit is the last digit of the current calendar year. The remaining four digits indicate the chronological sequence of CK forms being submitted by the ship/activity for the year and retain the second copy. Supply department personnel will ensure the work center entered in Block 23 as the correct work center having primary maintenance responsibility for the equipment (not the supply department work center). The supply department should then forward the original, and first and third copies to the 3-M system coordinator. After reviewing for completeness, initialing and dating in the appropriate block, the 3-M system coordinator submits the original CK to the 3-M ADP facility serving the activity. The third copy is to be maintained in the work center as a suspense copy.
Downloaded from https://www.everyspec.com
p. 256
NAVSEAINST 4790.8B
B-11 Figure B-1: Ship’s Configuration Change Form For Component Removal Maintenance Action Downloaded from https://www.everyspec.com
p. 257
APPENDIX B-12
Figure B-2: Ship’s Configuration Change Form For Component Install Downloaded from https://www.everyspec.com
p. 258
NAVSEAINST 4790.8B
B-13
Figure B-3: Ship’s Configuration Change Form Resulting From An Alteration Downloaded from https://www.everyspec.com
p. 259
APPENDIX B-14
Figure B-4: Ship’s Configuration Change Form For An Alteration Install (continuation) Downloaded from https://www.everyspec.com
p. 260
NAVSEAINST 4790.8B
B-15
Figure B-5: Ship’s Configuration Change Form For A Correction To A Previously Submitted Change Downloaded from https://www.everyspec.com
p. 261
APPENDIX B-16
Figure B-6: Ship’s Configuration Change Form For Location Correction Downloaded from https://www.everyspec.com
p. 262
NAVSEAINST 4790.8B
B-17
Figure B-7: Ship’s Configuration Change Form for COSAL Add Downloaded from https://www.everyspec.com
p. 263
APPENDIX B-18
Figure B-8: Ship’s Configuration Change Form for COSAL Delete Downloaded from https://www.everyspec.com
p. 264
NAVSEAINST 4790.8B
B-19
B-2 SHIP'S MAINTENANCE ACTION FORM (NAVSEA 4790/2K) The NAVSEA 4790/2K Form is used for reporting deferred maintenance actions, and the completion of those maintenance actions that do not result in a configuration change. To report completion of a configuration change, refer to the instructions for using the NAVSEA 4790/CK Form.
An original and three copies of the NAVSEA 4790/2K Form are required for deferring a maintenance action. The originals and third copy are forwarded to the automated data processing facility serving the activity. The first and third copy is retained by the issuing activity. The first copy is submitted when reporting the completion of the maintenance action. The second copy is retained until completion of the maintenance action is reflected in the CSMP and then may be destroyed.
Two blocks at the top of the form are used to specify what type of maintenance action is being reported, a deferral "DEFL", or a completion "COMP". The rest of the form is separated into six sections. (A partially completed maintenance action which results in configuration changes, and complete, or partial accomplishment of an alteration should be reported on the NAVSEA 4790/CK Form). There are six sections:
a. SECTION I - IDENTIFICATION. This section is used to identify the equipment or system on which maintenance actions are being reported.
b. SECTION II - DEFERRAL ACTION. This section, filled in when reporting a deferral of a maintenance action, indicates ship's force man-hours expended up to the time of deferral, the date of deferral, ship's force man-hours remaining, and required completion date (if necessary).
c. SECTION III - COMPLETED ACTION. This section is filled in when reporting the completion of a maintenance action, and special reporting blocks used when reporting maintenance actions on selected equipment.
d. SECTION IV - REMARKS/DESCRIPTION. This section is filled in when reporting the deferral of a maintenance action. The type of information recorded includes remarks that describe what is wrong. What caused the failure or malfunction, maintenance to be performed, the names of personnel involved in the maintenance action, a priority and availability assignment Downloaded from https://www.everyspec.com
p. 265
APPENDIX B-20 and Signatures by management personnel who screened the maintenance action.
e. SECTION V - SUPPLEMENTARY INFORMATION. This section issued by the reporting activity to provide necessary information pertaining to maintenance actions that are required or onboard (e.g., technical manuals, blueprints, etc.). This section is also used by the repair activity in planning, scheduling, and controlling the repair activity work.
f. SECTION VI - REPAIR ACTIVITY PLANNING/ACTION. This section is used by the repair activity for planning, estimating and scheduling purposes, and can be used to report work accomplishment by an internal department work center or by an external activity not under an ADP system.
NOTE:
Examples of completed NAVSEA 4790/2K forms for various reporting situations can be found following these written instructions. B-2.1 Procedures for Documenting A Deferred Maintenance Action Place an "X" in the block titled "DEFL" at top of form.
B-2.1.1 Section I - Identification
Block A Enter SHIP'S NAME
Block B Enter SHIP'S HULL NUMBER
JOB CONTROL NUMBER (Blocks 1 - 3):
Block 1 SHIP'S UIC: Enter the UIC of the activity initiating the maintenance action.
Block 2 WORK CENTER: Enter the Work Center code of the work center initiating the maintenance action. For ships, a four-position work center code will be entered. For repair departments of tenders, SIMAs, RMC’s, and other IMAs, a three-digit code has been assigned. The three -digit codes are entered left- to-right leaving the right most position blank.
Block 3 JOB SEQ. NO.: Enter the character job sequence number assigned by the work center supervisor. This Downloaded from https://www.everyspec.com
p. 266
NAVSEAINST 4790.8B
B-21 is an entry assigned sequentially from the SFWL/JSN Log.
Block 4 APL/AEL (Allowance Parts List/Allowance Equipment List): Enter the APL/AEL of the equipment being reported. These numbers are found in the COSAL or SCLSIS Index Report. An example of an APL would be "882170236" and an AEL would be "2-260034096."
Block 5 EQUIPMENT NOUN NAME: Enter the equipment nomenclature/description on which maintenance is being reported. The equipment nomenclature/ description should be the same as that identified by the Equipment Identification Code (EIC) and is limited to 16 positions. Standard abbreviations can be used if clarity is retained. For electronic equipment’s having an Army-Navy (AN) designation, it will be substituted for the equipment nomenclature.
Block 6 WHEN DISCOVERED (WND): Enter the code that best identifies when the need for maintenance was discovered.
Code Description
1 Lighting Off or Starting 2 Normal Operation 3 During Operability Tests 4 During Inspection 5 Shifting Operational Modes 6 During PMS 7 Securing 8 During AEC (Assessment of Equipment) Program 9 No failure, PMS Accomplishment Only 0 Not Applicable (use when reporting printing services, etc.)
Block 7 STATUS (STA): Enter the code that most accurately describes the effect of the failure or malfunction on the operational performance capability of the equipment when the need for maintenance was first discovered.
Code Description
1 Operational 2 Non-Operational Downloaded from https://www.everyspec.com
p. 267
APPENDIX B-22 Code Description
3 Reduced Capability 0 Not Applicable (use if reporting printing services, etc.)
Block 8 CAUSE (CAS): Enter the code that best describes the cause of the failure or malfunction when the need for maintenance was first discovered. (Refer to Appendix A, data element "CAUSE" for an expanded definition of the allowable codes/values).
Code Description
1 Abnormal Environment 2 Manufacturer/Installation Defects 3 Lack of Knowledge or Skill 4 Communications Problem 5 Inadequate Instruction/Procedure 6 Inadequate Design 7 Normal Wear and Tear 0 Other or No Malfunction
Block 9 DEFERRAL REASON (DFR): Enter the deferral reason code which best describes the reason the maintenance cannot be done at the time of deferral. (Refer to Appendix A, data element "DEFERRAL REASON" for an expanded definition of the allowable codes/values).
Code Deferral Reason
1 Due to Ship's Force Work Backlog/Operational Priority 2 Lack of Material 3 No Formal Training on this Equipment 4 Formal Training Inadequate for this Equipment 5 Inadequate School Practical Training 6 Lack of Facilities/Capabilities 7 Not Authorized for Ship's Force Accomplishment 8 For Ship's Force Overhaul or Availability Work List 9 Lack of Technical Documentation 0 Other - or Not Applicable
Block 10 This Block is reserved for TYCOM directed applications. Refer to TYCOM instruction for use.
Downloaded from https://www.everyspec.com
p. 268
NAVSEAINST 4790.8B
B-23 Block 11 This Block is reserved for TYCOM directed applications. Refer to TYCOM instruction for use.
Block 12 This Block is reserved for TYCOM directed applications. Refer to TYCOM instruction for use.
Block 13 IDENT./EQUIPMENT SERIAL NUMBER: Enter the identification or serial number of the equipment or system on which maintenance is being deferred. For HM&E equipment, enter the Valve Mark/Electric Symbol Number (ESN) or Primary Identification Number. For electronic equipment, enter the manufacturer's serial number of the equipment or system on which maintenance is being deferred.
Block 14 EIC: Enter the Equipment Identification Code of the component, equipment, subsystem, or system for which the maintenance is being reported.
Block 15 SAFETY HAZARD: Enter an "X" or applicable safety code if the maintenance action describes a problem or condition which has caused, or has the potential to cause serious injury to personnel or material. A brief explanation must be included in the Remarks/Description field (Block 35). For example: "RE-INSPECTION OF SEPARATOR FOR PRESENCE OF OIL AFTER RINSE. MRC A-27 EVIDENTLY NOT DONE. PRESENCE OF OIL RESULTED IN FIRE IN HP AIR SYSTEM WHEN COMPRESSOR OPERATED UNDER LOAD. FIRE BADLY BURNED VALVE AHP-287, REQUIRING REPLACEMENT."
The ship's 3-M system coordinator will forward a copy of all NAVSEA 4790/2K documentation having an entry in this field to the safety officer for review.
(Refer to Appendix A, data element "SAFETY HAZARD" for an expanded definition of the allowable codes/values).
Code Description
1 Critical Safety or Health Deficiency-Correct Immediately 2 Serious Safety or Health Deficiency- Suspension of Equipment/System/Space Use is Required Downloaded from https://www.everyspec.com
p. 269
APPENDIX B-24 Code Description
3 Moderate Safety or Health Deficiency-Waiver of Equipment/System/Space Use is granted Pending Correction of the Item 4 Minor Safety or Health Deficiency 5 Negligible Safety or Health Deficiency 0 Maintenance Action is Not Safety Related
NOTE:
Codes "6" through "9" may be locally assigned by TYCOMs for additional safety codes required.
Block 16 LOCATION: Enter the location (compartment number, deck, frame, or side notation), that best describes the location of the equipment requiring maintenance as identified in Block 13. If none of the above mentioned location identifications are appropriate, enter description of the location (e.g., FANTAIL, FLIGHT DECK, etc.).
Block 17 WHEN DISCOVERED DATE: Enter the Julian date when the equipment or system failure or malfunction was discovered.
Block 18 ALTERATIONS (SHIPALT, ORDALT, Fld. Chg., etc.): If reporting the deferral of a an alteration:
SHIPALT . Enter the alteration identification exactly as it appears on the Ship Alteration (SHIPALT) Record. Record the alteration type "SA" in the first two positions, ship type starting in position three, and the alteration number starting in the 7th position of the block (i.e., SASSBNf342130). Enter the title code from the alteration record in the last right-hand position of the block.
OTHER Alteration Types. Enter the alteration type character code in the first two positions of the block. Leave the third position blank and enter the alteration number starting in position four (i.e., OA f96999, FC 29, TY 0132).
If an alteration identification number is not provided with the alteration record, leave blank. Downloaded from https://www.everyspec.com
p. 270
NAVSEAINST 4790.8B
B-25 Following are the authorized alteration prefix codes:
SA = SHIP ALTERATION OA = ORDNANCE ALTERATION BA = BOAT ALTERATION FC = FIELD CHANGE MA = MACHINERY ALTERATION SI = SYSCOM COMMAND INSTRUCTION EC = ENGINEERING CHANGE HI = HABITABILITY TY = TYCOM DIRECTION TD = TECHNICAL DIRECTIVE SP = STRATEGIC SYSTEMS PROJECT OFFICE ALTERATION SC = SERVICE CHANGE TR = TRIDENT ALTERATION EP = ENGINEERING CHANGE PROPOSAL MO = CRYPTO EQUIPMENT MODIFICATION AR = ALTERATION REQUEST. May be originated by a ship to request an alteration design. Enter and left-justify the authorized prefix "AR" followed by a blank space any number the ship assigns for its own control.
Blocks 19 through 24 - FOR INSURV USE - no entries required. See Section 2 of the Manual for specifications.
B-2.1.2 Section II - Deferral Action
Block 25 SHIP'S FORCE MAN-HOURS EXPENDED (S/F MHRS. EXP.): Enter the total man-hours (to the nearest whole hour) expended by personnel of all work centers involved in the maintenance action up to the time of deferral (include documentation time which should not exceed 1 hour).
Block 26 DEFER. DATE: Enter the Julian date when the maintenance action was deferred. An example of a deferral on 11 January 1994 would be: "4f11".
Block 27 SHIP'S FORCE MAN-HOURS REMAINING (S/F MHRS. REM.): Enter the estimated number of ship's force man-hours remaining to complete the maintenance action. Round off to the nearest whole hour. If the TYCOM allows an automated close out of the deferral by the IMA, Downloaded from https://www.everyspec.com
p. 271
APPENDIX B-26 the letters "AUTO" will be entered. This is a request to the IMA to complete the maintenance action with no further documentation from the shop after the job has been accepted by the originator (authorized signature). If the originating ship does not receive CSMP support from the IMA doing the work, do not use the "AUTO" close out feature.
Block 28 DEADLINE DATE: This is an optional entry. The originator of the deferred action may enter the latest possible Julian date that outside assistance and ship's force work must be completed.
B-2.1.3 Section III - Completed Action
Blocks 29 through 33 - USED FOR REPORTING THE COMPLETION OF A MAINTENANCE ACTION
Block 34 METER READING: If the equipment has a time meter and is on the SEL, the reading (to the nearest whole hour) at the time of failure is entered in this block. If the equipment has more than one meter, designate the meter being recorded in Block 35 "REMARKS" using the letters "METRED" followed by the meter designator. An asterisk (*) must precede and follow the meter designation. Example: *METRED- 1A2M1*.
B-2.1.4 Section IV - Remarks/Description
Block 35 REMARKS/DESCRIPTION: Enter remarks relating to the maintenance action. These remarks should be brief, but complete and meaningful. Remarks should state what is wrong, and what caused the failure (if known); and what must be done to correct the problem. Separate the two statements with "XXX". For example, "HIGH PITCHED SQUEAL OF PUMP SHAFT, GAUGE READING ABOVE RED LINE ON #2 PUMP, SSG CASING IS EXTREMELY HOTXXXINVESTIGATE AND REPAIR AS NECESSARY." If more space is needed, check Block 36 "CONT. SHEET" and continue the remarks on a second form using the same JCN. Include the statement "2L USED" if the supplemental OPNAV/2L form is used for drawings or other supplemental information.
Downloaded from https://www.everyspec.com
p. 272
NAVSEAINST 4790.8B
B-27 NOTE:
The remarks should not include statements explaining what has been coded in another place of the form; i.e., "DEFERRAL REASON 2 = LACK OF MATERIAL".
Block 36 CONT. SHEET: Enter an "X" in this block if the "REMARKS" are continued on additional 2K forms. No more than three additional NAVSEA 4790/2K forms can be used. B-2.2 Procedures for Using NAVSEA 4790/2K Continuation Pages On each additional 2K form used for the continuation of "REMARKS" (no more than three additional NAVSEA 4790/2K forms can be used), enter the JCN of the first form and continue with the remarks in Section IV. In the top margin of each continuation page, insert the words "Page 2", "Page 3", etc….
Block 37 CSMP SUMMARY: Enter a condensed description of the problem. The work center supervisor is to ensure the summary succinctly captures the meaning of the REMARKS/DESCRIPTION (Block 35) narrative. The CSMP summary conveys to management the significance of the JCN (maintenance action). The CSMP summary is displayed on management reports, as opposed to the entire narrative of the REMARKS block.
Block 38 FIRST CONTACT/MAINT. MAN: Printed name of the senior person knowledgeable in the specifics of the JCN (maintenance action).
Block 39 RATE: Enter the rate of the first contact/maintenance person. Examples are:
Rank/Rate Code Entry
Officers OFF ET1 ET1 Civilian CIV GMG2 GMG2 FTGSN FTGN EMFN EMFN FN FN
Block 40 SECOND CONTACT/SUPERVISOR: Initialed by the supervisor of the first contact/maintenance person Downloaded from https://www.everyspec.com
p. 273
APPENDIX B-28 after screening the maintenance action for completeness and accuracy.
Block 41 PRI: Enter the appropriate priority code. Refer to Appendix A for an expanded definition of the allowable codes/values.)
Code Description
1 Mandatory 2 Essential 3 Highly Desirable 4 Desirable
Block 42 T/A: Enter the type availability (T/A) code for the type availability recommended for performance of the deferral.
Code Description 1 Depot (shipyard or ship repair facility) 2 Intermediate Maintenance Activity (tender, repair ship, etc.) 3 TYCOM Support Unit (floating dry dock, etc., or technical assistance from NAVSEACOMBATSYSENGSTA or FTSCPAC/FTSCLANT or contractor representative) 4 Ship's Force 0 Not Applicable
Block 43 INTEGRATED PRIORITY: If the maintenance is to be done by an outside activity, the ship's engineer may rank departmental deferrals by integrated priority. A sequential number may be placed in this block to indicate its priority relative to other deferred work for a given availability.
Block C DIV. INIT: Initialed by the division officer after screening the document.
Block D DEPT. INIT: Initialed by the department head after screening the document.
Block E COMMANDING OFFICER'S SIGNATURE: Required on all deferrals for outside assistance, the commanding officer or authorized representative must sign the deferral.
Downloaded from https://www.everyspec.com
p. 274
NAVSEAINST 4790.8B
B-29 Block F TYCOM AUTHORIZATION: This block is reserved for the signature of the TYCOM representative screening the deferral. This is usually applicable when direct routing from ship to TYCOM for deport emergent work is employed.
Blocks 44 through 46 are not completed at the time of deferral. Entries are made by the next level of management after leaving the ship (IUC and TYCOM during the screening process).
B-2.2.1 Section V - Supplementary Information
Block 47 BLUEPRINTS, TECH. MANUALS, PLANS, ETC…: Enter any TMs, blueprints, etc…, which might be of use to a repair activity providing assistance. Indicate with an "X" in the "AVAILABLE ON BOARD” – “YES/NO" block if the TM is onboard or not. B-2.3 Procedures for Documenting Internal Work Requests When it is necessary to obtain assistance from other departments within the organizational level of the ship, the NAVSEA 4790/2K Form can be used as an internal work request. If more than a single assisting work center is required, multiple copies will be prepared using the same JCN on each request.
The requesting work center prepares the number of copies required for internal control. The words "INTERNAL WORK REQUEST" is written at the top of each copy to be sent to the assisting work center(s). The following blocks are used:
B-2.3.1 Section I – Identification
Document all of this section. See "PROCEDURES FOR DOCUMENTING A DEFERRED MAINTENANCE ACTION"
B-2.3.2 Section IV - Remarks/Description
Block 35 REMARKS/DESCRIPTION: Describe the tasks required of the assisting work Center (AWC).
B-2.3.3 Section VI - Repair Activity Planning/Action
Block 49 REPAIR WORK CENTER (W/C): Enter the assisting work center's code.
Block 55 REPAIR ACTIVITY UIC: Enter the organization unit's Unit Identification Code (UIC). This will be the Downloaded from https://www.everyspec.com
p. 275
APPENDIX B-30 same as Block 1 except when the ship is being assisted by a non-reporting outside activity, and the outside activity's UIC will be entered.
Block 56 WORK REQ. ROUTINE: Enter the appropriate Expanded Ship Work Breakdown Structure (ESWBS), Ship Work Authorization Boundary (SWAB), Ship Work Line Item Number (SWLIN), etc., as directed by the TYCOM. B-2.4 Procedures for Documenting Screening Information On Deferred Maintenance Actions Used by other activities, such as, IUCs, TYCOM representatives, and IMAs for screening, planning, and scheduling.
B-2.4.1 Section IV - Remarks/Description
Block F TYCOM AUTHORIZATION: This block is reserved for the signature of the TYCOM representative screening the deferral.
Block 44 IUC: The IUC or designated representative screening the deferral enters the recommendation as to the action to be taken. See the allowable codes following Block 45 (TYCOM) below.
Block 45 TYCOM: The TYCOM or designated representative screening the deferral will enter the action to be taken.
Code Description
1 Depot (shipyard or ship repair facility) Accomplish 1A Depot Assisted by Ship's Force 1S Ship to Shop 1M Accomplish with Modification 2 Intermediate Maintenance Activity (IMA) (tender/repair ship, etc.) Accomplish 2A IMA Assisted by Ship's Force 2S Ship to Shop 2M Accomplish with Modification 3 TYCOM Support Unit (TSU) (floating dry dock, etc.) Accomplish or Technical Assistance from NAVUNDERSEAWARCENDET/FTSCPAC/FTSCLANT Contractor Representative 3A TSU Assisted by Ship's Force 3S Ship to Shop Downloaded from https://www.everyspec.com
p. 276
NAVSEAINST 4790.8B
B-31 Code Description
3M Accomplish with Modification 4 Ship's Force Accomplish 5 Deferred 5A Insufficient Time in the Availability to Complete the Task 5B Lack of Shipyard Capability
5C Lack of Material 5D Lack of Funds 5E Not Required During this Availability 5F General 6 Not Authorized 6A Not Technically Justified 6B Covered by an Existing Ship Alteration 6C Duplicate of Another Job Control Number (JCN) 6D Not Cost Effective 6E General 8* Disapproved 9** Remove from Current Ship's Maintenance Project (CSMP). Pass to history (to be assigned by TYCOM only)
NOTE:
* This screening code disapproves the accomplishment of a work item by an outside activity. It does not prevent entry of the deferral into the CSMP, which is the decision of the commanding officer.
NOTE:
** This screening code is restricted to the removal of INSURV items from the CSMP for which, in the opinion of the ship's IUC and TYCOM, the ship has no responsibility for accomplishment.
Downloaded from https://www.everyspec.com
p. 277
APPENDIX B-32 NOTE:
The first character of the IUC and/or TYCOM screening code should be entered in the appropriate field. The second character, when used, should be entered in the space just below it.
Block 46 (A-L) SPECIAL PURPOSE: Use of these codes indicates the quality control and quality assurance standards are required. Refer to TYCOM instructions for additional information relative to these blocks
Enter the code in the designated block 46A through 46L to show quality control and/or quality assurance requirements.
Block 46A The department head will enter the KEY EVENT code from the ISIC provided Key Event Schedule. (Refer to Maintenance Manual Volume III Section 7.)
Block 46B Enter the code "SS" if the job requires work within SUBSAFE boundaries or involves SUBSAFE materials. (Refer to COMSUBLANT/COMSUBPACINST 4855.2.)
Block 46C Enter the code "L1" if the job requires work within Level I boundaries or involves Level I material. (Refer to COMSUBLANT/COMSUBPACINST 4855.2.)
Block 46D Enter the code "08" if the job is associated with nuclear equipment. Refer to NAVSEAINST 9210.4A (NOTAL)).
Block 46E Enter the code "RC" if the job requires radiological controls (RADCON). (Refer to NAVSEA 389-0153.)
Block 46F Enter the code "DD" if the job requires drydocking to accomplish.
Block 46G Enter the code "NC" for critical noise deficiencies or "NP" for potential radiated noise deficiencies.
Block 46H Reserved for future use.
Block 46I Reserved for future use.
Block 46J Reserved for future use.
Downloaded from https://www.everyspec.com
p. 278
NAVSEAINST 4790.8B
B-33 Block 46K Reserved for future use.
Block 46L Enter the code assigned to the visiting activity. This will identify the visiting activity as the originator of the deferral.
B-2.4.2 Section V - Supplementary Information
Block 47 BLUEPRINTS, TECHNICAL MANUALS, PLANS, ETC: The repair activity can use this block during the work request planning in much the same manner as the originator. Information that might be of use in the accomplishment of the maintenance can be entered (e.g., TMs, blueprints, etc.).
Block 48 PREARRIVAL/ARRIVAL CONFERENCE ACTION/REMARKS: The repair activity may enter any remarks considered necessary to facilitate repairs.
B-2.4.3 Section VI - Repair Activity Planning/Action
Block 49 REPAIR W/C: Enter the character code of the lead work center assigned to the job. Refer to Appendix A data element "IMA REPAIR WORK CENTER" for a listing of IMA work center codes.
Block 50 EST. MHRS.: Enter the total number of estimated man- hours required by the lead work center to complete the job.
Block 51 ASST. REPAIR W/C: Enter the three or four character code of the first work center assigned to assist the lead work center on the job being planned. If more than one assist work center is required, check Block 36 to indicate a continuation page is being used. On the continuation page (new 2K form), fill in Blocks 1, 2, 3 with the same JCN of the original 2K. In Block 51, enter the second assist repair work center's code. No more than two assist work centers (two supplemental 2K forms) can be submitted.
Block 52 ASST. EST. MHRS: Enter the total number of estimated man-hours required by the assist work center to complete its portion of the job.
Block 53 SCHED. START DATE: Enter the Julian date that the work on the job is to begin. Downloaded from https://www.everyspec.com
p. 279
APPENDIX B-34
Block 54 SCHED. COMP. DATE: Enter the Julian date that all work on the job is scheduled to be completed by the repair activity.
Block 55 REPAIR ACTIVITY UIC: Enter the unit identification code of the repair activity performing the work for the originating ship.
Block 56 WORK REQ. ROUTINE: Enter the appropriate Expanded Ship Work Breakdown Structure (ESWBS), Ship Work Authorization Boundary (SWAB), Ship Work Line Item Number (SWLIN), etc., as directed by the TYCOM.
Blocks 57 through 63 - Used to identify depot estimates on individual CSMP items from the Master Job Catalog. These blocks may also be used as directed by TYCOM instruction.
Block 58 EST.: Enter the total material costs estimated to be required to complete the job.
Block 59 EST. MATERIAL COSTS: Enter an estimate of the total material costs required to complete the job.
Block 60 EST. TOTAL COST: Enter an estimate of the total cost required to complete the job. (Add Blocks 58 and 59.)
Block 61 JOB ORDER NUMBER: Enter Job order number assigned by the activity performing the work.
Block 62 LEAD P&E CODE: Enter the code assigned to the lead planning and scheduling organization.
Block 63 DATE OF EST.: Enter the date that the repair activity's planning action was completed. B-2.5 Procedures for Documenting A Completed Maintenance Action Previously Deferred Blocks A, B, and applicable Blocks 1 through 47 have previously been filled.
The maintenance person shall report completion of a previously deferred maintenance action by using the copy of the NAVSEA 4790/2K retained onboard when the maintenance action was deferred. If there is no record (paper) copy of the original 2K, and the maintenance action is on the CSMP, enter the JCN on Downloaded from https://www.everyspec.com
p. 280
NAVSEAINST 4790.8B
B-35 a blank 2K form, and without providing all the deferred maintenance information, enter the completion data in Section III. If the word "AUTO" has been entered in Block 27 as directed by the TYCOM, submission of a completed maintenance action by the originating ship may not be necessary.
B-2.5.1 Section III - Completed Action
Block 29 ACT. TKN: Enter the code that best describes the action taken to complete the maintenance.
Code Description
1 Maintenance Action Completed; Parts Drawn from Supply 2 Maintenance Action Completed; Required Parts Not Drawn from Supply (local manufacture, pre-expended bins, etc.) 3 Maintenance Action Completed; No Parts Required
NOTE:
The following second character codes can be used with the above Action Taken codes 1, 2, or 3 as directed by the TYCOM:
A Maintenance Requirement Could Have Been Deferred B Maintenance Requirement Was Necessary C Maintenance Requirement Should Have Been Done Sooner M High Cost Repairs T The Equipment Being Reported Had a Time Meter
Code Description
4 Canceled (When this code is used, the deferral will be removed from the CSMP. This code is not to be used with INSURV, safety, or priority 1 or 2 deferrals screened for accomplishment by the TYCOM or IUC.) 7 Maintenance Action Completed; 2-M (Miniature/Microminiature Electronic Modules) Capability Utilized.
NOTE:
The following second character codes can be used with Action Taken Code 7 to better describe the action taken:
Downloaded from https://www.everyspec.com
p. 281
APPENDIX B-36 A Parts Drawn from Supply Utilized B Parts Not Drawn from Supply Utilized C Automatic Test Equipment (ATE) Utilized D ATE and Parts Drawn from Supply Utilized E ATE and Parts Not Drawn from Supply Utilized
Code Description
8 Periodic Time Meter/Cycle Counter reporting. (This code is not applicable to the "FINAL ACTION" code reported by the repair activity.) 9 Maintenance Action Completed; 3M Fiber Optic Repair
NOTE:
The following second character codes can be used with Action Taken Code 9 to better describe the action taken:
A FOTE, multimode ST MQJs utilized B FOTE, multimode heavy duty MQJs utilized C FOTE, multimode rotary mechanical splice MQJs utilized D FOTE, single mode ST MQJs utilized E FOTE, single mode heavy duty MQJs utilized F FOTE, multimode specialty MQJs utilized G FOTE, single mode specialty MQJs utilized H FOTE, not available I Standard MQJs not available J Specialty MQJs not available
Code Description
0 None of the Above
Block 30 S/F MHRS: Enter the total man-hours (to the nearest whole hour) that ship's force expended doing the maintenance after submitting the deferral. This includes witnessing of tests, and those man-hours expended in reinstallation, test, documentation (not to exceed 1 hour), etc.
Block 31 COMPLETION DATE: Enter the Julian date the maintenance action was completed.
Block 32 ACT. MAINT. TIME: Enter the total clock hours (to the nearest whole hour) during which ship force Downloaded from https://www.everyspec.com
p. 282
NAVSEAINST 4790.8B
B-37 maintenance was actually performed. This should include time for troubleshooting, but not delays.
Block 33 TI: Enter a single numeral (1 through 9) to indicate, to the nearest 10%, the percentage of active maintenance expended in troubleshooting. For example, if no troubleshooting is involved, enter "f", "2" for 20%, "3" for 30%, "7" for 70%, etc.
Block 34 METER READING: There is no entry required on the completed deferral action. (Refer to Block 34 instructions for DOCUMENTING A DEFERRED MAINTENANCE ACTION above.)
Block 35 REMARKS/DESCRIPTION: When the "what must be done" statement on the original deferral accurately describes the work which was done, no further entries are required. If remarks in addition to the original remarks entered are needed to describe the work done, draw a line through all the previous remarks and starting on the next line, describe what was done, and any additional information considered significant. If additional space is needed for the completed action description, use up to three continuation pages.
B-2.5.2 Section IV - Remarks/Description
(Used by the Repair Activity when Reporting a Completed Maintenance Action). This type of completed work request is to be provided to the ship for 3-M processing.
Block 64 FINAL ACT.: Enter the code that best describes the final action taken to complete the maintenance. (Refer to Block 29 above for "ACTION TAKEN" allowable codes/values). In addition, the following codes can be used:
5A Partially Completed Alteration 5B Fully Completed Alteration 5C Fully Completed Equivalent to Alteration 5D Alteration Directive Not Applicable 6 Rejected Work Request (add suffix below for reason) A Ship's Force/Standard Stock Item B Excessive Shop Workload/Insufficient Availability Downloaded from https://www.everyspec.com
p. 283
APPENDIX B-38 C Lack of Skills D Lack of Facilities E Lack of Test or Calibration Equipment F Lack of Parts/Material G Lack of Documentation H Lack of Funds I Other (record the explanation in "Remarks")
Block 65 MHRS. EXPENDED: Enter the man-hours expended on the last day the repair work center is involved in the work Request (NOT the total man-hours of the work request).
Block 66 DATE COMPLETED: Enter the Julian date the work request is completed and signed off by the requesting ship.
Block G COMPLETED BY: The signature and rank/rate of the individual authorized by the tended ship to verify the acceptability of work performed is entered in this block.
Block H ACCEPTED BY: The signature and rank or rate of the individual authorized by the tended ship to verify the acceptability of work performed. Completion of this block is mandatory when a 2K is used to report completion of a previously deferred maintenance action. B-2.6 Procedures for Documenting A Completed Maintenance Action without prior deferral
Place an "X" in the block titled "COMP" at top of form.
B-2.6.1 Section I - Identification
Block A Enter SHIP'S NAME
Block B Enter SHIP'S HULL NUMBER
JOB CONTROL NUMBER (Blocks 1 - 3):
Block 1 SHIP'S UIC: Enter the UIC of the activity initiating the maintenance action.
Block 2 WORK CENTER: Enter the Work Center code of the work center initiating the maintenance action. For Downloaded from https://www.everyspec.com
p. 284
NAVSEAINST 4790.8B
B-39 Ship's, a four position work center code will be entered. For repair departments of tenders, SIMAs, RMC’s, and other IMAs, a digit code has been assigned. The digit code is entered left-to-right leaving the right most position blank.
Block 3 JOB SEQ. NO.: Enter the character job sequence number assigned by the work center supervisor. This is an entry assigned sequentially from the SFWL/JSN Log.
Block 4 APL/AEL (Allowance Parts List/Allowance Equipment List): Enter the APL/AEL of the equipment being reported. These numbers are found in the COSAL or SCLSIS Index Report. An example of an APL would be "882170236" and an AEL would be "2-260034096."
Block 5 EQUIPMENT NOUN NAME: Enter the equipment nomenclature / description on which maintenance is being reported. The equipment nomenclature/description should be the same as that identified by the Equipment Identification Code (EIC) and is limited to 16 positions. Standard abbreviations can be used if clarity is retained. For electronic equipment having an Army-Navy (AN) designation, it will be substituted for the equipment nomenclature.
Block 6 WHEN DISCOVERED (WND): Enter the code that best identifies when the need for maintenance was discovered.
Code Description
1 Lighting Off or Starting 2 Normal Operation 3 During Operability Tests 4 During Inspection 5 Shifting Operational Modes 6 During PMS 7 Securing 8 During AEC (Assessment of Equipment Condition) 9 No Failure, PMS Accomplishment Only 0 Not Applicable (use when reporting printing services, etc.)
Downloaded from https://www.everyspec.com
p. 285
APPENDIX B-40 Block 7 STATUS (STA): Enter the code that most accurately describes the effect of the failure or malfunction on the operational performance capability of the equipment when the need for maintenance was first discovered.
Code Description
1 Operational 2 Non-Operational 3 Reduced Capability 0 Not Applicable (use if reporting printing services, etc.)
Block 8 CAUSE (CAS): Enter the code that best describes the cause of the failure or malfunction when the need for maintenance was first discovered. (Refer to Appendix A, data element "CAUSE" for an expanded definition of the allowable codes/values).
Code Description
1 Abnormal Environment 2 Manufacturer/Installation Defects 3 Lack of Knowledge or Skill 4 Communications Problem 5 Inadequate Instruction/Procedure 6 Inadequate Design 7 Normal Wear and Tear 0 Other or No Malfunction
Block 9 DEFERRAL REASON (DFR): Leave blank.
Block 10 Block is reserved for TYCOM directed applications. Refer to TYCOM instruction for use.
Block 11 Block is reserved for TYCOM directed applications. Refer to TYCOM instruction for use.
Block 12 Block is reserved for TYCOM directed applications. Refer to TYCOM instruction for use.
Block 13 IDENT./EQUIPMENT SERIAL NUMBER: Enter the identification or serial number of the equipment or system on which maintenance is being deferred. For Hull, Mechanical & Electrical (HM&E) equipment, enter the Valve Mark/Electric Symbol Number (ESN) or Downloaded from https://www.everyspec.com
p. 286
NAVSEAINST 4790.8B
B-41 Primary Identification Number. For electronic equipment, enter the manufacturer's serial number of the equipment or system on which maintenance is being deferred.
Block 14 EIC: Enter the Equipment Identification Code of the component, equipment, subsystem, or system for which the maintenance is being reported.
Block 15 SAFETY HAZARD: Enter an "X" or applicable safety code if the maintenance action describes a problem or condition which has caused, or has the potential to cause serious injury to personnel or material. A brief explanation must be included in the Remarks / Description field (Block 35). For example: "RE- INSPECTION OF SEPARATOR FOR PRESENCE OF OIL AFTER RINSE. MRC A-27 EVIDENTLY NOT DONE. PRESENCE OF OIL RESULTED IN FIRE IN HP AIR SYSTEM WHEN COMPRESSOR OPERATED UNDER LOAD. FIRE BADLY BURNED VALVE AHP-287, REQUIRING REPLACEMENT."
NOTE:
The ship's 3-M system coordinator will forward a copy of all NAVSEA 4790/2K documentation having an entry in this field to the safety officer for review. (Refer to Appendix A, data element "SAFETY HAZARD" for an expanded definition of the allowable codes/values).
Code Description
1 Critical Safety or Health Deficiency-Correct Immediately 2 Serious Safety or Health Deficiency- Suspension of Equipment/System/Space Use is Required 3 Moderate Safety or Health Deficiency-Waiver of Equipment/System/Space Use is granted Pending Correction of the Item 4 Minor Safety or Health Deficiency 5 Negligible Safety or Health Deficiency 0 Maintenance Action is Not Safety Related
NOTE:
Codes "6" through "9" may be locally assigned by TYCOMs for additional safety codes required. Downloaded from https://www.everyspec.com
p. 287
APPENDIX B-42
Block 16 LOCATION: Enter the location (compartment number, deck, frame, or side notation), that best describes the location of the equipment requiring maintenance as identified in Block 13. If none of the above mentioned location identifications are appropriate, enter description of the location (e.g., FANTAIL, FLIGHT DECK, etc.).
Block 17 WHEN DISCOVERED DATE: Enter the Julian date when the equipment or system failure or malfunction was discovered.
Block 18 ALTERATIONS: Leave blank. If the completed maintenance action resulted in a configuration change or alteration, refer to the instructions for submitting an NAVSEA 4790/CK form.
Blocks 19 through 24 - FOR INSURV USE - no entries required. See Section 2 for details.
B-2.6.2 Section II - Deferral Action (Block 25 - 28) - Leave blank.
B-2.6.3 Section III - Completed Action
Block 29 ACT. TKN.: Enter the code that best describes the action taken to complete the maintenance.
Code Description
1 Maintenance Action Completed; Parts Drawn from Supply 2 Maintenance Action Completed; Required Parts Not Drawn from Supply (local manufacture, pre-expended bins, etc.) 3 Maintenance Action Completed; No Parts Required
NOTE:
The following second character codes can be used with the above Action Taken codes 1, 2, or 3 as directed by the TYCOM:
A Maintenance Requirement Could Have Been Deferred B Maintenance Requirement Was Necessary C Maintenance Requirement Should Have Been Done Sooner M High Cost Repairs T The Equipment Being Reported Had a Time Meter Downloaded from https://www.everyspec.com
p. 288
NAVSEAINST 4790.8B
B-43
Code Description
4 Canceled (When this code is used, the deferral will be removed from the CSMP. This code is not to be used with INSURV, safety, or priority 1 or 2 deferrals screened for accomplishment by the TYCOM or IUC.) 7 Maintenance Action Completed; 2-M (Miniature/Microminiature Electronic Modules) Capability Utilized.
NOTE:
The following second character codes can be used with Action Taken Code 7 to better describe the action taken:
A Parts Drawn from Supply Utilized B Parts Not Drawn from Supply Utilized C Automatic Test Equipment (ATE) Utilized D ATE and Parts Drawn from Supply Utilized E ATE and Parts Not Drawn from Supply Utilized
Code Description
8 Periodic Time Meter/Cycle Counter reporting. (This code is not applicable to the "FINAL ACTION" code reported by the repair activity.) 9 Maintenance Action Completed; 3M Fiber Optic Repair
NOTE:
The following second character codes can be used with Action Taken Code 9 to better describe the action taken:
A FOTE, multimode ST MQJs utilized B FOTE, multimode heavy duty MQJs utilized C FOTE, multimode rotary mechanical splice MQJs utilized D FOTE, single mode ST MQJs utilized E FOTE, single mode heavy duty MQJs utilized F FOTE, multimode specialty MQJs utilized G FOTE, single mode specialty MQJs utilized H FOTE, not available I Standard MQJs not available Downloaded from https://www.everyspec.com
p. 289
APPENDIX B-44 J Specialty MQJs not available
Code Description
0 None of the Above
Block 30 S/F MHRS: Enter the total man-hours (to the nearest whole hour) that ship's force expended completing the maintenance. This includes time witnessing tests, man-hours expended in reinstallation, test, and documentation (not to exceed 1 hour), etc.
Block 31 COMPLETION DATE: Enter the Julian date the maintenance action was completed.
NOTE:
Blocks 32, 33, and 34 are only to be reported, if the equipment has been SEL designated.
Block 32 ACT. MAINT. TIME: Enter the total clock hours (to the nearest whole hour) during which ship's force maintenance was actually performed. This should include time for troubleshooting, but not delays.
Block 33 TI: Enter a single numeral (1 through 9) to indicate, to the nearest 10 percent, the percentage of active maintenance expended in troubleshooting. For example, if no troubleshooting is involved, enter "", "2" for 20%, "3" for 30%, "7" for 70%, etc.
Block 34 METER READING: Enter the time meter reading (to the nearest whole hour) at the time of failure. If the equipment has more than one meter, designate the meter being recorded in Block 35 "REMARKS" using the letters "METRED" followed by the meter designator. An asterisk (*) must precede and follow the meter designation. Example: *METRED-1A2M1*.
Block 35 REMARKS/DESCRIPTION: Enter remarks relating to the maintenance action. These remarks should be brief, but complete and meaningful. Remarks should state what was wrong, what caused the failure (if known) and what was done to correct the problem. If "SAFETY HAZARD" (Block 15) is checked, a description of the condition creating the hazard should be Downloaded from https://www.everyspec.com
p. 290
NAVSEAINST 4790.8B
B-45 inserted in "REMARKS". If more space is needed, check Block 36 "CONT. SHEET" and continue the remarks on a second form using the same JCN. B-2.7 Procedures for Documenting Changes, Additions, and Deletions to Previously Submitted Maintenance Actions Print in large letters the word "Correction" at the top of the form. Enter the exact JCN (Blocks 1, 2, and 3) of the original 2K previously processed. Enter only the information to be added, deleted, or changed in the applicable blocks. Circle these blocks. If the selected data elements are to be deleted, without deleting the entire document, enter dashes (one dash per tic mark) within the data block to be deleted. When changing Block 35-REMARKS/DESCRIPTION, the entire narrative must be entered so that the correct information is included. It is not possible to change just a word or two. B-2.8 Procedures to Add-On Remarks to the CSMP To add to the remarks as originally submitted, print the words "ADD-ON REMARKS" at the top of a new 2K Form. Place an "X" in the "DEFL" block at the top right of the form, and enter in Block 1, 2, and 3 the JCN or the original 2K. In Block 35 "REMARKS/DESCRIPTION", print the initials of the activity adding on to the remarks followed by a dash (-). For example, CINCPACFLT would be entered as "CPF-". Following the dash (-) enter the additional information. If it is necessary to rewrite, or change the narrative as originally submitted, use the procedures for "DOCUMENTING CHANGES, ADDITIONS, AND DELETIONS". B-2.9 Handling Procedures The NAVSEA 4790/2K Form is printed on paper that does not require carbon to make multiple copies. The original and three (3) copies of the 2K are required for documenting the maintenance action. The original and third copy shall be forwarded to the automated data processing facility serving the ship or activity. The first copy is submitted when reporting the completion of that maintenance action. The second copy is retained until completion of the maintenance action results in its removal from the CSMP; it may be destroyed. Downloaded from https://www.everyspec.com
p. 291
APPENDIX B-46
Figure B-9: Ships Maintenance Acton Form For A Deferred Maintenance Action Downloaded from https://www.everyspec.com
p. 292
NAVSEAINST 4790.8B
B-47
Figure B-10: Ships Maintenance Acton Form For A Completed Maintenance Action Without Prior Deferral Downloaded from https://www.everyspec.com
p. 293
APPENDIX B-48
Figure B-11: Ships Maintenance Acton Form Change To A Previously Submitted Deferred Maintenance Action Downloaded from https://www.everyspec.com
p. 294
NAVSEAINST 4790.8B
B-49
Figure B-12: Ships Maintenance Acton Form Add-on Remarks To A Previously Submitted Deferred Maintenance Action
Downloaded from https://www.everyspec.com
p. 295
APPENDIX B-50 B-3 SUPPLEMENTAL FORM (NAVSEA 4790/2L) This form is used to provide amplifying information (such as drawings and listings) related to a maintenance action, reported on a NAVSEA 4790/2K Form. The 2L may be used to list multiple item serial numbers and locations for which identical maintenance requirements exist from an outside activity; or to provide a list of drawings and sketches that would be helpful in the accomplishment of the maintenance.
The 2L form is retained onboard ship with the suspense copy of the corresponding 2K form that deferred the maintenance action. The 2L is never submitted to the ADP facility servicing the activity, as the data on the 2L will never be entered into the computer. However, the 2L can be attached to the original 2K or computer produced (simulated) 2K when submitted to an assisting activity. B-3.1 Special Application If a Master Job Catalog (MJC) routine has been added to the CSMP for service routines or for IMA sheet metal hose manufacturing, multiple NAVSEA 4790/2Ls may be used for the same JCN. Each 2L would result in an additional task being added to the JCN, thus accounting for man-hour expenditure for each task. Similarly, the 2L could be used to request critical hose manufacturing by referencing the MJC number and using the ship's own JCN, thus precluding the necessity to submit multiple complete NAVSEA 4790/2Ks.
The form is separated into three sections: SECTION I "IDENTIFICATION", SECTION II "REMARKS/SKETCHES", and SECTION III "AUTHENTICATION". When using the 2L, all sections of the form are to be filled out. On the NAVSEA 4790/2K Form, be sure to enter the notation "2L USED" in the "REMARKS/DESCRIPTION" section, Block 35.
NOTE:
An example of a completed NAVSEA 4790/2L form can be found following these written instructions.
PROCEDURES FOR PROVIDING ADDITIONAL INFORMATION USING THE 2L
B-3.2.1 Section I - Identification
Block A Enter the SHIP'S NAME
Downloaded from https://www.everyspec.com
p. 296
NAVSEAINST 4790.8B
B-51 Block B Enter the SHIP'S HULL NUMBER
JOB CONTROL NUMBER: Enter the same JCN (Ship's UIC, Work Center, and Job Sequence Number) assigned to the original maintenance action in Blocks C, D, and E
Block F CONTINUATION FOR: Enter an "X" in one of the blocks to indicate that this 2L is a continuation of either an NAVSEA 4790/2K, 4790/2L, or a 4790/2P Form.
B-3.2.2 Section II - Remarks/Sketches
Block G Enter the information you wish to provide; such as, a list of serial numbers and locations for which identical maintenance requirements exist; or sketches or drawings that may be useful in the accomplishment of the maintenance action.
B-3.2.3 Section III - Authentication
Block H FIRST CONTACT/MAINTENANCE MAN: The maintenance person preparing the form prints his/her name in this Block.
Block I DATE (YR/DAY): Enter the Julian date the document is prepared.
Block J SECOND CONTACT/SUPERVISOR: The work center supervisor's prints his name following his review of the document in the block.
Block K DATE: The work center supervisor enters the Julian date the document was reviewed. Downloaded from https://www.everyspec.com
p. 297
APPENDIX B-52
Figure B-13: SUPPLEMENTAL FORM Containing an Equipment Listing Downloaded from https://www.everyspec.com
p. 298
NAVSEAINST 4790.8B
B-53
Figure B-14: SUPPLEMENTAL FORM Containing a Sketch/Drawing Downloaded from https://www.everyspec.com
p. 299
APPENDIX B-54 B-4 MAINTENANCE PLANNING AND ESTIMATING FORM (NAVSEA 4790/2P) This form is used along with an NAVSEA 4790/2K Form deferring maintenance to be done by an IMA. Attached to the original 2K at the intermediate maintenance activity, it is used by the IMA to screen and plan the job in detail. This planning information will include information pertinent to the lead work center (LWC), assist work center(s), material requirements, technical documentation, and cost estimates required to complete the maintenance action. (Upon approval of the TYCOM, planning, estimating and scheduling information may be entered in the appropriate sections of the NAVSEA 4790/2K Form).
NOTE:
An example of a completed NAVSEA 4790/2P form can be found following these written instructions. B-4.1 Procedures For Documenting Planning & Estimating Data B-4.1.1 Section I - Planning
Block A Enter the SHIP'S NAME originating the request for assistance (from the 2K)
Block B Enter the SHIP'S HULL number originating the request for assistance (from the 2K)
JOB CONTROL NUMBER: Enter the same JCN (Ship's UIC, Work Center, and Job Sequence Number) assigned to the original maintenance action. It must be identical to the JCN of the attached 2K in Blocks 1, 2, and 3.
Block 8 SCREENING ACTION: The appropriate action to be taken must be indicated in this block. It may be used by the IUC, however, the TYCOM Representative's decision has precedence. The IUC/TYCOM REP must indicate the level at which the maintenance is to be done, or if the job is disapproved. There must be an entry in either "a", "b", or "c" if screened by the IUC; and "h", "i", or "j" when screened by the TYCOM REP. Blocks "d" through "m" may be used to identify qualifying actions. If "accomplished with modifications" is checked, the IUC/TYCOM will provide amplifying remarks in Section IV, Block 49. If the work is disapproved ("g" or "n"), amplifying remarks should be made in Section IV, Block 49.
Downloaded from https://www.everyspec.com
p. 300
NAVSEAINST 4790.8B
B-55 Block C/D IUC/TYCOM SIGNATURE: The signature of the IUC and/or TYCOM REP must be entered in these blocks following the screening process.
THE FOLLOWING BLOCKS, AS APPLICABLE, ARE FILLED-IN BY THE PLANNING AND SCHEDULING SECTION AFTER THE IUC AND/OR TYCOM REP HAS SCREENED THE JOB FOR ACCEPTANCE (Block 8)
NOTE:
Blocks 4 through 7 are for Master Job Catalog (MJC) development.
Block 4 PERIODIC MAINTENANCE REQUIREMENT: Enter the code that identifies the specific periodic maintenance requirement. This code may be a PMS maintenance requirement code, a code identifying a periodic requirement of a PERA (Planning and Engineering for Repair and Alterations), or a calibration requirement of MEASURE (Metrology Automated System for Uniform Recall and Reporting), etc….
Block 5 PERIODICITY: Enter the number of months between which the periodic maintenance requirement is to be done.
Block 6 YYMM ISSUED: Enter the four numbers used to identify the year and month during which the periodic maintenance requirement entered in Block 4 was issued. The first two digits identify the year and the last two digits the month; e.g., "9402" represents February 1994.
Block 7 SPECIAL DATA: Reserved for future use.
Block 8 See Block "8" above.
Block 9 QUALITY ASSURANCE REQUIREMENTS: Enter an "X" in the applicable Blocks "a" through "l" to indicate the specific planning actions, work controls, and auditable records in support of individual TYCOM management needs.
Downloaded from https://www.everyspec.com
p. 301
APPENDIX B-56 Block 10 SPECIAL REQUIREMENTS:
KEY EVENT: A two-digit number identifies a key event that influences a job, or is influenced by the completion of a job. A blank in this block indicates that the job is not associated with a key event. The Key Event code with a definition is assigned and managed by TYCOM instruction.
SPECIAL INTEREST: An "X" entered in this block indicates that this job has significant management interest, and keys the job to be selected for job management reports.
DRY DOCK REQUIRED: An "X" in this block shows the requested maintenance requires the ship to be dry- docked.
PRE OVERHAUL TEST REQUIRED: An "X" entered in this block identifies a specific test prior to an equipment or ship overhaul.
POST OVERHAUL TEST REQUIRED: An "X" entered in this block identifies a specific test that must be completed after equipment or ship overhaul.
DEPARTURE REQUIRED: An "X" entered in this block shows that if the maintenance requested is not done by the required specifications, notice of this departure is to be sent to the TYCOM.
Block 11 See Block 11 below under "BLOCKS FILLED-IN BY THE REPAIR OFFICER"
B-4.1.2 Section II - Scheduling
Block 12 LEAD WORK CENTER: Enter the code (left to right) of the "lead" repair work center assigned to the job. (Refer to Appendix A data element "IMA REPAIR WORK CENTER" for standard IMA work center codes.)
Blocks 13, 19, 25, 31, 37, an 43: SCHED START DATE: Enter the Julian date that work is to be started by each repair work center. During the planning process when the availability date is unknown, these blocks may be left blank.
Downloaded from https://www.everyspec.com
p. 302
NAVSEAINST 4790.8B
B-57 Blocks 14, 20, 26, 32, 38, 44: SCHED COMP DATE: Enter the Julian date that the work of the individual repair work center must be completed.
Block 15, 21, 27, 33, 39, and 45: EST MHRS: Enter an estimate of the total number of man-hours necessary for each repair work center to complete its assigned work.
Blocks 16, 22, 28, 34, 40, and 46: KEY OP: Number the logical sequence, e.g., 001, 002, 003, etc., of the tasks identified in Blocks 17, 23, 29, 35, 41, and 47.
Blocks 17, 23, 29, 35, 41, and 47: TASK: Enter the description(s) of the task(s) for which the repair work center(s) assigned are responsible.
Blocks 18, 24, 30, 36, and 42: ASST WORK CENTER: Enter the code (left to right) of the repair work center(s) assisting the lead repair work center. (Refer to Appendix A, data element "IMA REPAIR WORK CENTER" for standard IMA work center codes.)
B-4.1.3 Section III - Technical Documentation
Block 48 TECHNICAL DOCUMENTATION: Enter any blueprints, technical manuals, etc., which might be of use in the accomplishment of the maintenance. Indicate by an "X" whether the publications held by the IMA or the tended unit.
B-4.1.4 Section IV - IUC/Repair Activity/TYCOM Remarks
Block 49 REMARKS: Used by the screening and repair managers to enter any remarks that amplify the scope or limitations applicable to the accomplishment of the maintenance.
B-4.1.5 Section V - Supplemental Planning
THE FOLLOWING BLOCKS ARE FILLED-IN WHEN REQUIRED BY THE TYCOM AND ONLY WHEN ESTIMATING THE COST OF DEPOT LEVEL WORK
Downloaded from https://www.everyspec.com
p. 303
APPENDIX B-58 NOTE:
Other uses of these blocks can be defined by TYCOM directive.
Block 50 EST MAN-DAYS: Enter the total number of estimated man-days (for all involved repair work centers) required too accomplish the JCN. If the estimated man-day is less than one, enter "1".
Block 51 EST MAN-DAYS COST $: Enter an estimate of the total man-day costs required to accomplish the JCN.
Block 52 EST MATERIAL COST: Enter an estimate of the total material cost.
Block 53 EST TOTAL COST $: Enter an estimate of the total cost to complete the job (add blocks 51 and 52). B-4.2 Repair Officer Actions THE FOLLOWING BLOCKS ARE FILLED-IN BY THE REPAIR OFFICER
Block 11 NORMALLY DONE BY: Entered by the Repair Officer, an "X" entered into the appropriate block (S/F, IMA, DEPOT) allows the collection of data for evaluation of the costs of the IMA relative to other maintenance activities. B-4.3 Procedures for Documenting Changes, Additions, and Deletions Any block, with the exception of the JCN, that has had the planning and estimating information entered into the supporting ADP system can be added, deleted, or changed. Refer to the instructions described for submitting a correction to an NAVSEA 4790/2K Form.
When modifying information in Section II - SCHEDULING, the modification must contain the appropriate lead or assist WCs.
When modifying information in Section III - TECHNICAL DOCUMENTATION and Section IV - IUC/REPAIR ACTIVITY/TYCOM REMARKS, the entire section must be revised so that correct information and change information is included. Do not change a word or two in these sections without resubmitting the entire section.
NOTE: Downloaded from https://www.everyspec.com
p. 304
NAVSEAINST 4790.8B
B-59
In the event the original lead work center (LWC) must be changed and a new LWC assigned, the planning section should submit the applicable documentation to change the LWC. Planning and estimating will submit a new planning sheet showing the new LWC and assist WC(s).
Downloaded from https://www.everyspec.com
p. 305
APPENDIX B-60
Figure B-15: Completed NAVSEA 4790/2P
Downloaded from https://www.everyspec.com
p. 306
MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL
APPENDIX C
3-M AUTOMATED PERIODIC MAINTENANCE PROGRAM (MASTER JOB CATALOG AND PERIODIC MAINTENANCE REQUIREMENTS)
Downloaded from https://www.everyspec.com
p. 307
APPENDIX C-i APPENDIX C
REFERENCES
REFERENCE INSTRUCTION NO. SUBJECT
(a) CINCLANTFLT/CINCPACFLT INST 4790.3 JOINT FLEET MAINTENANCE MANUAL
Downloaded from https://www.everyspec.com
p. 308
NAVSEAINST 4790.8B
C-ii APPENDIX C
3-M AUTOMATED PERIODIC MAINTENANCE PROGRAM (MASTER JOB CATALOG AND PERIODIC MAINTENANCE REQUIREMENTS) TABLE OF CONTENTS
Paragraph Title Page
C-1 PURPOSE...................................................C-1 C-2 SCOPE.....................................................C-1 C-3 OBJECTIVE.................................................C-1 C-4 MASTER JOB CATALOG (MJC)..................................C-3 C-4.1 Use of the MJC..........................................C-4 C-4.2 Control of MJC..........................................C-4 C-5 3-M PERIODIC MAINTENANCE REQUIREMENTS.....................C-5 C-5.1 Use of PMRs.............................................C-5 C-6 PMR REPORTING.............................................C-6 C-7 MASTER JOB CATALOG (MJC) INTERFACE WITH PMR..............C-19 C-7.1 TAMS Calibration.......................................C-19 C-7.2 Standard MJC Routines for TAMS Calibration and Weight Testing................................................C-20 C-7.3 Other Automated System in Support of PMR...............C-21 C-8 USING MJC JCN STRUCTURE TO MANAGE PROGRAMS...............C-21 C-8.1 Fleet/TYCOM/Local Site MJC Control.....................C-21 C-8.2 Applicability UIC Control..............................C-22 C-8.3 MJC WC Designations....................................C-22 C-8.4 MJC JSN Prefix for Work Category.......................C-23 C-8.5 Documenting the MJC Deferral...........................C-23 C-8.6 Documenting the MJC P&E................................C-25 C-8.7 Establish Bill of Materials Interface..................C-27 C-8.8 MJC Alteration Documentation Differences...............C-27 Downloaded from https://www.everyspec.com
p. 309
APPENDIX C-iii C-8.9 MJC Index and Statistics .............................. C-27 C-8.10 Analysis of MJC/PMR Originated Production History .... C-28 C-8.11 Modification of On-Site MJC .......................... C-29
Downloaded from https://www.everyspec.com
p. 310
NAVSEAINST 4790.8B
C-iv APPENDIX C
3-M AUTOMATED PERIODIC MAINTENANCE PROGRAM (MASTER JOB CATALOG AND PERIODIC MAINTENANCE REQUIREMENTS) LIST OF FIGURES
Figure Title Page
Figure C-1: Modified NAVSEA 4790/CK Form ...................C-10 Figure C-2: Master Job Catalog Index Page ..................C-30 Figure C-3: MJC Call Down Frequency Report .................C-31
Downloaded from https://www.everyspec.com
p. 311
Downloaded from https://www.everyspec.com
p. 312
NAVSEAINST 4790.8B
C-1 APPENDIX C
3-M AUTOMATED PERIODIC MAINTENANCE PROGRAM (MASTER JOB CATALOG AND PERIODIC MAINTENANCE REQUIREMENTS)
C-1 PURPOSE This appendix is to describe the automated Periodic Maintenance Program (PMP) capabilities, provide guidelines for its use, and standardize the requirements in support of fleet and depot maintenance and material 3-M reporting. This program was established to assist maintenance and material managers in executing Class Maintenance Plans (CMP) and Life Cycle Manager (LCM) requirements to sustain the operability of weapons systems. C-2 SCOPE Intermediate Maintenance Activities (IMAs) require the capability to generate work requests for periodic maintenance. Periodic Maintenance Requirements (PMRs) provides that capability. PMR also provides the capability to schedule, maintain, issue and report work accomplished for PMR items. The data elements for PMR conform to 3-M standards.
PMR requires the reporting of maintenance actions and configuration changes on all categories of equipment. C-3 OBJECTIVE The automated PMP can provide a means to effectively manage and control all PMRs beyond the scope of the organizational level Planned Maintenance System (PMS). It is managed by integrating the SYSCOM Life Cycle Requirements (LCRs), Configuration Data Managers' Database, periodicities invoked by system and equipment engineers with the 3-M Master Job Catalog (MJC) and PMR modules of the intermediate maintenance management automated systems. This integration provides an automated pre-planned deferral to be added to the Current Ship's Maintenance Project (CSMP) and procurement of repair parts specified by technical repair standards or other controlled work procedures. The system:
a. Provides continuous evaluation and adjustment of the CMP to reflect the specification of the Systems Command (SYSCOM) Platform Managers and the capabilities and capacities of fleet maintenance activities. Downloaded from https://www.everyspec.com
p. 313
APPENDIX C-2
b. Adjusts the Ship Configuration and Logistics Support Information System (SCLSIS) specifications and the Configuration Data Manager (CDM) databases to reflect all levels of equipments and components for existing and emerging PMRs.
c. Develops, evaluates and implements an MJC deferral for each PMR added to the CMP.
d. Distributes a Unit Identification Code (UIC) unique configuration and scheduling record for each CMP periodic requirement to each activity maintaining the ship class.
e. Maintains the MJC and PMR database at the central facility (regional hub, port facility, Readiness Support Group (RSG) or Parent Squadron/IMA) supporting the ship classes.
f. Plans and executes the ship's scheduled availabilities and planned work packages by retrieval of all scheduled PMRs, alterations, Type Commander (TYCOM)-directed and local support routines from the MJC/PMR module and all screened deficiencies from the tended ship's CSMP into the Master CSMP of the central facility.
g. Manages the execution of all authorized work, ensuring the progress, status change, delay and completion of each task is reported into 3-M as detailed in the applicable program user manuals.
h. Produces and distributes PMR, CSMP and production information (Availability Summaries, Key Event Schedules and Progress, AWRs, Calibration Summaries, CSMP Summaries, etc.) as specified by TYCOM directives.
i. Distributes Maintenance Data System (MDS) information from NAVSEALOGCEN to the applicable program managers and SYSCOM/fleet support activities for analysis and upgrade of CMPs, technical specifications, mandatory parts replacement requirements, affirmation/adjustments of Lead Work Center/Assistant Work Center (LWC/AWC) and task/keyop man-hour averages and standards for recycling MJC and PMR improvements.
j. Manages the distribution of information between central activities and the organizational calibration and scheduling systems to support accomplishment of shipboard PMRs (e.g., Submarine Operational unrestricted operations (URO) Downloaded from https://www.everyspec.com
p. 314
NAVSEAINST 4790.8B
C-3 requirements and gage calibration by certified Field Calibration Activity (FCA) personnel.)
k. Adds all Test and Monitoring System (TAMS) installed equipment records into the SCLSIS of the Class CDM so that cyclic requirements are tailored to the operating platform and the PMR scheduling record updated.
l. Adds all portable TAMS to the SCLSIS for control by SPAWAR/NAVSEASYSCOM Item Managers supported by Naval Weapons Assessment Division and Metrology Calibration (METCAL) organizations. This process:
(1) Increases the management of portable TAMS inventory control between the METCAL CDM and the fleets central activity PMR Configuration.
(2) Increases the management of alterations for portable TAMS applying business rules to justify upgrade. Controls TAMS alterations in the same manner as ship alterations (SHIPALTs) and TYCOM alterations (ALTs).
m. Provides information necessary to evaluate and improve reliability, maintainability, and availability of installed systems and equipment while eliminating periodic requirements whose material condition assessment (MCA) indicates little risk of equipment failure. C-4 MASTER JOB CATALOG (MJC) The MJC is a collection of recurring jobs applicable to multiple supported units.
a. These jobs typically consist of PMRs from the CMP; PMRs for inspection, test, calibration, and repair of various equipments; alterations; recurring Board of Inspection and Survey (INSURV) deficiencies; routines for IMA services; and depot routines for interfacing the CSMP with the Ship Alteration and Repair Package (SARP)/Overhaul Work Package (OWP).
b. There are many advantages of using jobs from the MJC. Use of the MJC reduces the documentation burden for ship's force in preparing deferrals for recurring maintenance actions. MJC preplanned jobs reduce the planning effort required by the IMA Planning & Estimating (P&E). Planning information is usually recorded for the MJC jobs. In addition, it reduces the variability in job accomplishment. This is contributed to the consistency of job requirements for each repetitive use of the Downloaded from https://www.everyspec.com
p. 315
APPENDIX C-4 MJC job. MJC jobs provide a ready vehicle for recording lessons learned as the job is accomplished time after time. C-4.1 Use of the MJC The MJC is structured as a CSMP deferral and planning record. The MJC describes mandatory maintenance requirements, CMP periodic requirements, IMA support routines, alterations, hazardous material (HAZMAT) procedures, calibration routines and other SYSCOM and TYCOM directed maintenance requirements applicable to one or more ship classes. The TYCOMs provide some MJC jobs, while individual IMAs prepare others.
In addition, each central maintenance activity may establish additional service routines to account for production-oriented work not otherwise covered by TYCOM direction. These periodic or repetitive requirements are retrieved from the MJC and added to an individual ship's Master CSMP for assignment to IMA and depot work packages.
Application of the MJC prior to and during a ship's availability relieves ship's force from documenting other than its own discovered deficiencies. The onboard automated CSMP need contain only these deficiencies, while the MJC retrieved requirements (and the ship's reported deficiencies) are maintained on a Master CSMP by the RSG, squadron or other central fleet activity. C-4.2 Control of MJC TYCOMS will establish joint instructions to identify common MJC requirements and standard procedures for its distribution and maintenance. The intermediate maintenance management automated systems user manuals describe methods to retrieve periodic requirements from the MJC to the individual availability work packages.
A TYCOM designated activity (Submarine Maintenance, Engineering, Planning, and Procurement (SUBMEPP) and/or other planning activity) may be assigned to maintain and distribute the MJC files to applicable fleet sites, and to provide analysis and improved planning and estimating, and material requirements for each documented MJC requirement.
All periodic requirements established by the SYSCOMs for a ship class should include the repair parts required and the forecast to the Navy Inventory Control Point (NAVICP) Mechanicsburg to build an effective load list over the projected life cycle of the ship class. The SUBMEPP/planning activity should provide Downloaded from https://www.everyspec.com
p. 316
NAVSEAINST 4790.8B
C-5 quarterly files to sustain the conjunctive Automated Material Requisitioning (AMR) for CMP projections. C-5 3-M PERIODIC MAINTENANCE REQUIREMENTS There are certain equipment and components in the fleet that require periodic maintenance such as tests, inspections, repairs, restorations, and replacements. With select automated systems, periodic maintenance tasks and routines are maintained on file with planning information. The record containing both the routine, test, etc., along with the scheduling and planning information is called a PMR. C-5.1 Use of PMRs Use of PMRs provide for the management of configuration and scheduling information for each equipment requiring periodic maintenance. As PMRs are established for an equipment, ship's force submits the related configuration and scheduling information. This information is used to establish a MJC routine. The MJC routine will be added to the CSMP when the equipment is due for periodic maintenance as indicated by the scheduling information. MJCs can be scheduled for accomplishment by ship's force or by an intermediate or depot level activity.
C-5.1.1 Configuration and Scheduling PMR Data
Both configuration and scheduling data files may be provided and downloaded from the CDM, SUBMEPP/planning activity, NSWC METCAL TAMS or from other SYSCOM or contractor sources supporting fleet maintenance. Ship's force may be required to initially document items for addition to the PMR database as directed by TYCOMs when the items require periodic testing, calibration or inspection by an intermediate level shop or fleet support team, electrical safety inspections, cyclic zone inspections by Damage Control teams vice sustaining a PMS Equipment Guide List (EGL) and requiring the ship to submit IMA work requests).
Detailed operating procedures for MJC and PMR are contained in Shipboard Non-Tactical ADP Program (SNAP) Central Design Activity (CDA) User Manuals and guides; these procedures are not repeated in this manual.
C-5.1.2 Modified OPNAV 4790/CK Form for PMR
The OPNAV 4790/CK (PMR) (Figure C-1), commonly referred to as a PMR CK is used to manually document an addition, change or deletion to a PMR Configuration and/or Scheduling Record. The PMR CK form must be locally reproduced. The manually prepared Downloaded from https://www.everyspec.com
p. 317
APPENDIX C-6 PMR CK is used when direct access to the automated system is not available for on-line entry. The original 3-M data elements for configuration reporting (Blocks 1 through 30) of the OPNAV 4790/CK form are retained. Additional data elements (fields) have been added to the form and in the automated systems for scheduling information required to link this data with the appropriate configuration record. C-6 PMR REPORTING PMR records and related equipment/component information can be maintained in the PMR/MJC system. Configuration file entries can be made on-line if the capability is there, or can be entered manually on a modified OPNAV 4790/CK. The modified CK, referred to as the PMR CK, is used to document configuration file entries to add, change or delete an equipment to the PMR inventory. Standard 3-M data elements (Blocks 1 through 30 or the OPNAV 4790/CK) is used for PMR configuration reporting. For additional information/data element definitions and approved values refer to the data element by name in Appendix A of this instruction.
NOTE:
For the following data elements, if a data element has been officially assigned a Data Element Number (DEN), the DEN will be listed.
A single block at the top of the form is used to specify that a configuration file correction "CONFIG FILE CORR" is being documented.
SECTION I - JOB IDENTIFICATION
This section is pre-filled except for the ship's UIC. The PMR "Work Center" can be tailored for different management programs by using a different suffix for each program LCM Code. The Job Control Number and Job Sequence Number ("JCN JSN") remains "0001" until the page count (number of adds) exceeds 9999, at which time the JSN will be changed to "0002" for the next 9999 page numbers. For example, NAVSEA Mechanical TAMS components use LCM code "HM" while SPAWAR Electronic TAMS uses "ET". A ship's PMR installation could use PMHM0001 and PMET0001 for up to 9999 components for each LCM. The total JCN for an initial "ADD" PMR item is then converted to reflect the PMR assigned line item number (LIN) as part of the Work Center (WC/JSN) (e.g., PM001454 - where 001454 is the LIN) to become the permanent JCN for the life of the component on the UIC. Downloaded from https://www.everyspec.com
p. 318
NAVSEAINST 4790.8B
C-7
Block A SHIP'S NAME Block B SHIP'S HULL NUMBER JOB CONTROL NUMBER (Blocks 1 - 3): Block 1 SHIP'S UIC (DEN A002): UIC of the customer unit/ship of installed equipment. Block 2 WORK CENTER (DEN E128): The PMR LCM code designated by the TYCOM. Block 3 JOB SEQ. NR. (DEN E349D): The JSN is pre-filled with "0001" until the number of "adds" (pages) exceeds 9999. The JSN is then changed to "0002" for the next 9999 "adds". Block 4 ALTERATION IDENTIFICATION (SHIPALT, FLD. CHG., ETC.): Masked out in the automated system. Leave blank for PMR. Block 5 EIC: EIC for the equipment identified. This EIC may be the general service code (U series) if the PMR is for support service of multiple systems. (These Service EICs may be used in combination with the primary IMA Work Center e.g., U60067B, U60096A, U60067F, etc.). Block 6 ACT. TKN: Action taken is masked out or pre-filled as specified by TYCOM instruction. Block 7 EQUIPMENT NOUN NAME: Pre-filled as specified by TYCOM instructions to describe the general category of the PMR management program. Block 8 S/F MHRS. EXP.: Ships' Force Man-hours Expended. Field is masked out in the automated system. Leave block blank if using the form. Block 9 ACT. MAINT. TIME: Actual Maintenance Time. Field is masked out in the automated system. Leave block blank if using the form. Block 10 COMP. DATE: Completion Date. Field is masked out in the automated system. Leave block blank if using the form. Block 11 M/R (Meter Reading): Masked out.
SECTION II - JOB DESCRIPTION/REMARKS
This section describes the appropriate management program being documented with PMR.
Block 12 JOB DESCRIPTION/REMARKS: Information/remark identifying the PMR management program as directed by TYCOM instructions.
SECTION III - COMPONENT CONFIGURATION INFORMATION Downloaded from https://www.everyspec.com
p. 319
APPENDIX C-8
This section records the PMR related equipment configuration/identifying information specific to the component. Note that PMR is not limited to supply worthy components but is used to also manage all cyclic maintenance worthy items (e.g., pad eyes, slings, hoists requiring weight tests can be added to PMR to ensure inventory and scheduling control as can damage control lockers and fire hose valve stations).
Block 13 COMPONENT NOUN NAME (DEN E224). For Hull, Mechanical, and Electrical Equipment (HM&E), the component name entered along with a descriptive nomenclature (e.g., Valve, Ball 3.5" MSW; Gauge, 0- 50psi Lube Oil Pump). For electronic components and test equipment, the AN nomenclature Joint Electronic Type Designation System (JETDS) or commercial model number is entered. Prefix the model number with the Commercial and Government Entity (CAGE) and a dash. For ordnance components, enter the system/equipment nomenclature, followed by the Mark and Mod. Block 14 QUANTITY (DEN DO1l) (CK limits 001-999, pre-filled with 000). This quantity will usually be 001, but if multiple items are to be tested or calibrated as a batch job, enter the contained quantity. For example: 100 Radiation Detection, Indication, and Computation (RADIAC) for a ship may be contained in four boxes of 25 each, resulting in four separate line items - each with a 025 in block 14. For IMA Electrical Safety, all receptacles in a single shop may be counted as one line item and the total quantity shown in Block 14. This would necessitate testing all of them at one time. Block 15 COMPONENT ACTION (DEN E033). If the item is not in the PMR INVENTORY, enter an "A" (add). Otherwise enter "C" (correct the record), or a "D" (delete the inventory line item). Block 16 COMPONENT IDENTIFICATION (DEN E093). Enter the Valve Mark/Electric Symbol Number (VM/ESN) or other identification. For inventory items controlled by an LCM, this identification would be retained as originally assigned. For Director Strategic Systems Project Office (DIRSSPO) controlled weapons handling gear, the identification number must be a "PMMP~~ (Pink Ticket) number. Once assigned, this element cannot be changed or corrected. For weight handling gear, include the safe working load in pounds prefixed by SWL (e.g., TP16SY SWL 6800). SCLSIS Downloaded from https://www.everyspec.com
p. 320
NAVSEAINST 4790.8B
C-9 defines this element as " Positional Reference Identification -PRID .II
Downloaded from https://www.everyspec.com
p. 321
APPENDIX C-10
Figure C-1: Modified NAVSEA 4790/CK Form Downloaded from https://www.everyspec.com
p. 322
NAVSEAINST 4790.8B
C-11 NOTE:
The two data elements of the OPNAV 4790/CK Blocks 16 (Component Identification) and Block 17 (Component Serial Number) becomes a single data element in Block 13 (Identification Equipment Serial Number) of the OPNAV 4790/2K used for reporting corrective maintenance. The PMR program selects the Component Identification from the configuration change (Block 16) and pre-fills this number in the Identification Equipment Serial Number field.
Block 17 COMPONENT SERIAL NUMBER (DEN D032). If the nameplate serial number is not available, a number assigned by the owning ship will be entered. The ship’s UIC (Block 1) and owning work center (Block 23) are separately shown on the PMR reports and in the system; there is no requirement to repeat the hull number and work center as part of the serial number. Weight handling equipment must be marked or tagged with the hull number (equal to the UIC) and the serial number of the component. The combination of blocks 1, 16, and 17 must not be duplicated in the PMR configuration file. If there are multiple PMRs for the same item, the additional requirements must be identified by separate MJC numbers.
NOTE:
For SUBMEPP/CDM. When a commercial serial number is not assigned, record the unique functional group code (FGC) in this field and in the ship equipment file (SEF).
Block 18 COMPONENT APL/AEL (DEN DO08). Enter the Component Allowance Parts List/Component Identification Number/Repairable Identification Number (APL/CID/RIC). If there is no APL/AEL (Allowance Equipage List), enter NOT LISTED. For SUBMEPP inventory, when NOT LISTED is entered, the tenth and eleventh position must contain a number from 01-99 for interface with the Automated Material Requisitions (AMR) program. This is required to allow different components with the same MJC/PMR to be provided with separate "Bills of Material" for automatic call out. Block 19 LOCATION (DEN E052). (Preliminary Equipment Index Location). Enter the location of the item. For inventories being converted by LCMS, if the location Downloaded from https://www.everyspec.com
p. 323
APPENDIX C-12 is not available, enter the customer’s (ship’s) work center and a question mark (e.g., "EEO1?"). Block 20 EIC (DEN DO08D). Enter the components EIC. The EIC entered in Block 5 may be a General Support Code (U series EIC) or a System/Sub-System Code. The component EIC, when identified in the 3-M EIC Manual, should identify to the component being added to the configuration file. Block 21 NEXT HIGHER ASSEMBLY. Enter the Equipment/System Designator (ESD) (DEN T058) or other identity of the system/sub-system. Block 22 SAC (DEN EO1OA). Enter the Service Application Code (SAC) from the Coordinated Shipboard Allowance List (COSAL)/SCLSIS source if available. Note that it is a five character element on the OPNAV 4790/CK form but 10 characters in the automated system. LCMS should interface with NAVICP Mechanicsburg to obtain the ten character element. Block 23 WORK CENTER (DEN E128). This is the 3-M code of the customer maintenance work center required to maintain the component. If a Work Center Responsible for Compartment (WCRC) DEN 127)) code is also available in the LCM inventory, enter it. SUBMEPP use MJC WC with last two characters of 01 (e.g., EACC=EAO1). Block 24 NAME PLATE DATA. Use to describe any other characteristics not covered by other elements. This data will not display on reports but will be accessible in the program. For SUBMEPP it will be the CSMP Summary from the individual MJCS assigned to the PMRS . Block 25 PMS MAINT INDEX PAGE (MIP). Enter the PMS MIP if available. PMS MAINT INDEX PAGE (MIP). Enter the PMS MIP if available. Block 26 EOSS . If applicable, enter the Engineering Operational Sequencing System (EOSS). Block 27 TECHNICAL MANUAL NUMBER. If available, enter the TM number, otherwise enter NA. Block 28 RIN (DEN E221). If the component is listed in the COSAL or the SCLSIS, enter the Record Identification Number (RIN). If not available, the program will assign a temporary RIN as a permanent data element until changed by the SCLSIS CDM external interface. For automated ships, first review the SEF for the component’s RIN. Block 29 AILSIN/FUNCTIONAL GROUP CODE (DEN T063). If the Automated Integrated Language System Identification Downloaded from https://www.everyspec.com
p. 324
NAVSEAINST 4790.8B
C-13 Number (AILSIN) is not available, enter the Ship Work Authorization Boundary (SWAB) or Ship Work List Item Number (SWLIN), if known. TRIDENT applications will contain the FGC in lieu of AILSIN. Other class submarines use SWAB, other type ships use Expanded Ship Work Breakdown Structure (ESWBS). Block 30 SPECIAL PURPOSE - These requirements are TYCOM directed and are provided by the TYCOM supporting activity (SUBMEPP/PERA).
The following are PMR requirements for SUBMEPP LCM. These requirements, if applicable, are provided by SUBMEPP. If the local site determines that changes are required, additions may be made. Deletions must first be coordinated with SUBMEPP. Block 30A SS. Use “X” if the component is submarine safe (SUBSAFE).
Block 30B Use an "X" if the component is LEVEL 1. Block 30C NL1 . Use an "X" if the component is NUCLEAR LEVEL 1. Block 30D NDT. Use an “X” if the component requires NON- DESTRUCTIVE TEST. Block 30E NWP. Use an "X" if the component requires NUCLEAR WORK PROCEDURES. Block 30F SAED. Use an “X” if the component requires SUB ANTENNA ENGINEERING DIVISION. Block 30G SAED. Use an “X” if the component requires SUB ANTENNA ENGINEERING DIVISION. Block 30H ST. Use an "X" if the component requires SPECIAL TESTING. Block 30I Use an “X” if the component requires SPECIAL IDENTIFICATION. Block 30J NC. Use an “X” if the component is NOISE CRITICAL. Block 30K RAD. Use an “X” if the component requires RADIOLOGICAL CONTROL. Block 30L OC. Use an "X" if the component requires OTHER CONTROLS. Block 30M D/D. Use an "X" if the component requires DRYDOCKING. Block 32 LINE ITEM NUMBER. This element is assigned by the program when items/components are added to the system. The LIN is unique to the configuration file for each customer UIC and is retained until the record is deleted from the ship’s inventory.
NOTE:
Downloaded from https://www.everyspec.com
p. 325
APPENDIX C-14 This line item number preceded by PM becomes the permanent 3-M Work Center and JSN. Subsequent changes made to the record are reported upline as a corrected CK using this permanent JCN. In addition, changes to the scheduling record and to the Calibration Laboratory (Cal Lab) production record are reported upline with the same permanent JCN to support the MEASURE integration into 3-M. Note that the LIN plays the same role as the RIN for "non- supply worthy" items.
Block 33 ON SITE. If the component being calibrated/tested cannot be delivered to the Testing Work Center (TWC) because of location, size, etc., enter a "Y" to show the TWC must calibrate on-site. Otherwise leave this field blank. Leave blank for Submarine Extended Operating Cycle (SEOC) PMRs relating to installed HM&E. Block 34 PERIODICITY. Enter the number of months between calibration/testing or other PMR cycles. If the requirement is situational, see Block 45. Block 35 DATE LAST DONE. Enter the date (DDMMMYY) the PMR was last accomplished (e.g., 05FEB00). For EPP, if the PMR has never been done because the periodicity has not exceeded the months since commissioning, construction, overhaul; enter this event date if the PMR authorizes. If the PMR is for test equipment/slings/portable tools that have not previously been calibrated/inspected, the PMR must be accomplished prior to first use. Block 35 will be entered by the TWC. Block 36 NEXT DUE DATE. Enter the date (DDMMMYY) the PMR is next due for accomplishment (e.g., 27JUL00). This data element is calculated and reported upline by the automated program when the PMR is reported completed by the TWC. Block 37 STND/ETV Man-Hours - TENTHS. If the component PMR has a standard, engineered time value, or historically based man-hour estimate, it should be provided by the LCM/NAVSEA for the initial download or subsequent Automated Shore Interface (ASI) process. This element is not for expended man-hours reported when the PMR is accomplished. Block 38 APPROVED PROCEDURE. Enter the procedure, periodic maintenance requirement, technical repair standard or other directive used during the required action on the component. SUBMEPP should not repeat the Downloaded from https://www.everyspec.com
p. 326
NAVSEAINST 4790.8B
C-15 Integrated Maintenance and Modernization NUMBER in this block as it is planning record.
NOTE:
This entry is displayed in the last Program (IMMP) P~ included in the MJC column of the PMR report. This information may be used as an update record to show such information as the name of the per-son conducting the test/calibration, or the measurement of the gear. Once entered, it will display on subsequent reports until changed when next tested.
Block 39 CAGE (DEN C035). Enter the Commercial and Government Entity (CAGE), if applicable. Block 40 NATIONAL STOCK NUMBER (NSN). Enter the NSN, if applicable, or the LCM assigned number used for procurement/replacement/supply action. Block 41 PLANT ACCOUNT NUMBER. Enter the plant account number if applicable. This usually applies only to shore activity permanent/fixed equipment. Block 42 CALIBRATION STANDARD. Enter a "Y" if the component is used as a measurement standard for calibrating or testing other test equipment, otherwise leave blank. Block 43 CLASS STANDARD. To identify the source/type of man- hours/tenths for Block 37. A = Engineered, B = Historical, C = Estimated. Block 44 EQUIPMENT TYPE. Enter the functional category of the equipment. 1 = Electronic; 2 = Coaxial/ Microwave; 3 = optical/Dimensional; 4 = Physical/ Mechanical; 5 = Electrical; 6 = Special Support. These are for LCM Measurement Equipment. Additional codes and other categories will be established by other LCMS. Block 45 PHASE LEVEL. For measurement equipment (SUBMEPP or CMP events) if applicable, enter an asterisk plus the four digit KEY EVENT code describing the situational requirement. Block 46 ACTION REQUIRED. Primarily calibration codes are entered. For PERA and weight handling components, use Code 06 TEST/INSP. Block 47 OVERFLOW INDICATOR. For measurement (TAMS), the IMA lab may use a two character code to identify a specific shore facility. A similar code may be used for SUBMEPP to identify components requiring off site assistance teams. Downloaded from https://www.everyspec.com
p. 327
APPENDIX C-16 Block 48 SCAT CODE. For Ships Portable Electrical/Electronic Equipment Requirements List (SPETERL) TAMS. The LCM should provide the subcategory code. Not applicable to other equipment. Block 49 SUPPRESS LANTFLT 4790/6 (if applicable). A custody receipt is provided to the customer when test equipment or other portable components are delivered to the Cal Labs. This form is not required for other categories of equipment. Enter a "Y” to prevent printing of the custody receipt. Enter an "N" for all test equipment having to be delivered to the Cal Lab. This causes the printing of a four- part custody receipt when the component is due for calibration. When the PMR is run at the beginning of each month, the computer will generate the PMR DUE/OVERDUE/INVENTORY REPORT for the customer ship and the Cal Lab. After generating the Cal Lab reports, the system will print the LANTFLT 4790/6 for each DUE component.
NOTE:
These LANTFLT 4790/6s must be delivered to the Cal Lab and These not to the customer ship with the recall reports.
Block 50 MEC-VITALITY CODE. Mission Essential Code V = Vital. For SUBMEPP use codes reflected in EOC IMMP/URO/LID. Use only if required and furnished by LCM. IMA Work Center. Enter the 3-M Intermediate Maintenance Activity Repair WC code of the Cal Lab or Testing WC. This is obtained from the MJC planning record. Block 51 MAINTENANCE LEVEL. From the CMP, used to identify where PMR will be performed: Organizational (0), Intermediate (I) or Depot (D). Additional data elements used in PMR as part of the Configuration/Equipment Record, and for generating from one to multiple scheduling records for each equipment record file, are detailed in the NAVSEA Technical Specification Manual. Each scheduling record must be identified to a unique MJC JCN general requirement for multi-tasking.
The following are data elements used in creating scheduling records for MJC supported equipment. These elements are used with the automated processing of PMRs and do not have a correlating block entry requirement on the PMR CK form. For Downloaded from https://www.everyspec.com
p. 328
NAVSEAINST 4790.8B
C-17 additional information refer to TYCOM instructions and systems user manuals.
DATA ELEMENT Description/Entry Criteria
ALMAD Identifies the ALMAD of the PMR component for calculating the Next Due Date. This is for SEOC IMMP/URO programs which adjusts the LMA date to the end of the availability. EOSS Assigned by the CDM if applicable to the PMR accomplishment. FREQUENCY (DAILY, WEEKLY, MONTHLY, ETC.) The periodicity frequency of the PMR. Used by SUBMEPP to identify SEOC events from the CMP. It should cross reference to scheduling of situational PMRs. IMA WORK CENTER (DEN E902A) The 3-M IMA Repair WC code of the Cal Lab or Testing WC. This is obtained from the MJC planning record. “FCA” is used for shipboard gage calibration. INITIALIZATION NEXT DUE DATE The CDM assigned date to identify when new requirements are to be scheduled for accomplishment. This date is required for implementing PMR on newly commissioned ships or when PMR components receive additional scheduling requirements. Format is YYMMDD. LAST ACTION TAKEN The Final Action Taken (FAT) code from the Completed automated work request. Date is retained on record. LAST ASSIGNED AVAILABILITY NUMBER (ANNN) Identifies the Availability Category and number in which the component PMR was last accomplished. LAST ASSIGNED REPAIR ACTIVITY UNIT IDENTIFICATION CODE (RAUIC) This RAUIC identifies the IMA last accomplishing the component PMR. LAST JCN REFERENCE The WC and JSN of the last reported JCN that accomplished the PMR. The intermediate maintenance management automated systems include retention of the last JCN and Availability Number in the PMR Scheduling file for determining the Adjusted Last Maintenance Action Date (ALMAD).
LIFE CYCLE MANAGER CODE (DEN E137) The LCM code assigned to the MJC planning record and as shown in the modified OPNAV 4790/CK (PMR CK). Note that the one character code from COSAL Maintenance Manual is Downloaded from https://www.everyspec.com
p. 329
APPENDIX C-18 expanded to two (with an optional suffix). This allows identification of multiple functions within the SYSCOMS. LIFE CYCLE MANAGER CODE SUFFIX (OPTIONAL) MAINTENANCE ACTION CODE LITERAL The four character literal to describe the required PMR. Calibrate = CAL, Special Calibration = SCAL, User Calibrate = UCAL, Test or Inspection = TEST, No Cal Required = NCR, Inactive = INAC. MASTER JOB CATALOG NUMBER Enter the MJC number from the bottom of the modified OPNAV 4790/CK (PMR CK) or from the TYCOM MJC Index. PERIODIC MAINTENANCE REQUIREMENT (PMR) NUMBER The PMR number as recorded on the MJC planning record (OPNAV 4790/2P) and as identified in the CMP. RAUIC FINAL ACTION TAKEN (FAT) CODE Identifies the FAT reported by the RAUIC for the component PMR. SCHEDULED SHOP CODE Identifies the IMA Cal Lab or other primary LWC to accomplished the PMR. For TAMS, use 51C, 67B, 67F, 96A, and FCA. SCHEDULED RAUIC Identifies the planned RAUIC for accomplishing PMR calibrations and other actions. SELECTED EQUIPMENT LIST INDICATOR (SEL) An “X” is used if CDM has indicated Meter Readings or Specialized Reporting. SITUATIONAL REQUIREMENT KEY EVENT CODES For scheduling PMRs to be done during non-cyclic situational events (e.g., calibrate tank level indicators whenever tanks are opened). These event codes are assigned by the CDM or supporting activity for CMP requirements. SPECIAL HANDLING REQUIREMENTS A series of codes and definitions to be assigned as agreed between the TYCOM, Platform Manager and designated CDM for TAMS and other PMR components. A total of eight codes may be defined for each ship type. Four codes are reserved for the following: A= POTENTIALLY RADIOACTIVE CONTAMINATED B = REACTOR PLANT CLEAN REQUIREMENT C = STEAM PLANT CLEAN REQUIREMENT D = OXYGEN CLEAN REQUIREMENT SYSTEMS CALIBRATION (SISCAL) CALIBRATION REQUIREMENTS LIST (CRL) INDICATOR Reserved for use as an interface to indicate PMR is to be performed by NAVSEA Team. VERSION ISSUE DATE (DEN D917A) Downloaded from https://www.everyspec.com
p. 330
NAVSEAINST 4790.8B
C-19 The Julian Date (YDDD) of the original MJC JCN deferral. C-7 MASTER JOB CATALOG (MJC) INTERFACE WITH PMR The MJC and PMR integration provides management of many other maintenance applications including all Class Maintenance Plan requirements, electrical safety and weight handling safety requirements, PMS requirements calling for IMA support, periodic inspections of reduced instruction set computing (RISC) and flexible hoses, IMA testing of system relief valves, IMMP/URO submarine requirements, tracking of multi-phase alterations and corrosion control management.
The decision to manage these cyclic requirements as single or multi-task requirements is usually determined by the scope of the task, and if a single work center can accomplish the task or whether multiple work centers will be required. C-7.1 TAMS Calibration PMR provides the TAMS community with inventory management, calibration scheduling management and calibration results reporting capabilities. TAMS categorizes equipment requiring calibration and weight testing periodic maintenance. The MJC supports TAMS equipments and the special IMA Routines required to support calibration and weight test periodic maintenance requirements that are to be accomplished during scheduled availabilities. The lab assigned responsibility for calibration and repair along with the work centers responsible for accomplishment are provided in the MJC.
a. PMR tracks all due and overdue TAMS of each MJC category. For each periodic requirement that needs to be accomplished, PMR creates a single deferral for each scheduling record. This assists the Cal Labs in identifying all items requirement periodic test, monitoring/calibration to be identified to the customer ship and the IMA lab.
b. When the items are delivered to the lab, PMR will track delivery, progression, status, completion and pick-up of each piece of test equipment. The Master CSMP will display within the single deferral all of the due/overdue items by line item, model, serial and nomenclature.
c. As each task (TAMS item) is completed, the expended man- hours are accumulated against the production AWR and the detailed reporting of hours, delays, parts usage, out-of- tolerance readings and standards being used are recorded and upline reported. This information is also retained in the PMR Downloaded from https://www.everyspec.com
p. 331
APPENDIX C-20 so that the Cal Labs have an on-line history of each ship's TAMS.
d. When the availability is completed (or optionally the Automated Work Request (AWR) can be created each month or quarter and be closed at the end of the period), the AWR is signed off for processing. A special record is automatically created for each item calibrated against the single CSMP JCN.
e. If any unscheduled TAMS items are delivered by the ship, the Lab (or TYCOM designated support activity) need only to access the PMR record and add it to the outstanding AWR.
f. The Cal Lab can call out a standard REPAIR routine for the specific lab and PMR item. For example, if Lab 67B cannot calibrate one of the 150 items, the unique MJC JCN with the item data from PMR is retrieved against the repairable item. This REPAIR routine assigns 67A (Electronics Repair) as the Assist Work Center and 67B inputs the defective item to 67A. C-7.2 Standard MJC Routines for TAMS Calibration and Weight Testing The "PMR WC" entry of the MJC standard routines identify the specific Logistic Manager Code for each category of TAMS. ET = SPAWAR Electronics, JR = NAVSEA RADIAC, etc. A "2" causes multiple task (line items) per single AWR, and the "MC" is the special suffix assigned to the Master CSMP deferral from the MJC.
From the MJC routine record, a PMR WC entry adjacent to the REPAIR MJC will create one item per AWR. This item will have a unique WC suffix - "CR" for Cal Repair. This allows retrieval of all TAMS repair history from NAVSEALOGCEN by keying on the JCN WC suffix or by MJC JCN which is contained in Block 18 of each MJC-originated CSMP deferral. The LCM code is included on each PMR detailed record reported to NAVSEALOGCEN via 3-M. Downloaded from https://www.everyspec.com
p. 332
NAVSEAINST 4790.8B
C-21
Lab MJC for Cal PMR WC MJC for Repair PMR WC 51C N0000EXCAB702 HE2MC N0000EXCAE702 HE CR 67B N0000OXCAB701 ET2MC N0000OXCAE701 ET CR 67F N0000EXCAB703 JR2MC N0000EXCAE703 JR CR 72D N0000WXCNC719 HW2MC N0000WXCNE719 HW CR 96A N0000EXCAB704 HM2MC N0000EXCAE704 HM CR FCA N0000EXCAB706 HM2MC N0000EXCAE706 HM CR C-7.3 Other Automated System in Support of PMR Other automated systems and system programs interface with the MJC and PMR programs. Refer to TYCOM instructions and system user manuals for particular system capabilities and requirements. C-8 USING MJC JCN STRUCTURE TO MANAGE PROGRAMS The MJC File is created and managed the same as the CSMP file. Each "deferral" is a requirement or special work request (for service, scheduling of alterations or specialized CMP requirements, etc.) which is copied to a CSMP or work package. The method by which many different programs can be added to a single MJC is by control of the MJC JCN. In documenting an MJC, there are exceptions to the standard documenting procedures for a CSMP deferral (OPNAV 4790/2K) as described in other chapters. C-8.1 Fleet/TYCOM/Local Site MJC Control BLOCK 1 UIC. The first character defines the MJC Manager Code and identifies the activity responsible for the MJC item. It is assigned by the TYCOM. This same code is used as a prefix to the MJC JSN log. The following restrictions apply to the use of MJC Manager Code.
A - Not used. Reserved for foreign ship UIC identity. I - Not used. To avoid confusion with numeral 1. O - Not used. To avoid confusion with numeral 0. Q - Not used. To avoid confusion with numeral 0. N - Used for MJC items issued and controlled by TYCOMs. M - Used for MJC items issued and controlled by the Fleet CINC.
a. When MJC items are added to a ship's CSMP, the program adds the original MJC JCN (with an "M"-MJC-prefix) to the "ALTERATION (Block 18)" data field. This allows the 3-M history at NAVSEALOGCEN to be queried relative to man-hour and material cost expenditures. A single calibration routine can provide (by individual ship, RAUIC, type of ship, etc) total cost per TYCOM Downloaded from https://www.everyspec.com
p. 333
APPENDIX C-22 for each and all electronic calibration labs for specific periods of time. In addition, the associated Repair routine will identify each unique piece of TAMS repaired during the same period. C-8.2 Applicability UIC Control BLOCK 1 UIC. The remaining four characters of the MJC UIC identify MJC categories and the type of ships to which they apply.
0000 All Ships 0001 All Surface Ships 0002 All SSNs 0003 All SSBNs 0006 SSN/SSBN 0007 AEGIS CRUISERS 0100 ALTS AS/AD 0210 ALTS SSBN 0230 ALTS SSN 4020 SSN OVERHAUL ROUTINES 5000 TRIDENT UNIQUE 5100 SEA WOLF UNIQUE
For each MJC UIC, there must be a corresponding UIC control record added to the master file. C-8.3 MJC WC Designations a. BLOCK 2 WC. The left two letters identify the shipboard department and division to which the item normally applies. If a specific division is not applicable, use "X". When the MJC item is for multiple departments, use "E" for Engineering.
b. The third and fourth letters identify the maintenance category and its source.
(1) When the third letter is a "C" (a corrective maintenance directive or periodic service routine item), the fourth letter will identify its source as follows:
Code Source of Directive A PLANNED MAINTENANCE SYSTEM (PMS) F NAVSEA H SPAWAR M CINCLANTFLT/CINCPACFLT I,O,Q NOT USED OTHER RESERVED FOR TYCOM USE
(2) Other combinations of the third and fourth letter may be used to identify other categories as directed by TYCOMs.
c. When the MJC item is an alteration controlled through a TYCOM alteration management system or the Fleet Modernization Downloaded from https://www.everyspec.com
p. 334
NAVSEAINST 4790.8B
C-23 Program Management Information System (FMPMIS), the first letter will identify the shipboard department, the second letter will be "X" and the third and fourth letter will identify the type of alteration (SA, TY, etc).
(1) The combination WC and JSN will be assigned by the alteration issuing authority and is displayed along with the structured alteration number on the alteration issuing directive.
(2) The structured alteration number must be recorded in Block 18 of the MJC deferral exactly as described in the AMS chapter. This provides for an error free Alteration Record being added to the ship's CSMP and provides for the necessary 3- M to FMPMIS completion status feedback. Because Block 18 is prefilled, the MJC JCN will not be copied into that field in the CSMP. However, the AMS WC/JSN will be assigned as the ship's WC/JSN. This same combination must be reported on the completed OPNAV 4790/CK Configuration Change Record rather than a shipboard assigned WC/JSN.
(3) An additional restrictive WC/JSN combination is for tracking the standard depot overhaul routines which have an MJC WC of "EXSY" and are identified in OWP so that depot estimates and return costs can be reported to the SWLIN/ESWBS level and individual work center deferrals from the CSMP can be grouped and costed under the EXSY "bucket jobs". These standard EXSY routines retain the MJC WC/JSN when added to the CSMP and allows the ship's engineer and overhaul coordinator to track the overhaul progress by use of the CSMP. NAVSEASYSCOM (SEA 07) directed these procedures be followed by SUPSHIP and Shipyards when costing Departure Reports and to provide for depot 3-M reporting. C-8.4 MJC JSN Prefix for Work Category BLOCK 3. JSN. This entry is the sequence number of the item unique to the MJC "work center" code. It is usually all numeric, but there may be conjunctive or associated actions following an MJC inspection, test or calibration. If so, the total set should reflect a different alphabetic code as the first character of the JSN. C-8.5 Documenting the MJC Deferral The amount of detail within an individual MJC item is dependent on whether the action required is to provide IMA routines such as "Printing Services", specific non-scheduled refurbishment or repair for a recurring failure of a specific Allowance Parts Downloaded from https://www.everyspec.com
p. 335
APPENDIX C-24 List (APL), standard procedure for docking/undocking ships, corrosion control inspections of piping, or PMR scheduling of individual components. Details will be provided by TYCOM directives.
C-8.5.1 Evaluating Requirement for Single or Multi-Task
When the MJC item is being created for general service routines, and is not to interface with PMR configuration and scheduling, follow the standard deferral documentation procedures and describe in the Remarks data field (Block 35 of the 2K) the actions required for the routine. An example entry may read "IMA provide sheet metal service. Limit to 1/8" thick metal. S/F provide sketch on OPNAV 2L. Maximum 100 man hours".
a. When the MJC item is written to interface with the PMR, the detail of the equipment or component is a function of the PMR configuration and scheduling records. When a single requirement requires a single JCN, data element fields for "Alterations" (Block 4), "Component Noun Name" (Block 13), and "Component Identification" (Block 16) of the MJC will contain an asterisk. The data will be pre-filled from PMR when retrieved into the CSMP. An individual work request (JCN) per component is appropriate when multiple work centers are to be involved in the requirement or when there is a requirement for controlled work procedures required by TYCOM Quality Assurance Procedures. For example:
(1) If there were 100 sea valves due for a 72-month refurbishment, 100 separate JCNs would be added to the CSMP.
(2) If there were a second requirement to visually check all sea valves for external corrosion every 24 months, an additional MJC item would be created and another PMR scheduling record would be added to each sea valve configuration record. In this situation, the MJC would be coded as multi-tasked and one JCN would be created with 100 tasks (1 task per valve). The above MJC calibration routines are all coded as multi-tasked.
Downloaded from https://www.everyspec.com
p. 336
NAVSEAINST 4790.8B
C-25 C-8.5.2 Standard Narrative (Block 35)
Narrative should include a statement of the requirement and include notices to the tended unit and LWC on ship to shop or special controls. The deferral narrative is limited to 1200 characters. However, when the AWR is completed, an additional 1200 characters may be used by the LWC to provide feedback information (free-form) to the SYSCOM directing the requirement.
C-8.5.3 Structured Narrative (Block 35)
There are two types of structured narrative provided by MJC:
a. Certain inspection or test criteria are specified by the requirement in which the LWC/AWC is to feedback the material condition assessment by "yes/no" responses to conditional questions printed on the CSMP AWR. In these cases, the narrative will begin with a general statement of the requirement, followed by specific inspection conditions and a response space for "Y" or "N". For example: "Was there evidence of external leakage? ( ); corrosion? ( )."
b. Certain equipment are designated for specialized reporting by the LCM or item manager and the organization. Automated ships'/systems must flag the SEF to display the structured narrative specified and funded by the LCM. This requires the shipboard technician to enter "as found" readings and symptoms which are upline reported for SYSCOM analysis. If an extension of these specialized reporting requirements to the off-ship IMA technician is required, the PMR screen could display a similar format (refer to Appendix A, data element "REMARKS/DESCRIPTION" for Selected Equipment List (SEL) reporting requirements). C-8.6 Documenting the MJC P&E The OPNAV 4790/2P is used for MJC P&E with entries made as described in Appendix C except for the following:
SECTION I - PLANNING
Block A SHIP'S NAME. Enter the "MJC ITEM". Block B HULL NUMBER. Leave Blank Blocks 1-3 JOB CONTROL NUMBER: Enter the same JCN as assigned to the attached MJC 2K. Block 4 PERIODIC MAINTENANCE REQUIREMENT NUMBER. If the MJC is for a PMR, enter the appropriate number from the CMP or other directive. Downloaded from https://www.everyspec.com
p. 337
APPENDIX C-26 Block 5 PERIODICITY. If applicable, enter the periodicity of the requirement. Block 6 YEAR AND MONTH ISSUED. Enter the date (YYMM) the PMR was established. Block 7 SPECIAL DATA. The first two positions are to identify the LCM code controlling the PMR. These codes are listed in the lower right section of the OPNAV 4790/CK (PMR CK). The third position is for entering whether the MJC is to control single (1) or multi-component (2) JCNs. Leave blank if the MJC is for non-PMR service routines. The fourth and fifth position is to record a special program WC suffix to the output CSMP JCN (e.g., Submarine IMMP/URO/LID SEOC program is assigned "JC" as a suffix). If no entry is made, the output JCN will be assigned a WC suffix of "MC". Only alphabetic codes should be assigned to separate MJC retrieved deferrals from shipboard created deficiency deferrals. Block 8 SCREENING ACTION: When authorized by TYCOM instructions, the MJC may be designated as preapproved. Entry of the screening code will cause the MJC retrieval to by-pass normal screening action and the JCN will be sent directly for release to the IMA for accomplishment. Block 9 QUALITY ASSURANCE REQUIREMENTS (QA): Assign the QA requirements applicable to the MJC. The PMR scheduling record for individual components will take precedence during call-down.
SECTION II - SCHEDULING
Block 12 LEAD WORK CENTER (LWC): Enter the code of the LWC assigned to control the coordination and completion of the total JCN. When the MJC is for multi- component inspection/calibration/testing, the primary WC is assigned. When an associated "Repair" MJC is to be created, assign the same primary WC as LWC and other required WCS as assisting (AWC). To ensure standardization for IMA capabilities and continuity when transferring work packages, the TYCOM controlled MJC assigned LWC must not be changed unless approved by TYCOM instruction.
Downloaded from https://www.everyspec.com
p. 338
NAVSEAINST 4790.8B
C-27 Blocks 13, 19, 25, 31, 37, and 43 as required: SCHED START DATE: Enter a numeric value for the start day relative to the start of the availability. When the MJC is subsequently retrieved and added to the CSMP, the relative day will be added to the availability start date and output as a Julian date that each task is to be started by the LWC and any AWCs. Note that multi-component MJCs will not include AWC entries. C-8.7 Establish Bill of Materials Interface When the MJC is for refurbishment of APL identified components, the repair part requirements (both mandatory and conditional) are provided on magnetic media by the LCM or TYCOM assigned activity (SUBMEPP/PERA).
When the MJC is retrieved for each component, an automated material requisition is produced for mandatory parts and a list of contingency items provided with the work request.
The same format record can be added by local sites if local MJC items are developed. C-8.8 MJC Alteration Documentation Differences Alterations added to the MJC will be limited to those managed by the AMS. These are identified by the assignment of the AMS WC/JSN and structured alteration number as described in the Joint Fleet Maintenance Manual (JFFM).
Block 1 SHIP'S UIC: Enter the MJC UIC established by the TYCOM Blocks 2-3 WC AND JSN: Enter the WC/JSN assigned by the alteration issuing authority. Block 18 ALTERATIONS: Enter in position 1 and 2 the alteration type identified in Appendix C. This entry must match the WC suffix in the WC field (Block 2). Block 27 S/F MHRS REM: Entry must be numeric. The use of "AUTO" (auto-close) is not appropriate for MJC alterations. Completion of deferrals for alterations must be by OPNAV 4790/CK. C-8.9 MJC Index and Statistics The MJC Index (Figure C-2) is produced as required by TYCOM instructions. A number of selection parameters are provided during call-down to limit the volume of the Index to particular Downloaded from https://www.everyspec.com
p. 339
APPENDIX C-28 applications. MJC JCNs required by tended ships may be recorded on the OPNAV 4790/2L and provided to the TYCOM-designated support activity during the availability arrival conference. Selected MJC JCNs may be called down as directed by the TYCOM prior to the availability or by quarter year (e.g., calibration routines) and may be assigned to other than the scheduled availability. This allows the Production Management Assistant (PMA) and other managers to focus on correction of deficiencies with weekly status reports of service routines progression.
Also available is the MJC Call-Down Frequency Report. A number of selection parameters are provided to limit the volume of the report to particular applications. Available is a report on the number of times the MJC JCN was retrieved and the last retrieval date. This report allows monitoring of mandated JCN call-downs and also provides for culling out of locally created MJC routines which are seldom used. (Refer to the applicable system's user manual for additional reports that may be generated.) C-8.10 Analysis of MJC/PMR Originated Production History Each JCN called down from the MJC as a deferral into the Master CSMP is assigned a CSMP JCN different than the MJC JCN. Each specialized project may be assigned a unique WC suffix so that the Program Manager may retrieve selective history from the NAVSEALOGCEN 3-M data base (see Figure C-3 MJC Call Down Frequency Report).
Some special program WC suffix codes currently being used are:
_XSA SHIPALTS _XTY TYCOM ALTS EXSY Depot Level (SY=ShipYard) availability routines. These routines assign standard 3-M data to each. ESWBS/SWLIN For Depot Return Cost Departure Reports as approved by NAVSEASYSCOM (SEA 07) _XCR Jobs for repair of components that failed calibration or weight testing. Each failed component will be assigned a unique JCN. __JC IMMP/RO/LID and other scheduled CMP PMRs
When a special program code is not assigned, the program will assign a WC suffix of "MC".
If allowed by TYCOM instructions, the ship may assign its own WC/JSN to the MJC routine. Downloaded from https://www.everyspec.com
p. 340
NAVSEAINST 4790.8B
C-29
With the exception of MJC Alterations, each retrieved MJC deferral will have its MJC JCN prefixed with an "M" and be written to the Configuration/Alteration Number field (block 18) of the CSMP deferral.
When the MJC is designated as multi-level, the MJC call-down is linked to the PMR scheduling file and retrieves all due and overdue components as tasks within the one CSMP deferral JCN. This will result in a family of data records being created to capture the METCAL required data when the lab reports completion of each component.
Each Program Manager is able to retrieve and analyze all transactions unique to the MJC JCN and WC suffices assigned to a special program. C-8.11 Modification of On-Site MJC Implementation, distribution and maintenance of the MJC will be as described in this instruction and supplemented by Fleet/ TYCOM instructions. It is essentials that existing MJC files, which have common application, be adapted by those commands not yet implemented. This will speed the integration of the Regional Maintenance Hubs and provide continuity to the existing 3-M database for Program Manager requirements.
The Fleet Maintenance Management System will provide connectivity to the initiatives of the SYSCOMs' for data storage and distribution.
The FLTCINCs/TYCOMs will provide instructions for management of the MJC to include centralized and on-site control.
The existing method of confirming updates to the MJC by the IMAs is by including a "completed AWR record" in the update files sent from the originator. The originator subsequently monitors the MDS data.
Downloaded from https://www.everyspec.com
p. 341
APPENDIX C-30
Figure C-2: Master Job Catalog Index Page Downloaded from https://www.everyspec.com
p. 342
NAVSEAINST 4790.8B
C-31
Figure C-3: MJC Call Down Frequency Report
Downloaded from https://www.everyspec.com
p. 343
NAVSEAINST 4790.8B
D-1 MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL
APPENDIX D SHIPS' 3-M FORMS AND PMS MANAGEMENT TOOLS ORDERING INFORMATION
PMS MANAGEMENT TOOLS NSN
Conventional Sizes
Weekly PMS Schedule Holder, Single Display Surface.....................................1H9905-00-255-5930 Weekly PMS Schedule Holder with 1 Hinged Panel,3 Display Surfaces......................1H9905-00-255-5932 #2 Panel for Weekly PMS Schedule Holder 5932 increases to 5 Display....................1H9905-00-255-5933 #3 Panel for Weekly PMS Schedule Holder 5932 w/5933 increases to 7 Display Surfaces....1H9905-00-255-5934 MCB (Maintenance Control Board), Standard, 2 Hinged Panels, 6 Surfaces.................1H9905-00-255-5954 MCB Hinged Panel, 1 Panel, 2 Additional Display Surfaces, increases 5954 to 8 Surfaces.1H9905-00-255-5953 MCB Hinged Panel, 1 Panel, 2 Additional Display Surfaces, incr 5954 w/5953 to 10 Surfaces ..................................................................1H9905-00-255-5952 MCB (Maintenance Control Board), 10 Surfaces...........................................1H9905-00-255-5951 MCB Hinged Panel, 1 Panel, 2 Additional Display Surfaces, increases 5951 to 12 Surfaces ....................................................................1H9905-00-255-5950 MCB Hinged Panel, 1 Panel, 2 Additional Display Surfaces, incr 5951 w/5950 to 14 Surfaces ....................................................................1H9905-00-255-5949 MCB Hinged Panel, 1 Panel, 2 Addnl Display Surfaces, incr 5951 w/5950 & 5949 to 16 Surfaces ................................................................1H9905-00-255-5948
Compact Sizes
Weekly PMS Schedule Holder, Single Display Surface.....................................1H9905-00-255-5931 Weekly PMS Schedule Holder with 1 Hinged Panel, 3 Display Surfaces.....................1H9905-00-255-5935 #2 Panel for Weekly PMS Schedule Holder 5935 increases to 5 Display Surfaces...........1H9905-00-255-5936 #3 Panel for Weekly PMS Schedule Holder 5935 w/5936 increases to 7 Display Surfaces....1H9905-00-255-5937 MCB, Compact, 3 Hinged Panels, 7 Display Surfaces......................................1H9905-00-255-5955 #4 MCB Hinged Panel, 1 Panel, 2 Additional Display Surfaces, increases 5955 to 9 Surfaces .....................................................................1H9905-00-255-5938 #5 MCB Hinged Panel, 1 Panel, 2 Addnl Display Surfaces, incr 5955 w/5938 to 11 Surfaces ....................................................................1H9905-00-255-5956
Maintenance Requirement Card Holders
Standard MRC and Maintenance record Holder.............................................1H9905-00-255-5929 Large Capacity MRC and Maintenance Record Holder.......................................1H9905-00-255-5960
PMS OPNAV FORMS NAME/NUMBER
Cycle PMS Schedule (conventional) OPNAV 4790/13........................................1I0107-LF-770-3220 Quarterly PMS Schedule (conventional) OPNAV 4790/14....................................1I0107-LF-770-3241 Weekly PMS Schedule (conventional) OPNAV 4790/15.......................................1I0107-LF-770-3260 Cycle PMS Schedule (compact) OPNAV 4790/13A............................................1I0107-LF-770-3230 Quarterly PMS Schedule (compact) OPNAV 4790/14A........................................1I0107-LF-770-3250 Weekly PMS Schedule (compact) OPNAV 4790/15A...........................................1I0107-LF-770-3270 PMS Feedback Report, OPNAV 4790/7B.....................................................1I0107-LF-007-8000
OTHER FORMS USED IN PMS
Maintenance Requirement Card OPNAV 4790/85.............................................1I0107-LF-047-9410 Maintenance Requirement Card (MRC) Continuation Card OPNAV 4790/83.....................1I0107-LF-047-9415 Maintenance Index Page (MIP) OPNAV 4790/85.............................................1I0107-LF-047-9420 Tag Guide List OPNAV 4790/107..........................................................1I0107-LF-047-9545 Technical Publication Deficiency Report OPNAV 4790/66..................................1I0107-LF-002-4400 Equipment Guide List OPNAV 4790/81.....................................................1I0107-LF-047-9405
II. SHIPS' 3-M MDS FORMS
Ship's Configuration Change Form OPNAV 4790/CK.........................................1I0107-LF-047-9001 Ship's Configuration Change Form Continuation Page OPNAV 4790/CK(C)....................1I0107-LF-047-9010 Ship's Maintenance Action Form OPNAV 4790/2K...........................................1I0107-LF-047-9011 Supplemental Form OPNAV 4790/2L........................................................1I0107-LF-770-3060 Maintenance Planning and Estimating Form (P&E)OPNAV 4790/2P............................1I0107-LF-770-3079 Downloaded from https://www.everyspec.com
p. 344
NAVSEAINST 4790.8B
E-1
MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL
APPENDIX E
LIST OF ACRONYMS
A
A&I Alteration and Improvement ACF Accomplishment Confidence Factor ACN Advance Change Notice ACU Assault Craft Unit ADP Automated Data Processing ADPE Automated Data Processing Equipment AEC Assessment of Equipment Condition AEL Allowance Equipage List AER Alteration Equivalent to Repair AILSIN Automated Integrated Language System Identification Number AIS Automated Information Systems AIMD Aircraft Intermediate Maintenance Department AIT Alteration Installation Team ALID Automated Library Issue Document ALRE Aviation Launch and Recovery Equipment AMS Alteration Management System AMT Amalgamated Military/Technical Improvement Plans APL Allowance Parts List AR Alteration Request ASG Afloat Shipping Guide ASI Automated Shore Interface ATG Afloat Training Group ATO Afloat Training Organization AWR Automated Work Request
B
BACD Basic Alteration Class Drawings BOATALT Boat Alteration BOC Base Operating Contract BUIC Benefiting Unit Identification Code BUMED Bureau of Medicine and Surgery
Downloaded from https://www.everyspec.com
p. 345
APPENDIX E-2 C
CA Coordinating Activity CAGE Commercial and Government Entity CANTRAC Catalog of Naval Training Courses CASREP Casualty Report CCF Configuration Change Form CD-ROM Compact Disk - Read Only Memory CDA Central Design Activity CDM Configuration Data Manager CFFC Commander Fleet Forces Command CID Component Identification Number CINC Commander in Chief CIS Commercial Industry Service CM Corrective Maintenance CMP Class Maintenance Plan CNO Chief of Naval Operations COMNAVSEASYSCOM Commander Naval Sea Systems Command COMSPAWARSYSCOM Commander Space and Naval Warfare Systems Command COSAL Coordinated Shipboard Allowance List CSA Navy's Central Configuration Status Accounting System CSMP Current Ship's Maintenance Project
D
DATC Development and Training Center DBI Demand Based Items DCA Damage Control Assistant DCPO Damage Control Petty Officer DEN Data Element Number DFS Departure from Specification DIRSSPO Director Strategic Systems Project Office DLR Depot Level Repairable DOD Department of Defense DPMA Docking Phased Maintenance Availability DSRV Deep Submergence Recovery Vehicles DSS Deep Submergence System DT Downtime
E
EC Engineering Change ECP Engineering Change Proposal EGL Equipment Guide List EIC Equipment Identification Code Downloaded from https://www.everyspec.com
p. 346
NAVSEAINST 4790.8B
E-3 ELEX Electronics Equipment EOSS Engineering Operational Sequencing System ESWBS Expanded Ship Work Breakdown Structure
F
FBR Feedback Report FC Field Change FGC Functional Group Code FLETRACEN Fleet Training Center FLETRAGRU Fleet Training Group FLR Field Level Repairable FLTC Fleet Commander FMP Fleet Modernization Program FMPMIS Fleet Modernization Program Management Information System (See NDE) FMSO Fleet Material Support Office FPR Failed Part Reporting FR Force Revision FSCM Federal Supply Code for Manufacturers FTC Fleet Training Command FTSCLANT Fleet Technical Support Center, Atlantic FTSCPAC Fleet Technical Support Center, Pacific
H
HAZMAT Hazardous Material HM&E Hull, Mechanical, and Electrical Equipment HMUG Hazardous Material User's Guide HT Hull Technician
I
IEM Inactive Equipment Maintenance ILO Integrated Logistics Overhaul ILS Integrated Logistics Support ILSMT Integrated Logistics Support Maintenance Team IM Intermediate Maintenance IMA Intermediate Maintenance Activity IMAV I-Level Maintenance Availability INSURV Board of Inspection and Survey ISE In-Service Engineer ISEA In-Service Engineering Agent ISIC Immediate Superior in Command IUC Intermediate Unit Commander
Downloaded from https://www.everyspec.com
p. 347
APPENDIX E-4 J
JCN Job Control Number JETDS Joint Electronic Type Designation System JSN Job Sequence Number
L
LATD Lacks Adequate Technical Description LID Library Issue Document LOEC List of Effective Cards LOEP List of Effective Pages LSD Logistic Support Data LU Lay-Up Maintenance LWC Lead Work Center
M
MA Maintenance Action MACHALT Machine Alteration MACN Manual Advance Change Notice MCB Maintenance Control Board MCC Material Control Code MDCO Maintenance Document Control Office MDS Maintenance Data System MDSTEIR Maintenance Data System Transaction Error Identification Report MEASURE Metrology Automated System for Uniform Recall and Reporting MH Man-hour MHR Material History Report MILSTRIP Military Standard Requisitioning and Issue Procedures MIP Maintenance Index Page MIS Management Information System MJC Master Job Catalog MPR MDS Performance Rate MR Maintenance Requirement MRC Maintenance Requirement Card MRS Maintenance Requirement Substantiated MSC Maintenance Support Center MTR Mandatory Turn-In Repairable MTS Moored Training Ship MTSSY Moored Training Ship Support Yard
Downloaded from https://www.everyspec.com
p. 348
NAVSEAINST 4790.8B
E-5 N
NALCOMIS Naval Aviation Logistics Management Information System NAALS Naval Air Navigation and Landing Systems NAVCOMTELSTA Naval Computer and Telecommunications Station NAVDAC Naval Data Automation Command NAVMEDLOGCOM Naval Medical Logistics Command NAVSEA Naval Sea Systems Command NAVSEASYSCOM Naval Sea Systems Command NAVSEALOGCEN Naval Sea Logistics Center NC Not Carried NDE Navy Data Environment NEC Navy Enlisted Classification NHA Next Higher Assembly NICN Navy Item Control Number NIR No Individual Requirement NISMF Navy Inactive Ship Maintenance Facility NMR No Maintenance Required NROTC Naval Reserve Officers Training Corps NSDSA Naval Sea Data Support Activity NSN National Stock Number NSWCCD SSES Naval Surface Warfare Center, Carderock Division Ship Systems Engineering Station NTCSS Navy Tactical Command Support System
O
OA Ordnance Alteration (See ORDALT) OCS Officer Candidate School O&MN Operation and Maintenance Navy OM Organizational Maintenance OMMS-NG Organizational Maintenance Management System- Next Generation OPNAV Naval Operations (CNO staff) ORD Ordnance Equipment ORDALT Ordnance Alteration OT Operational Test OWP Overhaul Work Package (Submarines)
P
PD Priority Designator PEB Propulsion Examining Board PEETE Portable Electrical/Electronic Test Equipment PM Periodic Maintenance PMDO Planned Maintenance During Overhaul Downloaded from https://www.everyspec.com
p. 349
APPENDIX E-6 PMR Periodic Maintenance Requirement PMS Planned Maintenance System PMT Performance Monitoring Team POM Program Objective Management PPE Personal Protective Equipment PPR PMS Performance Rate PQS Personnel Qualification Standard PREINSURV Pre-Inspection and Survey PSA Post-Shakedown Availability
Q
QA Quality Assurance
R
RAUIC Repair Activity Unit Identification Code RAV Restricted Availability RCM Reliability-Centered Maintenance REC Re-entry Control RIC Repairable Identification Code RIN Record Identification Number RM&A Reliability, Maintainability, and Availability ROH Regular Overhaul ROV Repair of Other Vessels RWC Repair Work Center RSG/MCC Readiness Support Group/Maintenance Coordinating Center
S
SAC Service Application Code SAR Ship Alteration Record SARP Ship Alteration and Repair Package SCAT Sub-Category Code SCLSC Ship Configuration Logistic Support Control SCLSIS Ship Configuration Logistic Support Information System SEAS Supply Edit Audit and SIM System SEF Ship Equipment File SEL Selected Equipment List SFWL Ships Force Work List SHAPM Ship Acquisition Program Manager SHIPALT Ship Alteration SHIPMER Ship Maintenance Effectiveness Review SIMA Shore Intermediate Maintenance Activity SLCC Ship's Logistics Component Configuration Downloaded from https://www.everyspec.com
p. 350
NAVSEAINST 4790.8B
E-7 SLEC Ship's Logistics Equipment Configuration SLM Ship Logistics Manager SMIC Special Material Identification Code SMIP Ships' 3-M Systems Improvement Program SMMSO SSBN Maintenance Monitoring Support Office SMS Surface Missile System SNAP Shipboard Non-Tactical ADP Program SOC Scope of Certification SPALT Special Projects Alteration SPAWARSYSCOM Space and Naval Warfare Systems Command SPETERL Ship's Portable Electrical/Electronics Test Equipment Requirements List SPIN Standard PMS Item Name SPMIG Standard PMS Material Identification Guide SRD Selected Record Date/Drawing SSC Supply Support Center STEP Shipboard Training Enhancement Program SU Start-Up Maintenance SUBMEPP Submarine Maintenance, Engineering, Planning, and Procurement SUPSHIP Supervisor of Shipbuilding, Conversion, and Repair, USN SURFMER Surface Ship Maintenance Effectiveness Review SWAB Ship Work Authorization Boundary SWBS Ship Work Breakdown Structure SWLIN Ship Work Line Item Number SYSCOM Systems Command
T
T/A Type Availability TAV Technical Availability TECSUPGRU Technical Support Group TEI Test Equipment Index TFBR Technical Feedback Report TGL Tag Guide List TM Technical Manual TMDER Technical Manual Deficiency/Evaluation Report TRF Trident Refit Facility TSU TYCOM Support Unit TYCOM Type Commander TYCOM REP Type Commander Representative
Downloaded from https://www.everyspec.com
p. 351
APPENDIX E-8 U
UIC Unit Identification Code UND Urgency of Need Designator UM Unscheduled Maintenance USNA U.S. Naval Academy
W
WC Work Center WDC Work Definition Conference WPNSTA Weapons Station WSF Weapon Systems File
MISCELLANEOUS
2-M Miniature/Microminiature Repair (Electronic Modules) 2P Planning and Estimating Record 3-M Maintenance and Material Management System 3MPR 3-M Performance Rate CK Configuration Change Record
Downloaded from https://www.everyspec.com
p. 352
NAVSEAINST 4790.8B
F-1
MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL
APPENDIX F
SHIPS' 3-M POINTS OF CONTACT
TELEPHONE NUMBERS ACTIVITY/CODE DSN AREA COMM EXT
***CNO (N431H) CHIEF OF NAVAL OPERATIONS N431H WASHINGTON DC 20350-2000 329 703 601-1665
***COMLANTFLT (N432) COMMANDER U S ATLANTIC FLEET N432 1562 MITSCHER AVE SUITE 250 NORFOLK VA 23551-2487 836 757 836-3754
***COMPACFLT (Code 4314C) COMMANDER U S PACIFIC FLEET CODE 4314C PEARL HARBOR HI 96860-7000 474 808 474-6353
***COMNAVAIRLANT (N71) COMMANDER NAVAL AIR FORCE U S ATLANTIC FLEET CODE (N71) NAVAL AIR STATION BLDG S29 NORFOLK VA 23511 564 757 444-8836/8949
***COMNAVAIRPAC (N435) COMMANDER NAVAL AIR FORCE U S PACIFIC FLEET N435 P O BOX 357051 SAN DIEGO CA 92135-7051 735 619 545-1523
***COMNAVSURFLANT (N432) COMMANDER NAVAL SURFACE FORCE U S ATLANTIC FLEET N432A64/N432A65 1430 MITSCHER AVENUE NORFOLK VA 23551-2494 836 757 836-3367
Downloaded from https://www.everyspec.com
p. 353
APPENDIX F-2 TELEPHONE NUMBERS ACTIVITY/CODE DSN AREA COMM EXT
***COMNAVSURFPAC (N41) (3-M Officer) COMMANDER NAVAL SURFACE FORCE U S PACIFIC FLEET N41 2841 RENDOVA ROAD SAN DIEGO CA 92155-5490 577 619 437-3513
***COMNAVSURFPAC (N41) (ATG) (Afloat Training Group Pacific) COMMANDER AFLOAT TRAINING GROUP PACIFIC N41 3455 STURTEVANT ST STE 1 SAN DIEGO CA 92136-5069 526 619 556-1792
***COMSUBLANT (N4071A) COMMANDER SUBMARINE FORCE U S ATLANTIC FLEET N4071A 7958 BLANDY BLVD NORFOLK VA 23551-2492 836 757 836-1278
***COMSUBPAC (N4721) COMMANDER SUBMARINE FORCE U S PACIFIC FLEET N4721 1430 MORTON STREET BLDG 665 PEARL HARBOR HI 96860-6543 808
473-5577
128
***COMNAVRESFOR (Code N4) COMMANDER NAVAL RESERVE FORCES CODE N4 4400 DAUPHINE STREET NEW ORLEANS LA 70146-5100 678 504 678-5715
***COMMINEWARCOM (N841) COMMANDER MINE WARFARE COMMAND N841 325 FIFTH STREET S.E. CORPUS CHRISTI TX 78419-5032 861 361 961-4852
Downloaded from https://www.everyspec.com
p. 354
NAVSEAINST 4790.8B
F-3 TELEPHONE NUMBERS ACTIVITY/CODE DSN AREA COMM EXT
***COMNAVSEASYSCOM (SEA 04RM11) (Ships' 3-M (SEA 04RM11)) COMMANDER NAVAL SEA SYSTEMS COMMAND SEA 04RM11 1333 ISAAC HULL AVE SE STOP 4111 WASHINGTON NAVY YARD DC 20376- 4111 326 202 781-3374/3372
***COMNAVSEASYSCOM (SEA 04L5) (Fleet Logistics Support – Configuration Management (SCLSIS)) COMMANDER NAVAL SEA SYSTEMS COMMAND SEA 04L5 1333 ISAAC HULL AVE SE STOP 4066 WASHINGTON NAVY YARD DC 20376- 4066 326 202 781-1852/3346
***COMNAVSEASYSCOM (SEA 04RM) (Maintenance Engineering & Technology Transfer Division) COMMANDER NAVAL SEA SYSTEMS COMMAND SEA 04RM 1333 ISAAC HULL AVE SE STOP 4111 WASHINGTON NAVY YARD DC 20376- 4111 326 202 781-3382
***COMNAVAIRSYSCOM (AIR 3.6) (AVIATION 3-M) COMMANDER NAVAL AIR SYSTEMS COMMAND AIR 3.6 LOGISTICS SUPPORT DEPARTMENT 47060 MCLEOD ROAD UNIT 8 PATUXENT RIVER MD 20670-1625
757 301 757-8790
Downloaded from https://www.everyspec.com
p. 355
APPENDIX F-4 TELEPHONE NUMBERS ACTIVITY/CODE DSN AREA COMM EXT
***COMSPAWARSYSCOM (04L) COMMANDER SPACE AND NAVAL WARFARE SYSTEMS COMMAND 04L 4301 PACIFIC HIGHWAY SAN DIEGO CA 92110-3127 524 858 537-0521
***COMNAVSUPSYSCOM (SUP 412) COMMANDER NAVAL SUPPLY SYSTEMS COMMAND SUP 412 5450 CARLISLE PIKE P O BOX 2050 MECHANICSBURG PA 17055-0791 430 717 605-7254
***FIRSTNCD (N432) FIRST NAVAL CONSTRUCTION DIVISION 1310 8TH STREET, SUITE 100 NORFOLK VA 23521-2435 253 757 462-8131 169
***TRASUPCEN NORFOLK DET COMMANDING OFFICER TRAINING SUPPORT CENTER NORFOLK DET 9545 BAINBRIDGE AVENUE NORFOLK VA 23511-2794 565 757 445-7353 1098 ***FTSCLANT (Code 4103) COMMANDING OFFICER FLEET TECHNICAL SUPPORT CENTER, ATLANTIC CODE 4103 9727 AVIONICS LOOP NORFOLK VA 23511-4396 646 757 443-3872 2576
***FTSCPAC (Code 401) COMMANDING OFFICER FLEET TECHNICAL SUPPORT CENTER PACIFIC CODE 401 3375 SENN ROAD SUITE 1 SAN DIEGO CA 92186-5002 524 619 524-2647 Downloaded from https://www.everyspec.com
p. 356
NAVSEAINST 4790.8B
F-5 TELEPHONE NUMBERS ACTIVITY/CODE DSN AREA COMM EXT
***NSWC CD SSES (Code 952) (Assessment of Equipment Condition (AEC) Program) COMMANDING OFFICER NSWC CD SSES PHILADELPHIA CODE 952 5001 SOUTH BROAD STREET PHILADELPHIA PA 19112-1403 443 215 897-7440
***NSWC CD SSES (Code 942) (Hull, Mechanical and Electrical PMS) COMMANDING OFFICER NSWC CD SSES PHILADELPHIA CODE 942 5001 SOUTH BROAD STREET PHILADELPHIA PA 19112-1403 443 215 897-1361
***INSURV PRESIDENT PRESIDENT BOARD OF INSPECTION AND SURVEY 2600 TARAWA COURT SUITE 250 NORFOLK VA 23521 253 757 462-7006
***CENTER FOR SERVICE SUPPORT COMMANDING OFFICER CENTER FOR SERVICE SUPPORT FIM DIRECTORATE 1425 PRINCE AVENUE ATHENS GA 30677
354 706 355-7501
***SPAWARSYSCEN NORFOLK COMMANDING OFFICER SPACE AND NAVAL WARFARE SYSTEMS CENTER NORFOLK 1837 MORRIS STREET SUITE 3311 NORFOLK VA 23511-3432 *24 HOUR TROUBLE DESK 646
588 757
800 443-0400
836-1816* 5665
Downloaded from https://www.everyspec.com
p. 357
APPENDIX F-6 TELEPHONE NUMBERS ACTIVITY/CODE DSN AREA COMM EXT
***SPAWARSYSCEN NORFOLK (Code 60) DET SAN DIEGO, CA OFFICER IN CHARGE SPAWARSYSCEN CHESAPEAKE DETPAC CODE 60 P O BOX 217 NAVAL STATION SAN DIEGO CA 92136-5217 *24 HOUR TROUBLE DESK 526
526 619
619 556-7671
556-7648*
***NAVSEALOGCEN (Code 60) COMMANDING OFFICER NAVAL SEA LOGISTICS CENTER CODE 60 P O BOX 2060 5450 CARLISLE PIKE MECHANICSBURG PA 17055-0795 430 717 605-4730
***NSDSA (Code 0310) COMMANDER NAVAL SURFACE WARFARE CENTER, PORT HUENEME DIV NAVAL SEA DATA SUPPORT ACTIVITY CODE 0310 4363 MISSILE WAY PORT HUENEME CA 93043-4307 982 805 228-0777
Downloaded from https://www.everyspec.com
p. 358
MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL
APPENDIX G
MANUAL PREPARATION OF PMS SCHEDULES
Downloaded from https://www.everyspec.com
p. 359
APPENDIX G-i APPENDIX G
MANUAL PREPARATION OF SCHEDULES TABLE OF CONTENTS
Paragraph Title Page
G-1 PURPOSE .................................................. G-1 G-2 PREPARATION OF CYCLE PMS SCHEDULE ........................ G-1 G-3 PREPARATION OF QUARTERLY PMS SCHEDULE .................... G-4 G-4 PREPARATION OF WEEKLY PMS SCHEDULE ....................... G-6
Downloaded from https://www.everyspec.com
p. 360
NAVSEAINST 4790.8B
G-1 APPENDIX G
MANUAL PREPARATION OF SCHEDULES G-1 PURPOSE This appendix provides instruction on how to create and maintain cycle, quarterly and weekly schedules for commands that are unable to utilize the SKED Program. Appendix H will also assist in those instances when SKED is not available due to network and or computer difficulties and the Work Center needs to manually track PMS accomplishment until the program is available. G-2 PREPARATION OF CYCLE PMS SCHEDULE Cycle PMS Schedules are used to plan and schedule maintenance requirements to be conducted during each calendar quarter. Department heads should devote considerable attention to the preparation of the Cycle schedule since these efforts will directly affect long-range PMS scheduling.
a. Materials required for preparation:
(1) Blank Cycle schedules (OPNAV 4790/13 or OPNAV 4790/13A).
(2) The work center's portion of the PMS Master File (List of Effective Pages (LOEP)) (Report No. PMS 5)
(3) Applicable MRCs (for general reference) from the Work Center's PMS Manual.
(4) Applicable MIPs from the work center’s file.
b. Procedures:
(1) Initial entries will be typed or legibly written in black ink on the Cycle schedules. Changes will be made in ink and initialed. In the "Schedule Quarter After Overhaul As Indicated" columns, each quarter is circled when the schedule for that quarter has been prepared. The previous quarter is X'd out.
(2) The cycle numbering will be reset after three Inter-Deployment Training Cycles or Docking Availability. The next full calendar quarter following completion will be designated as the "first quarter after overhaul." Shore stations will reset after every 20 quarters.
Downloaded from https://www.everyspec.com
p. 361
APPENDIX G-2 (3) From the LOEP, accurately transcribe each item of equipment in MIP sequence excluding equipment coded "NIR", "NMR", and “MRS” on the Cycle schedule. If desired, list the MIPs for equipment coded "MRS", and complete the scheduling information for those items when the developed PMS is received. (Note: It is not necessary for the Cycle schedule to match the LOEP line for line.)
(a) Use the MIP column to list the MIP code without the date coding, e.g., E-l/55, EL-2/BO, 4411/I, etc.
(b) Use the Component column to list the name of each system, subsystem, or equipment. When more than one item is located within a work center, the serial numbers or ship's numbering system shall be entered to identify each item on a single line of the schedule. The location may be entered. "EGL" shall be entered in this column when an EGL is applicable. When multiple EGLs are used, they can be scheduled on separate lines or on one line (or group of lines) as "1-Q-1", "2-Q-1", "3-Q-l", etc.
(4) From the applicable MIP, list the periodicity codes in the "Schedule Quarter After Overhaul As Indicated" and "Each Quarter" column as described below. Only the presence of mandatory related maintenance will be indicated by the "#” symbol associated with the parent MR (e.g., "S-l#").
(a) In the column "Schedule Quarter After Overhaul As Indicated:”
1. List each semiannual (S) maintenance requirement in one of the four columns, then list again 6 months later. For example, an S-1 requirement scheduled to occur in the 1, 5, -and 9 quarters is also scheduled in the 3, 7, and 11 quarters.
2. List each annual (A) maintenance requirement in one of the four columns.
3. List each multiple month periodicity MR (9M, 18M, 24M, 30M, 36M, etc.). Quarter after overhaul must be indicated in parentheses. (For example, l8M-1(6) indicates an "every 18 months" periodicity MR scheduled to be accomplished in the sixth quarter after overhaul.) The following tables serve as examples for determining quarter after overhaul. To use these tables, determine in which quarter after overhaul the MR will first occur. Go to this quarter in the first row of the table. Downloaded from https://www.everyspec.com
p. 362
NAVSEAINST 4790.8B
G-3 Then schedule the MR for the quarters in that column as applicable. (For example, if l8M-1 is scheduled for the 4th quarter after overhaul, it must also be scheduled for the 10th, 16th, and 22nd quarter after overhaul; as applicable.) The table elements below are listed by quarters (3 months = 1 quarter).
18M Scheduling Table
First Scheduling: 1 2 3 4 5 6 Second Scheduling: 7 8 9 10 11 12 Third Scheduling: 13 14 15 16 17 18 Fourth Scheduling: 19 20 21 22 23 24
24M Scheduling Table
First Scheduling: 1 2 3 4 5 6 7 8 Second Scheduling: 9 10 11 12 13 14 15 16 Third Scheduling: 17 18 19 20 21 22 23 24
30M Scheduling Table
First Scheduling: 1 2 3 4 5 6 7 8 9 10 Second Scheduling: 11 12 13 14 15 16 17 18 19 20 Third Scheduling: 21 22 23 24
36M Scheduling Table
First Scheduling: 1 2 3 4 5 6 7 8 9 10 11 12 Second Scheduling: 13 14 15 16 17 18 19 20 21 22 23 24
48M Scheduling
First scheduling in first 16 quarters Second scheduling 16 quarters later
60M Scheduling
First scheduling in first 20 quarters Second scheduling 20 quarters later
NOTE
Prior to scheduling 30M, 36M; 48M, or 60M, review MRC to see if specific quarter after overhaul is indicated
Downloaded from https://www.everyspec.com
p. 363
APPENDIX G-4 4. Ships with cycles of less than 24 quarters are to schedule cycle requirements within this operational time frame. Ships delayed beyond 24 quarters are to extend their Cycle PMS Schedule by adding quarter numbers in the "Schedule Quarter After Overhaul As Indicated" column. (Multiple month requirements needed before entering overhaul must be reviewed and rescheduled as necessary.)
(a) In the "Each Quarter" Column: List 2W, 3W, M, 2M, and Q maintenance requirements, and all situational requirements. Only the presence of mandatory related maintenance will be indicated by a "#" symbol with the parent MR.
5. The prepared Cycle PMS Schedule is reviewed, signed, and dated by the Department Head. Once the cycle schedule has been signed, maintenance requirements listed are not to be moved from one quarter to another. If rescheduling becomes necessary, it will be reflected on the Quarterly PMS Schedules.
6. All superseded Cycle schedules will be retained for 12 months. G-3 PREPARATION OF QUARTERLY PMS SCHEDULE OPNAV 4790/14 or 14A (for SSBNs, 14B or 14C) will be used. Initial form entries will be typed or legibly written in black ink. Changes will be made in ink and initialed. Process is as follows:
a. Enter the work center code.
b. Enter the calendar year of the current quarter.
c. Enter the number of the quarter after overhaul as reflected on the Cycle PMS Schedule.
d. Enter the calendar months of the quarter (SSBNs will prepare quarterly schedules to coincide with crew cycle).
e. Each column represents a week and is divided into 7 days by the use of tick marks across the top. The first tick marked space within a column represents Monday. Monday's date for each week in the quarter is placed on the pedestal between each column. The first Monday in January, April, July, or October will begin each quarter.
Downloaded from https://www.everyspec.com
p. 364
NAVSEAINST 4790.8B
G-5 f. The days the ship expects to be underway are lightly shaded (in pencil) across the tick marks (this does not apply to submarines).
g. Using both the LOEP and the Cycle PMS Schedule, enter the complete MIP number in the column titled "MIP" in a space in line with the subject equipment on the cycle schedule. From the Cycle PMS Schedule, select the "Schedule Quarter After Overhaul As Indicated" column corresponding to the quarter being scheduled. Transcribe and appropriately schedule each of the maintenance requirements (S, A, and multi-month) listed in this column to the quarterly schedule. From the maintenance requirements listed in the "Each Quarter" column, transcribe and appropriately schedule only 2W, 3W, M, 2M, and Q MRs. The intervals of periodic maintenance are defined as:
(1) Monthly--Will be scheduled within the interval between 3 and 6 weeks following the last accomplishment. A monthly PMS maintenance requirement must be scheduled three times in a quarter. Note: If a monthly maintenance check is circled and rescheduled, it may be necessary to move all subsequent checks to meet allowed intervals.
(2) Multi-Month, less than annual.
(a) 2M--Every second month within the interval between seven and ten weeks.
(b) 9M--Every ninth month within the interval between 8 and 10 months from its last accomplishment.
(3) Quarterly--Will be scheduled once each quarter within the interval 2 to 4 months following the last accomplishment.
(4) Semiannual--Within the interval between 4 and 8 months following last accomplishment.
(5) Annual--Within the interval between 3 and 5 quarters following last accomplishment.
(6) Multi-months greater than annual. Those MRs performed less frequently than once a year (e.g., 18M, 24M, 36M, etc.) within the interval of plus/minus one quarter of the quarter specified by the periodicity interval. Downloaded from https://www.everyspec.com
p. 365
APPENDIX G-6 NOTE
To determine if maintenance actions should be performed in port or at sea, refer to MIPs and MRCs for a brief description of the maintenance actions.
h. With the exception of related daily and weekly PMS requirements, ensure that all mandatory related maintenance is identified and scheduled. Mandatory maintenance will be identified with a leading pound sign "#" and bracketed within parentheses. Convenience related maintenance selected for accomplishment is identified by ( ) brackets.
i. All calendar situation requirements (24M-2R, A-2R, S- 1R, Q-3R, M-lR) must be accomplished at least once during the calendar periodicity specified. In addition, these requirements and situational requirements will be accomplished and documented each time the situation arises.
j. Bring forward any PMS requirement listed in the "Reschedule" column of the previous Quarterly PMS Schedule to the Quarterly PMS Schedule being prepared. Ensure emphasis is given to accomplishing rescheduled MRs.
k. The prepared Quarterly PMS Schedule shall be reviewed, signed, and dated by the Division Officer in the approval signature block. If the ship's operating schedule changes significantly, review the PMS requirements scheduled in the affected periods and reschedule as necessary. G-4 PREPARATION OF WEEKLY PMS SCHEDULE Using OPNAV 4790/15 or 4790/14A, type or legibly write in ink the following information from the Cycle PMS Schedule, the LOEP
and applicable MIPs.
a. Work center identification.
b. MIP number and component will match the Cycle PMS Schedule line for line.
c. Daily and weekly PMS requirements as indicated on the MIPs. List all weekly requirements in the Monday column and daily requirements in each day of the week column and twice in the "SAT. - SUN." column.
d. All situation requirements are listed in the "Next Four Weeks" column and scheduled, as the situation requires. Downloaded from https://www.everyspec.com
p. 366
NAVSEAINST 4790.8B
G-7 The 2W and 3W periodicities are also listed in the "Next Four Weeks" column.
e. The schedule will then be either laminated or covered with plastic so it can be cleared and updated each week. Downloaded from https://www.everyspec.com
p. 367
MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL
APPENDIX H
ASSIGNMENT OF RESPONSIBILITIES FOR THE PLANNED MAINTENANCE SYSTEM (PMS) OF THE SHIPS' MAINTENANCE AND MATERIAL MANAGEMENT (3-M) SYSTEM
Downloaded from https://www.everyspec.com
p. 368
APPENDIX H-i
REFERENCE INSTRUCTION NO. SUBJECT
(a) OPNAVINST 4700.7 Series, Maintenance Policy for Naval Ships (b) MIL-P-24534A (NAVY) PMS Document Development Specification
Downloaded from https://www.everyspec.com
p. 369
NAVSEAINST 4790.8B H-ii
Table of Contents
Paragraph…..Title ............................................Page
H-1 PLANNED MAINTENANCE SYSTEM (PMS) POLICY...................H-1 H-2 RELIABILITY-CENTERED MAINTENANCE (RCM) WAIVER POLICY......H-2 H-3 PMS RESPONSIBILITIES AND PROCEDURES.......................H-4 H-4 PMS FOR NEW CONSTRUCTION OR CONVERSION SHIPS..............H-6 H-5 PMS FOR OVERHAULED SHIPS..................................H-7 H-6 PMS FOR NEW SYSTEMS AND EQUIPMENT BEING PROCURED BY NAVSEA AND OTHER ACTIVITIES......................................H-8 H-7 PMS FOR EXISTING SYSTEMS AND EQUIPMENT IN THE FLEET.......H-8 H-8 SHIPALTS, ORDALTS, MACHALTS, FIELD CHANGES, AND ENGINEERING CHANGE PROPOSALS..........................................H-9 H-9 PMS FOR FOREIGN NAVIES (FORMER U. S. NAVY SHIPS)..........H-9 H-10 PMS FOR FOREIGN NAVIES (NEW CONSTRUCTION, MODERNIZATION, OVERHAUL, AND CONVERSION)................................H-10 H-11 PMS TECHNICAL FEEDBACK REPORTS..........................H-10 H-11.1 TFBR Procedures.......................................H-11 H-11.2 PMS Technical Feedback Response Instructions..........H-12 H-11.2.1 Critical Review Questions for PMS TFBR Review.......H-14 H-11.3 PMS Advance Change Notice Guidance....................H-15 H-12 PMS Workload Increase and Waiver Policy.................H-16
Downloaded from https://www.everyspec.com
p. 370
Downloaded from https://www.everyspec.com
p. 371
NAVSEAINST 4790.8B H-1
H-1 PLANNED MAINTENANCE SYSTEM (PMS) POLICY.
a. All maintenance requirements shall be developed using Reliability-Centered Maintenance (RCM) methodology as directed by reference (a). Preventive maintenance actions are required by reference (a) to be developed in accordance with reference (b) including preservation and maintenance requirements for equipment in an inactive status and calibration requirements relating to the Shipboard Gage Calibration Program. PMS requirements shall be developed concurrently with ship construction or conversion and new shipboard systems or equipment procurements including research and development items. In addition, PMS requirements shall be developed or revised to cover PMS changes which result when SHIPALTs, ORDALTs, MACHALTs, Field Changes, and other engineering changes are authorized. Development and distribution of other preventive maintenance procedures for ships’ use is prohibited.
b. The PMS Coordinating Activities (CA), who are COMNAVSEASYSCOM 04RM designated activities for the oversight of PMS, shall distribute all PMS documentation to ships. No other activities are authorized to distribute PMS documentation to ships.
c. PMS products resulting from other SYSCOM development activities shall be integrated with NAVSEA PMS products into a single complete shipboard PMS package which is distributed by the PMS CAs.
d. PMS documentation shall be reviewed to ensure technical accuracy, incorporation of configuration changes, technical manual changes, changes initiated by technical feedback reports, and improved maintenance procedures. All documentation will be validated prior to distribution to the fleet. Validation will consist of checking the accuracy of the documentation by performing the procedures aboard ship, where practical.
e. PMS procedures should not include the following actions or items:
(1) Watch routines.
(2) Corrective maintenance, except unscheduled maintenance.
Downloaded from https://www.everyspec.com
p. 372
APPENDIX H-2 (3) Major overhaul of equipment including tear down inspections or repair actions required to be done during an overhaul period. Scheduling of overhaul items may be included.
(4) Facilities or housekeeping maintenance items.
(5) Requirements that are documented by other means, such as underway check off lists, boiler light off procedures, rounds fired logs, and any Operational Sequencing System (OSS) procedures.
(6) Inventory checks such as repair locker check lists. H-2 RELIABILITY-CENTERED MAINTENANCE (RCM) WAIVER POLICY
a. Maintenance requirements for shipboard equipment and systems shall be developed using the Reliability-Centered Maintenance (RCM) methodology detailed in reference (b). Waivers from developing requirements in accordance with reference (b) may be requested in the following circumstances:
(1) A new maintenance requirement (e.g., MRC) is added to an existing MIP for a system already in PMS;
(2)The new system or equipment maintenance requirement results from a modification or upgrade to a system or equipment that is already included in the 3-M System with valid and current PMS requirements;
(3) The new maintenance requirement applies to a unique system or equipment that is being used on a temporary basis (i.e., being installed on a single hull vice on a ship class).
b. Waiver requests associated with the addition of a new maintenance requirement should include the following information:
(1) Requirement description;
(2) Failure mode (i.e., material condition after failure) the maintenance requirement is intended to prevent;
(3) Description of origination for this new maintenance requirement. This description could include results of INSURV Material Inspection, Navy Safety Center Surface Ship Downloaded from https://www.everyspec.com
p. 373
NAVSEAINST 4790.8B H-3 Safety Survey findings, details of a preventable equipment casualty or performance of routine maintenance. If a reference exists (e.g., TFBR DDG 51 Ser 0051-02, INSURV message 031530Z OCT 02, FTSCPAC Code 307 TAVR message 031530Z OCT 02, etc), identify the reference;
(4) Explanation of how the periodicity of the requirement was determined (e.g., OEM recommendation, MTBF data);
(5) Details of actual failures occurring in the Fleet which this maintenance requirement will prevent, and frequency of those failures;
(6) MIP and MRC information for any current and valid MRC or task that is similar to the proposed requirement;
(7) Additional technical information that might support adjudication of the waiver request.
In addition, a Backfit RCM analysis, similar to that conducted at SHIPMER, should be submitted for each proposed maintenance requirement for which a waiver is being requested. Each Backfit RCM analysis should include a detailed rationale and justification addressing how this proposed task satisfies the Applicability and Effectiveness criteria for the proposed maintenance requirement.
c. Equipment or system modification or upgrade-related waiver requests should include an explanation of the modification or upgrade being implemented and how it will impact the following specific equipment characteristics:
(1) Function (2) Equipment/system operating parameters (3) Operating environment (4) Duty cycle (5) Materials (6) Protective devices (7) Safety features
Equipment or system modification or upgrade-related waiver requests should also include a Backfit RCM analysis for each proposed maintenance requirement for which a waiver is being requested. Each Backfit RCM analysis should include a detailed rationale and justification addressing how this proposed task Downloaded from https://www.everyspec.com
p. 374
APPENDIX H-4 satisfies the Applicability and Effectiveness criteria for the equipment as modified or upgraded.
d. Temporary installation waiver requests should include the following equipment and/or system details:
(1) Ship or location of installation (2) Period of installation (3) Function (4) Equipment/system operating paramaters (5) Operating environment (6) Duty cycle (7) Materials (8) Protective devices (9) Safety features H-3 PMS RESPONSIBILITIES AND PROCEDURES
a. The Maintenance Engineering Policy and Knowledge Transfer Division (SEA 04RM) is responsible for COMNAVSEASYSCOM's efforts in managing the development, implementation and maintenance of the Ship's Maintenance and Material Management (3-M) System. Specifically, relative to the PMS responsibility, SEA 04RM will:
(1) Manage, coordinate, and monitor the PMS actions within the NAVSEASYSCOM to ensure compliance with the requirements specified in OPNAVINST 4790.4D and this instruction.
(2) Plan, develop, and implement PMS improvement programs.
(3) Manage the PMS efforts assigned to the PMS CAs.
b. The PMS CAs, when tasked and funded shall:
(1) Conduct technical reviews, standardize and validate MIPs and MRCs to ensure compliance with references (a) and (b).
(2) Deliver and install PMS packages to ships, craft, and other designated commands.
(3) Conduct maintenance liaison with fleet and type commands in implementing, supporting, and adapting COMNAVSEASYSCOM PMS programs to meet fleet requirements. Downloaded from https://www.everyspec.com
p. 375
NAVSEAINST 4790.8B H-5
(4) Provide input to Integrated Logistics Support Planning and ship manning document evaluations as requested by SEA 04RM.
(5) Initiate development for update of PMS for overhauled ships.
(6) Maintain the PMS database and the identity of library PMS documents.
(7) Maintain the PMS Management Information System (PMS MIS).
(8) Provide guidance to maintenance requirement developers to ensure compliance with references (a) and (b).
(9) Maintain records to support audits of response performance for feedback reports.
(10) Forward TFBRs to appropriate Design Activities and/or ISEAs by electronic means.
(11) Perform other PMS support functions as tasked by SEA 04RM.
c. Activities developing maintenance requirements shall ensure that all PMS requirements are included in all provisioning allowance and fitting out procedures and specifications.
d. NAVSEA technical codes and In-service Engineering Activities (ISEAs), when tasked and funded, shall perform the following for systems and equipment under their cognizance:
(1) Develop, review or revise, as applicable, maintenance requirements to ensure their technical accuracy for systems and equipment under their cognizance.
(2) Review and resolve PMS Technical Feedback Reports (TFBRs). Ensure that the procedures of paragraph H-11.2 are followed when responding to PMS TFBRs.
e. Other SYSCOMs with responsibility for shipboard equipment included in PMS, are requested to:
Downloaded from https://www.everyspec.com
p. 376
APPENDIX H-6 (1) Coordinate PMS requirements with SEA 04RM and provide completed PMS documentation to the PMS CAs for technical review, entry into the PMS data bank and issue to applicable ships in accordance with reference (a).
(2) Provide timely response and resolution to Technical Feedback Reports (TFBRs) for systems and equipment under their cognizance using the procedures of paragraph H-11.2. H-4 PMS FOR NEW CONSTRUCTION OR CONVERSION SHIPS
a. The Ship Program Manager (SPM) shall:
(1) Ensure development and review of maintenance requirements is completed in accordance with reference (b) using one or more of the following options:
(a) Require in shipbuilding contracts that PMS documentation be developed and provided by the shipbuilder.
(b) Task and fund system and equipment acquisition managers to develop PMS for systems and equipment under their responsibility.
(c) Task and fund the PMS CAs to develop PMS documentation for NAVSEA equipment and systems.
(2) Task and fund the PMS CAs through SEA 04RM to provide technical review, standardization, validation, printing, delivery and installation of a complete PMS package in the ship.
(3) Ensure that approved technical manuals, logistic support analysis, plans for maintenance, and drawings needed to develop PMS requirements are identified and provided to the developing activity 9 months prior to the scheduled PMS installation date to ensure availability of PMS documentation at installation date.
(4) If PMS CAs are not tasked to develop the PMS documentation, the SPM shall ensure that developing activities submit the PMS requirement development to the PMS CAs no later than 6 months prior to scheduled installation date for technical review, standardization, validation and printing to ensure availability of PMS documentation at installation date.
(5) Provide PMS CAs copies of Schedule A lists (government furnished equipment), preliminary equipment Downloaded from https://www.everyspec.com
p. 377
NAVSEAINST 4790.8B H-7 component indexes, and other configuration lists to ensure availability of PMS at scheduled installation date. Where feasible, the configuration data shall be provided in final form no later than 10 months prior to the PMS installation date.
b. NAVSEA 04RM and the PMS CAs shall be responsible, as tasked and funded by the SPM, for the following:
(1) Develop PMS requirements for NAVSEA cognizant systems and equipment.
(2) Perform technical reviews, validate, standardize, and print all PMS documentation developed.
(3) Verify, deliver, and install a complete PMS package in ships.
(4) Provide the SPM the development status of PMS for all ships' systems and equipment.
c. Acquisition managers tasked by the SPM to provide PMS requirements development documentation shall provide the following to the PMS CAs:
(1) A copy of contract or task requiring PMS development.
(2) The identification and nomenclature of ships' systems and equipment and related technical manual numbers.
(3) A list of designated ships on which systems and equipment will be installed.
(4)The date by which PMS documentation is required. H-5 PMS FOR OVERHAULED SHIPS
a. SPMs shall:
(1) Ensure development and review of PMS requirement development documentation is completed in accordance with one or more of the following options:
(a) Require in overhaul contracts that PMS documentation be developed and provided by the shipbuilder.
Downloaded from https://www.everyspec.com
p. 378
APPENDIX H-8 (b) Task and fund system and equipment acquisition managers to develop PMS for systems and equipment under their responsibility.
(c) Task and fund PMS CAs to develop PMS documentation for NAVSEA systems and equipment.
b. The PMS CAs shall deliver updated PMS documentation to the ships. H-6 PMS FOR NEW SYSTEMS AND EQUIPMENT BEING PROCURED BY NAVSEA AND OTHER ACTIVITIES
a. Acquisition managers responsible for systems and equipment requiring scheduled preventive maintenance shall task and fund for development of initial PMS requirements in accordance with reference (b) concurrent with system and equipment delivery. Criteria for waiving requirements of reference (b) for new PMS documentation associated with development, modification or addition to existing PMS is addressed in paragraph H-2. This requirement includes equipment purchased by TYCOMs, ship purchases, and other Commercial Off- The-Shelf (COTS) equipment.
b. Acquisition managers will fund PMS CAs for initial printing and distribution of PMS documentation for new systems. The only activity authorized to distribute PMS documentation to ships are the PMS CAs. H-7 PMS FOR EXISTING SYSTEMS AND EQUIPMENT IN THE FLEET
SEA 04RM will task and fund the PMS CAs to:
a. Maintain, standardize, print, and distribute the PMS documentation.
b. Provide processing for non-Technical feedback reports and for researching and resolving TFBRs.
c. Maintain the PMS Management Information System (PMS MIS).
Downloaded from https://www.everyspec.com
p. 379
NAVSEAINST 4790.8B H-9 H-8 SHIPALTS, ORDALTS, MACHALTS, FIELD CHANGES, AND ENGINEERING CHANGE PROPOSALS
The alteration or change sponsor (SPM, TYCOM, etc.) shall task and fund Life Cycle Managers (LCMs) for systems and equipment to develop new maintenance requirements in accordance with reference (b). If an RCM waiver is approved, they should task and fund revision to PMS documentation to reflect changes in systems and equipment resulting from alterations or changes. The PMS requirements documentation shall be provided to the PMS CAs at least 4 months prior to required PMS documentation delivery date. H-9 PMS FOR FOREIGN NAVIES (FORMER U. S. NAVY SHIPS)
PMS documentation requests from foreign navies for former U. S. Navy Ships shall be processed as follows:
a. Requests for PMS coverage for foreign navies on former U. S. Navy Ships shall be directed to the NAVSEA Office of International Programs (SEA 63).
b. Upon receipt of a request from a foreign navy for PMS coverage for a former U. S. Navy ship, SEA 63 will request from the appropriate PMS CA the cost and availability of providing a one-time updated PMS package and whether a List of Effective Pages (LOEP) is available for the ship. If the ship's LOEP is not available, then the PMS CA should advise SEA 63 whether another ship's LOEP can be used as a verification document.
c. After receipt of a signed acceptance of the offer, SEA 63 will issue a funding document to the appropriate PMS CA. The PMS CA will provide SEA 63 with a LOEP and instruction for its use within 60 days.
d. SEA 63 is to complete and return the updated verified LOEP package to the appropriate PMS CA.
e. The appropriate PMS CA will deliver a one-time updated PMS package based upon the verified LOEPs within three months after receipt. This updated package will include only data available in the data bank. No new PMS development will be undertaken for equipment not having PMS coverage. Continuing PMS support will be provided if funded by SEA 63.
Downloaded from https://www.everyspec.com
p. 380
APPENDIX H-10 H-10 PMS FOR FOREIGN NAVIES (NEW CONSTRUCTION, MODERNIZATION, OVERHAUL, AND CONVERSION)
The USN Program Manager (PMs or SPMs) responsible for the specific foreign navy effort will provide funding to initiate new, or modify existing PMS documentation in accordance with the procedures described herein for USN ships. The Program Manager shall be the sole authority for PMS requirements on cognizant foreign ships. H-11 PMS TECHNICAL FEEDBACK REPORTS
TFBR are to be used for reporting technical deficiencies or errors in PMS documents. Technical PMS discrepancies that could have a detrimental effect on personal safety, safety of ship, or could result in significant equipment damage, are classified as "Urgent." All other TFBRs are classified as “Routine.”
a. The central control points for processing TFBRs are the PMS CAs. Depending on the type and level of technical authority necessary to answer the TFBR, PMS CAs will either respond to the originator with a resolution, or forward the TFBR to the appropriate technical authority for their action. The PMS CAs will enter all TFBR information in the PMS MIS for tracking and control purposes.
b. Naval Sea Systems Command Activities. Design Activities, ISEAs, or other activities under the direction of the Naval Sea Systems Command holding technical authority for systems and equipment shall take appropriate action on all TFBRs under their cognizance, forwarding responses to the PMS CAs. Responses will be electronically transmitted to the appropriate PMS CA. The PMS CAs will record the TFBR result in the PMS MIS and provide the final response to the originator.
c. Other Systems Command Activities. Design Activities, In-Service Engineering Agents (ISEAs), or other activities under the direction of other Systems Commands (SYSCOMs) holding technical authority for systems and equipment are requested to take appropriate action on all TFBRs under their cognizance forwarding responses to the PMS CAs. Responses will be electronically transmitted to the appropriate PMS CA. The PMS CAs will record TFBR results in the PMS MIS and provide the final response to the originator.
Downloaded from https://www.everyspec.com
p. 381
NAVSEAINST 4790.8B H-11 H-11.1 TFBR Procedures
a. Urgent TFBRs.
(1) Urgent TFBRs are those feedbacks reporting technical discrepancies that can result in personnel injury, risk to the safety of the ship or significant equipment damage.
(2) PMS CAs shall provide a message response to all Urgent TFBRs informing the originator of specific actions and required changes that will result from TFBR evaluation or forward the TFBR to the appropriate Design Activity or ISEA within 1 working day of receipt. This message response shall be addressed to the originator and distributed to TYCOMs. TYCOMs will forward this message to all commands that could be affected by PMS change. The Urgent TFBR response message may recommend pen and ink changes to the affected PMS requirement.
(3) If the PMS CAs forward the TFBR to a Design Activity or ISEA for resolution, than the Design Activity or ISEA shall provide a message response to all Urgent TFBRs informing the originator of the specific actions and required changes that will result from the TFBR evaluation within 1 working day of receipt. This message response shall be addressed to the originator and distributed to TYCOMs and PMS CAs. TYCOMs will forward this message to all commands that could be affected by the PMS change. The Urgent TFBR response message may recommend pen and ink changes to the affected PMS requirement.
(4) PMS CAs shall distribute revised PMS documentation to affected users within 30 calendar days of receipt via special issue or Advance Change Notice (ACN).
b. Routine TFBRs.
PMS CAs shall perform technical review, research and provide a response to routine TFBRs where resolution does not require technical authority action. TFBRs that PMS CAs cannot resolve will be sent to the cognizant Design Activity or ISEA. The cognizant Design Activity or ISEA will provide the response to the appropriate PMS CA. The response shall describe the action taken. The PMS CAs will provide the response to the originator by electronic means. Distribution of the revised MRC to the originator and other affected users will be accomplished via the next Force Revision (FR). COMNAVSEASYSCOM has established a goal of providing answers to all TFBRS in one day. While it is Downloaded from https://www.everyspec.com
p. 382
APPENDIX H-12 realized that some TFBRs will require more extensive research, the majority of TFBRs received can and should be answered in one day.
c. Special Issues.
If revised PMS documentation is determined to have safety considerations, or the Design Activity or ISEA funds the PMS Program Oversight Manager, then the PMS CAs will prepare and distribute a PMS Special Issue to all holders of the affected PMS documentation.
d. Changes to RCM-based MRCs require the Design Activity or ISEA to:
(1) Modify the original RCM Corporate History data to reflect the justification for the MRC change.
(2) Provide technical justification for changes to the PMS CA as part of the response to the Feedback Report. The Feedback Report response with the change and justification/rationale will then become part of the RCM Corporate History.
H-11.2 PMS Technical Feedback Response Instructions
All PMS Technical Feedback Reports shall be answered using the guidelines in paragraph H-11.2.1.
a. For concurrence response:
(1) If PMS documentation must be changed, the revision information shall be provided to the appropriate PMS CA by electronic means. NAVSEA 04RM approved software may be used to make revisions to PMS documentation, but the use of this software should not delay the response to the appropriate PMS CA.
(2) If no revision to PMS documentation is required provide pertinent comments in the response to the appropriate PMS CA.
b. For non-concurrence responses. When not concurring with the feedback report, the rational for non-concurrence must be given.
Downloaded from https://www.everyspec.com
p. 383
NAVSEAINST 4790.8B H-13 c. The response shall be electronically provided to the appropriate PMS CA with any applicable corporate history changes and revised documentation. Downloaded from https://www.everyspec.com
p. 384
APPENDIX H-14
H-11.2.1 Critical Review Questions for PMS TFBR Review
The following questions shall be considered in the response to all TFBRs.
a. What is the Sailor's question or problem?
b. Is the MRC necessary?
c. What failure mode(s) does the MRC prevent or detect?
d. Is the MRC clear and easy to follow?
e. Is the MRC safe for the Sailor to accomplish?
Check to see that the Sailor is protected from falls, chemicals, asbestos, sewage, high voltage, rotating machinery, pressurized fluids or gases, poisonous gases, and that two-man protection is specified when necessary. If required, is the use of protective clothing, safety glasses or hearing protection specified?
f. Is the equipment being maintained within the boundaries of the applicable guidelines for selection and use of lubricants and hydraulic fluids for use in Shipboard Systems?
g. Have you specified the correct number of Sailors, skill level, and man-hours required to accomplish this task?
h. Is the periodicity such that it represents the absolute minimum necessary to achieve the inherent level of reliability?
i. What would be the effect on the equipment if the MRC was accomplished less frequently? Not accomplished at all?
j. For test maintenance actions, what is proven by this test?
k. Does this action lead towards standardization of MRCs for similar equipment?
l. Did you answer the Sailor's question?
Downloaded from https://www.everyspec.com
p. 385
NAVSEAINST 4790.8B H-15 H-11.3 PMS Advance Change Notice Guidance
A PMS Advance Change Notice (ACN) is authorization for changing a MRC or addition of a new MRC. An ACN is also a record of change to a MRC or addition of a new MRC. An ACN is issued in the format of a Maintenance Requirement Card suitable for attachment to the MRC to which it applies. An ACN can be issued to advise ships to annotate MIPs.
a. PMS docume ntation changes typically promulgated by ACNs include:
(1) Increase or decrease periodicity to change the interval between maintenance actions.
(2) Delete or modify an existing maintenance requirement.
(3) Addition or modification of an MRC procedure note to clarify the context or description of a procedure step.
(4) Change a procedure step to correct maintenance technical data, e.g., frequency, pressure, voltages, current, decibels, resistance values, clearance, test data, etc.
(5) Addition, deletion or modification of existing procedure steps which significantly improve the technical accuracy of the MRC.
(6) Addition or change of tools, parts, materials and/or test equipment that significantly improves PMS performance.
b. Distribution and Control of ACNs
(1) A PMS ACN shall refer to a specific MIP and MRC. A new MRC page shall be provided for each MRC page affected by the ACN.
(2) Each PMS ACN shall be serialized. The serial number will consist of the originating activity code, log number (if appropriate), MIP number, MRC control number, and date.
(3) The PMS CAs shall maintain accountability of all outstanding ACNs by Maintenance Index Page (MIP)/Maintenance Requirement Card (MRC). When revising and distributing affected MIP, the revision shall include annotation of applicable ACNs. Downloaded from https://www.everyspec.com
p. 386
APPENDIX H-16 H-12 PMS Workload Increase and Waiver Policy
a. Any revision to PMS requirements resulting in an increase in workload, or denial of a request to change periodicity that would reduce workload, requires the Design Activity or ISEA to obtain SEA 04RM approval. Upon concurrence, SEA 04RM will forward the response to the cognizant PMS CA. PMS Workload Increase Waivers should be requested in the following circumstances:
(1) A change is made that increases the performance frequency of a current and valid MRC (e.g., changing a Quarterly maintenance action to a Monthly maintenance action). A valid MRC is one generated using reference (b) or vetted by Backfit- RCM methodology;
(2) The Procedures on a current and valid MRC is either modified or task steps are added that results in additional workload;
(3) A current and valid MRC is added to a MIP that does not currently contain that MRC.
b. PMS Workload Increase Waivers are not required when:
(1) New equipment, with current and valid PMS, is installed in a ship when that equipment and its corresponding maintenance are identical to that installed on other ships or stations;
(2) The MRC workload information is updated to more accurately reflect actual time required to perform the MRC.
c. PMS workload waiver requests should include an explanation of the change being implemented and the following information:
(1) MRC or task description;
(2) Failure mode (material condition after failure) the MRC or task is intended to prevent;
(3) Description of origination for this new maintenance requirement. This description could include results of INSURV Material Inspection, Navy Safety Center Surface Ship Safety Survey findings, details of a preventable equipment casualty or performance of routine maintenance. If reference Downloaded from https://www.everyspec.com
p. 387
NAVSEAINST 4790.8B H-17 exists, (e.g., TFBR DDG 51 Ser 0051-02, INSURV message 031530Z OCT 02, FTSCPAC Code 307 TAVR message 031530Z OCT 02, ISEA PMS review, etc) identify the reference;
(4) How the new requirement (i.e., revised periodicity, new procedural step, new maintenance requirement) was determined;
(5) Details of actual failures occurring in the Fleet which this revision to the current maintenance requirement will prevent, and frequency of those failures;
(6) Provide MIP and MRC information for any current and valid MRC or task similar to the proposed, modified, MRC or task;
(7) Any additional technical information that might support adjudication of the waiver request.
In addition, for waiver requests associated with increases in maintenance periodicity or changes to existing MRC procedures (paragraph a.(1) and a.(2) above), a Backfit RCM analysis, similar to that conducted at SHIPMER, should be submitted for each proposed maintenance requirement. Each Backfit RCM analysis should include a detailed rationale and justification addressing how this proposed task satisfies the Applicability and Effectiveness criteria for the proposed maintenance requirement.
Downloaded from https://www.everyspec.com
p. 388
MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL
APPENDIX I
ALTERATION MANAGEMENT
Downloaded from https://www.everyspec.com
p. 389
APPENDIX I-i APPENDIX I
REFERENCES
REFERENCE INSTRUCTION NO. SUBJECT
(a) OPNAVINST 4720.2 SERIES FLEET MODERNIZATION PROGRAM (FMP) POLICY
(b) SL720-AA-MAN-010/020 FLEET MODERNIZATION PROGRAM MANAGEMENT AND OPERRATIONS MANUAL
(c) NAVSEA TECH SPEC SHIP CONFIGURATION AND 9090-700 Series LOGISTICS SUPPORT INFORMATION SYSTEM (SCLSIS)
(d) NAVSEAINST 4720.15 Series MACHINERY ALTERATIONS (MACHALTS) ON HM&E EQUIPMENT AND SYSTEMS
Downloaded from https://www.everyspec.com
p. 390
NAVSEAINST 4790.8B
I-ii
ALTERATION MANAGEMENT
TABLE OF CONTENTS
Paragraph Title Page
I-1 PURPOSE...................................................I-1 I-2 DEFINITIONS...............................................I-2 I-3 ORGANIZATIONAL RESPONSIBILITY.............................I-8 I-3.1 Naval Sea Systems Command...............................I-8 I-3.2 TYCOMs..................................................I-9 I-3.3 Fleet Units............................................I-11 I-4 ALTERATION PROCESS......................................I-112 I-4.1 Alteration Management 3-M Reporting Requirements.......I-13 I-4.2 Ship's Force Requests for Configuration Changes........I-13 I-4.3 Departure From Specification...........................I-13 I-4.4 Certification of Shipyard Installed Alterations........I-14 I-4.5 Automated Data Process Between 3-M and SCLSIS..........I-14
Downloaded from https://www.everyspec.com
p. 391
APPENDIX I-iii TABLE OF CONTENTS
Paragraph Title Page
Figure I-1 Sample Certification of Alteration Installation.. I-15 Figure I-2 1st Endorsement to Alteration Certification Letter .......................................... I-16
Downloaded from https://www.everyspec.com
p. 392
NAVSEAINST 4790.8B
I-1
ALTERATION MANAGEMENT
1-1 PURPOSE
This Appendix describes how planned alterations are incorporated into the 3-M system. It is intended as a guide for understanding the process and assist in annotating the required Maintenance Data System (MDS) documents resulting from an alteration to a vessel, its systems, and/or equipment as described in other sections in this manual.
The Fleet Modernization Program (FMP) provides the policy and procedures used to manage alterations for individual hulls based on scheduled ship availabilities. The FMP is supported by the Navy Data Environment – Navy Modernization (NDE-NM) database. References (a) and (b) are the FMP policy and procedure documents. Reference (b) details the process along with participants responsibilities in supporting the automated system (NDE-NM).
The Type Commander (TYCOM) directs the accomplishment of D, F and AER (Alteration Equivalent to Repair) alterations after the NAVSEASYSCOM Ship Program Manager (SPM) has approved the alteration, assigns priorities, monitors and controls the alteration progress while Fleet Units must provide accomplishment feedback through the OMMS-NG/SNAP process. The CNO and NAVSEASYSCOM perform these functions for K and KP alterations. It is the responsibility of the SPM, TYCOM and/or Accomplishing Activity to maintain the installation schedule and completions in the NDE-NM database.
1-2 DEFINITIONS
a. Applicability - A technical review and examination was conducted and the alteration was made applicable to a specific ship or ships. This does not mean that the alteration will be programmed on the ship. The Ship Alteration Record (SAR), AER and Equipment Alteration shall provide applicability information that shall also be reflected in NDE-NM.
b. Alteration - Any change in the hull, machinery, equipment, or fittings which involves a change in design, materials, number, location, or relationship of an assembly’s component parts whether the change is separate from, incidental to, or in conjunction with repairs. Downloaded from https://www.everyspec.com
p. 393
APPENDIX I-2
c. Alteration-Equivalent-To-Repair (AER) – An Alteration- Equivalent-To-Repair (formerly known as a Letter AER for Surface Ships, an Alteration and Improvement (A&I) for Submarines, and an Alteration Request for Aircraft Carriers) is a permanent alteration formally approved by the SPM, typically via letter, which has one or more of the attributes described in TYCOM Alterations (see paragraph I-2 p.) and all of the following criteria:
(1) It does not impact Battle Force Interoperability (BFI).
(2) It does not impact the ship’s stability records (weight and moment).
(3) It does not impact or alter the 3-dimensional footprint of the equipment it is replacing.
(4) It does not impact shipboard distributive systems (i.e., water, ventilation, electrical, power), their SSR or interfacing equipment or systems; compartmental arrangement records; or Damage Control records.
(5) It does not impact Manpower and Personnel.
All AERs require SPM technical approval. Non-military improvements may be approved and authorized for accomplishment by the cognizant SPM.
The following procedures will be followed if the SPM’s internal review determines that the proposed AER should be accomplished as a SHIPALT (Title “F”, “D”, “KP”, or “K”) or is already under development as a SHIPALT:
(1) An AER can be a prerequisite to a SHIPALT such as Title “F” and “D” SHIPALTs. In this case, information relating to the development of the SHIPALT will be included in the body of the AER recommendation letter. Additionally, it should be stated that ILS products affected will be covered during the SHIPALT development and execution.
(2) AERs can be accomplished in place of SHIPALTs where an emergent requirement of limited applicability dictates. In this case, the body of the recommendation letter shall state that the Planning Yard (PY) shall prepare the AER installation procedures.
(3) If a proposed AER is required until the accomplishment of a SHIPALT, the AER recommendation will Downloaded from https://www.everyspec.com
p. 394
NAVSEAINST 4790.8B
I-3 identify the SHIPALT and its estimated completion date. All detailed procedures, material requirements and ILS requirements will be excluded from the letter.
d. Authorization – Empowers a command to direct a specified alteration to be accomplished.
e. Approval - An action of the cognizant SPM signifying the accomplishment of an alteration is technically feasible. Evidence of "Approval" is the signature of the SPM on the Ship Alteration Record, AER or TEMPALT.
f. Equipment Alteration – Any alteration, other than a SHIPALT, in the configuration of an equipment or system (including embedded equipment, computer programs and expendable ordnance) after establishment of the product baseline. An Equipment Alteration involves a change in design, type of material, quantity, installed location, logistics, supportability, or the relationship of the component parts of an assembly within the ship. Equipment Alterations include the addition, deletion, rework, or replacement of parts, assemblies or equipment; or changes in assembly procedures. Alterations to associated computer programs include the incorporation of different computer program versions and approved modification or corrections to both operational test and maintenance programs. Equipment Alterations are initiated by approved Class I Engineering Change Proposals (ECPs). Equipment Alterations apply equally to changes installed in delivered systems and equipment, and changes installed in systems and equipment in production to identify differences from an established product baseline. Equipment Alterations may be initiated to correct a design defect, to change equipment operational capability, to eliminate safety hazards, to update obsolete components, or for any combination of these reasons. There are four types of Equipment Alteration (Engineering Change, Field Change, Machinery Alteration and Ordnance Alteration) that are defined below.
(1) Engineering Change (EC) – A modification, usually to Under-Sea Warfare (USW) equipment or systems, or other equipment groups as designated by the cognizant Systems Command, Program Manager (PM),Participating Acquisition Resource Manager (PARM), and Configuration Control Boards (CCBs).
(2) Field Change (FC) – A mechanical, electronic or electrical change, modification or alteration made to electronic equipment after delivery to the government or installation on board ship, including software changes, which does not impact interfaces to other equipment within the ship, change the footprint, form or fit, change power, weight, or air Downloaded from https://www.everyspec.com
p. 395
APPENDIX I-4 conditioning requirements. If power, weight or air conditioning requirements are modified, the modification must be discussed with the appropriate SPM, who will decide whether to proceed with the modification as a Field Change or SHIPALT. Field Changes are initiated and approved by the cognizant Headquarters Systems Command and are implemented by Field Change Bulletin (FCB). Alteration Installation Teams (AITs) or Ship’s Force can accomplish FCs. For these specific types of alterations, the cognizant SPM shall be notified of the approved changes affecting their respective platforms, shall be periodically advised of installation status and shall be notified of any logistics upgrades, which have been completed as a result of the alteration.
(3) Machinery Alteration (MACHALT) - A planned change, modification or alteration of any Hull, Mechanical or Electrical (HM&E) equipment in service (shipboard or shore activities) when it has been determined by the MACHALT Configuration Control Board that the alteration or modification meets all of the following conditions:
(a) Can be accomplished without changing an interface external to the equipment or system.
(b) Are modifications made within the equipment boundary or is a direct replacement of the original equipment system.
(c) Can be accomplished without the ship being in an industrial activity.
(d) Can be accomplished individually, not conjunctively with a SHIPALT or other MACHALT. If power, weight or air conditioning requirements are modified, the modification must be discussed with the appropriate SPM, who will decide whether to proceed with the modification as a MACHALT or SHIPALT.
(4) Ordnance Alterations (ORDALTs) - Changes made to ordnance equipment or their computer programs by the addition, deletion, rework, or replacement of parts, assemblies or equipment, or by a change in assembly procedures.
g. Fleet Modernization Program (FMP) – The Fleet Modernization Program (FMP) provides a structure for the orderly identification, approval, design, planning, programming, budgeting, installation, life cycle support and configuration control of military, technical, and survivability improvements to all ships of the active and reserve fleets. An “improvement” Downloaded from https://www.everyspec.com
p. 396
NAVSEAINST 4790.8B
I-5 is an enhancement to a ship that increases its capability or reliability to perform its assigned mission.
h. Forces Afloat Accomplishment - The SHIPALT shall be accomplished by ship's force and/or IMA for shipboard installation.
i. Industrial Activity - Any activity that has the capability to perform all aspects of work on ships. These activities generally include Naval Bases, Naval Ship Repair Facilities (NSFRs), Intermediate Maintenance Facilities, Trident Refit Facilities (TRFs), public (Naval) shipyards and private shipyards that hold Agreements for Boat Repair (ABR) or Master Ship Repair (MSR) Agreements in accordance with the NAVSEA Supervisor of Shipbuilding, Conversion and Repair (SUPSHIP) USN Operations Manual.
j. Levels of Maintenance
(1) Organizational (Shipboard) Level Maintenance - maintenance that is the responsibility of ship’s force for accomplishment.
(2) Intermediate Level Maintenance – ship’s maintenance that is normally performed by Navy personnel on board tenders, repair ships, Shore Intermediate Maintenance Activities (SIMAs), aircraft carriers, and fleet support bases.
(3) Depot (Shipyard) Level Maintenance – ship’s maintenance that is performed by industrial activities. Depot level maintenance requires major overhaul or a complete rebuilding of parts, assemblies, subassemblies, and end items, including the manufacturing of parts, modifications, testing, and reclamation.
k. Package SHIPALT - (P) is assigned to those SHIPALTs being prepared under the Package SHIPALT Program. SHIPALTs under this program must meet the following basic criteria:
(1) The material, plans, installation instructions, spare parts, technical data, etc., are pre-packaged by an industrial facility for specific ships suitable for installation by forces afloat or AIT. As part of the package, only nominal technical assistance will be provided at the time of installation.
(2) All funds to support preparation of Package SHIPALTs, including technical assistance (except for Special Program Material), are FMP funded. Downloaded from https://www.everyspec.com
p. 397
APPENDIX I-6
l. Ship Alteration (SHIPALT) – An approved permanent change to the configuration of a ship that is documented as a SHIPALT Record (SAR) and implemented through the FMP Process. SHIPALTs are classified by title/type and comprise any change in hull, machinery, equipment, or fittings that involves changes in design, material, quantity, location, or relationship of the component parts of an assembly. Note: Other alterations which modify shipboard systems such as ordnance alterations, electronic field changes, air alterations, and special project alterations are not considered SHIPALTs, but may require conjunctive SHIPALTs where systems interface changes are involved.
m. SHIPALT Title – The title assigned to a SHIPALT identifying the approving authority and responsibility for funding. SHIPALT titles are:
(1) Title “D” – A permanent alteration that does not affect the military characteristics of a ship. It is formally approved by the SPM in the form of a Justification/Cost Form (JCF) and a SHIPALT Record (SAR). It may require Centrally Provided Material (CPM) but does not require Headquarters CPM (HCPM). A Title “D” SHIPALT may specify whether it should be accomplished only by a depot level maintenance facility. They generally include more efficient, cost effective designs that improve ship maintainability, and meets one or more of the TYCOM Alteration attributes described in paragraph I-2 p. TYCOM Alterations.
(2) Title “F” – A permanent alteration that is formally approved by the SPM in the form of a JCF and a SAR. It does not require Centrally Provided Material (CPM) or Headquarters CPM and is within the ship’s force capabilities for accomplishment, however, it may be accomplished by a Fleet Maintenance Activity (FMA). It must also meet one or more of the TYCOM Alteration attributes described in I-2 p. TYCOM Alterations.
(3) Title “K” – A permanent alteration to provide a military characteristic, upgrade existing systems or provide additional capability not previously held by a ship, which affects configuration controlled areas or systems of a ship or which otherwise requires the installation of Headquarters Centrally Provided Material (HCPM). These SHIPALTs are approved for development and authorized for accomplishment by the CNO (military improvements) or the Hardware Systems Command (HSC) (non-military improvements). The technical approval for Title “K” SHIPALTs is provided by COMNAVSEASYSCOM. Downloaded from https://www.everyspec.com
p. 398
NAVSEAINST 4790.8B
I-7
(4) Title “K-P” – A Title “K” SHIPALT which is within forces afloat or Alterations Installation Team (AIT) capability for accomplishment, and for which required special program and centrally provided materials are provided as a package by the cognizant Hardware Systems Command (HSC).
n. Temporary Alteration (TEMPALT) – Any alteration that provides given capabilities on a temporary basis (not to exceed one year or one operational deployment in duration) in support of Research, Development, Test and Evaluation (RDT&E) or exercise or mission requirements. TEMPALTs are reviewed and technically approved by the cognizant Ship Program Manager (SPM) and authorized for accomplishment by the cognizant TYCOM. The SPM review considers safety, technical adequacy, impact on ship stability, operational characteristics including warfare capability, damage control, ship structure, ship services, ships interfaces, and habitability. Alterations intended to be installed for a period in excess of one year or one operational deployment shall be considered a permanent change to a ship’s configuration and shall be accomplished as a SHIPALT accordingly. After completion of testing requirements, mission or exercise support requirements or one year, whichever comes first, TEMPALTs must be removed and the ship restored to its previous configuration. The activity sponsoring the accomplishment of the TEMPALT shall be responsible for funding the removal of the TEMPALT and the restoration of the ship.
p. TYCOM Alterations – TYCOM Alterations are approved by the SPM for accomplishment as a Title “D” or “F” SHIPALT or AER depending upon the scope and effects of the change. TYCOM Alterations are programmed for installation by the TYCOM, as well as funded for accomplishment by the TYCOM or other organization as agreed upon. TYCOM Alterations are maintenance alterations normally accomplished to improve reliability or maintainability. A TYCOM Alteration is a technical alteration that has one or more of the following attributes:
(1) The use of different materials that have been approved for similar use and such materials are available from standard stock.
(2) The replacement of obsolete, worn-out or damaged parts, assemblies or components requiring renewal by those of later and more efficient design which has been previously approved by the SPM and such replacement does not cause a change to the systems or equipment normally associated with the military characteristics of the ship.
Downloaded from https://www.everyspec.com
p. 399
APPENDIX I-8 (3) The strengthening of parts that require repair or replacement in order to improve reliability of the parts and of the unit, provided no other change in design is involved.
(4) Minor modifications involving no significant changes in design or functioning of equipment but considered essential to prevent recurrence of unsatisfactory conditions.
(5) The replacement of parts, assemblies or equipment with like items of later or more efficient design where it can be demonstrated that the cost of the installation and maintenance of the new parts, assemblies or components is less than the cost of maintaining the installed parts, assemblies or components, and such replacement does not cause a change to the existing system design or affect any interfacing system design and does not effect a change to the systems of equipment normally associated with the military or technical characteristics of the ship.
(6) The proposed alteration is an inspection or documentation change requiring no equipment modification, but requires a vehicle to monitor accomplishment.
1-3 ORGANIZATIONAL RESPONSIBILITY
Responsibility for alteration management is required at various levels of command. Command responsibilities include:
1-3.1 Naval Sea Systems Command
As the managing agent for the FMP program, COMNAVSEASYSCOM provides a major input into the NDE-NM database from MDS reports. The NDE-NM records and tracks authorized configuration change requirements and status. Specific alteration management responsibilities for the managing agent are:
a. Maintain and update the NDE-NM database, requesting reports from fleet commands per reference (b) when the 3-M database cannot supply the required information.
b. Ensure NDE-NM transactions and supporting information is available to applicable TYCOMs. Data should include:
(1) MDS OPNAV Form 4790/2K information concerning all SHIPALTs, including ORDALTs. This excludes NAVSEA-08 alterations.
Downloaded from https://www.everyspec.com
p. 400
NAVSEAINST 4790.8B
I-9 (2) Programmed status for all SHIPALTs and AERs.
(3) Plans, material, and package availability status for all SHIPALTs and AERs.
(4) Priorities for planned Amalgamated Military/Technical Improvement Plans (AMTs).
(5) Estimated man-days to complete.
(6) Estimated material costs (latest).
(7) Estimated total cost to complete.
(8) Fiscal year planned.
(9) Returned total cost this alteration.
(10) Plans availability code.
1-3.2 TYCOMs
The TYCOMs are responsible for alteration management within their force. Responsibilities include:
a. Assign priorities to alterations:
(1) For Title "K" alterations, review the NDE-NM and recommend changes of priorities to CNO.
(2) For Title "D" and "F" alterations and for TYCOM Alterations, assign the priorities of precedence for installation.
b. For the TYCOM Mandatory Priority List, identify for CNO the planned installation year and assigned priority for Title "F" SHIPALTs. This information is subsequently displayed in the NDE-NM database.
c. Check the NDE-NM Alteration Management data by verifying that:
(1) The information recorded is supported by corresponding SARs.
(2) Applicabilities are assigned and correct.
(3) Programmed status is assigned. Downloaded from https://www.everyspec.com
p. 401
APPENDIX I-10
d. Document the following information (if desired) for local processing and control:
(1) Material, plans, and Package SHIPALT availability.
(2) Alteration cost estimates.
(3) Priorities for accomplishment.
e. For TYCOM Alterations maintain the following information in NDE-NM:
(1) Type Availability (T/A), and TYCOM Screening Code.
(2) Priority, if desired.
(3) Designated planning activity, if desired.
(4) Designation to add to applicable ship CSMP file.
(5) Planned installation year, if desired.
f. Monitor alteration management reports to ensure accuracy, including monitoring of the transaction and error reports.
g. Provide direction to the supporting data processing activity concerning the production and distribution of alteration management reports.
h. Take appropriate action when transferring alteration management files and reports to another command. This requires that both TYCOMs maintain the same alteration management master records.
i. Issue instructions to:
(1) Provide for advanced planning for alterations.
(2) Assign planning activities.
(3) Report return cost of alterations.
(4) Assign parent IMAs, if applicable.
(5) Transfer files from one command to another.
Downloaded from https://www.everyspec.com
p. 402
NAVSEAINST 4790.8B
I-11 (6) Provide for the routine correction of alteration files.
j. Provide information on problems, and solutions in alteration completions reported by an IMA to all other concerned activities.
1-3.3 Fleet Units
The Commanding Officer is responsible for the expeditious completion of all alterations authorized for the ship. Ship alteration management responsibilities are:
a. Audit for accuracy alteration management reports and MDS Transaction and Error Identification Reports containing alteration information. Report required corrections to the TYCOM.
b. Ensure that the applicable Ship Alteration Record or similar document is provided to the ship for all alterations programmed in the execution year.
c. Submit OPNAV Form 4790/CK, or electronic version following installation of alterations. See Section I-Chapter 3 of this manual for detailed instructions and Appendix B for details of specific blocks.
d. When reporting alteration status changes:
(1) Ensure the remarks section (Block 12) of the configuration change record (OPNAV Form 4790/CK) expressly states the work that remains to be completed on partially completed alterations.
(2) Ensure that all of the configuration data required by Section I-Chapter 3 is reported on the configuration change record (OPNAV Form 4790/CK).
(3) Ensure that OPNAV Form 4790/2K for partial alterations are completed.
Downloaded from https://www.everyspec.com
p. 403
APPENDIX I-12 1-4 ALTERATION PROCESS
The alteration process begins when the Systems Commands (SYSCOMs) forward alteration documents and data, which interface with MDS, to the TYCOMs. These documents authorize the accomplishment of alteration requirements and configuration changes to components or systems installed on ships or installed at shore activities. The TYCOMs review and modify the data as necessary before forwarding the alteration data on to the appropriate units, or designated activity that will process the data into the Ships' 3-M System. Specific procedures for processing alteration data from the NDE-NM into 3-M are contained in reference (b) and TYCOM instructions with a summary provided in the following sections.
All alterations scheduled for accomplishment must be in the ship's CSMP. This is the entry point for the alteration data into the 3-M System. Some of these alterations require extensive logistic support while others may be limited to, for example, a wiring change in a circuit. For each type/category of alteration a unique alteration prefix has been assigned as an identifier. Authorized alteration categories and associated prefixes are:
Prefix Alteration Category
SA Ship Alteration OA Ordnance Alteration FC Field Change AR Alteration Request BA Boat Alteration MA Machinery Alteration SI SYSCOM Command Instruction EC Engineering Change HI Habitability TY TYCOM Direction TD Technical Directive SP Strategic Systems Project Office Alteration SC Service Change TR Trident Alteration EP Engineering Change Proposal MO CRYPTO Equipment Modification
In addition to configuration changes made during corrective maintenance and reported as required by Section I Chapter 3, preplanned equipment modernization must be authorized prior to the exchange by the responsible SYSCOM. When a component supported by the Coordinated Shipboard Allowance List (COSAL) is Downloaded from https://www.everyspec.com
p. 404
NAVSEAINST 4790.8B
I-13 replaced by a component with different repair part requirements, but meets the same equipment design specifications, the appropriate SYSCOM must authorize the exchange. The SYSCOM must also authorize exchanges of components replaced by non- supportive components.
1-4.1 Alteration Management 3-M Reporting Requirements
For FMP managed alterations requiring logistic support, the 3-M documentation provided by the SYSCOM will have the Work Center, Job Sequence Number (JSN), and structured Alteration Number pre- assigned. These identifiers are used for tracking the life cycle of the alteration. This information is reported through the 3-M system as a configuration change. Refer to Section I Chapter 3 for additional information on configuration reporting.
If the issuing authority does not provide the formatted 3-M WC/JSN and Alteration number, the ship will assign the JCN. The structure of the alteration number is left to the reporting activity, except for the first two positions that must have an authorized alteration category prefix. Note that reference (c) contains additional types of configuration changes that are not applicable to 3-M reporting.
1-4.2 Ship's Force Requests for Configuration Changes
Ship's Force requests for Configuration Changes not covered by applicable alterations shall be submitted as TYCOM directed (refer to the TYCOM instruction). The request should be in the ship's CSMP prefixed by the authorized alteration category "AR".
1-4.3 Departure From Specification
When a component supported by the COSAL is replaced by a component with different repair part requirements but meeting the same specifications, the appropriate SYSCOM must authorize the exchange. Written communication is usually by Departure From Specifications (DFS) or Liaison Action Request (LAR) and subsequently documented by a completed Configuration Change Request (CCR). The CCR would identify the removal of the component by Record Identification Number (RIN). The replacement (Installed) component would require assignment of a new RIN and Logistic Support Documentation (LSD) by the Configuration Data Manager (CDM).
Downloaded from https://www.everyspec.com
p. 405
APPENDIX I-14 1-4.4 Certification of Shipyard Installed Alterations
The Naval Supervising Activity (NSA) provides a certification of alteration installations to the recipient ship when the alterations are accomplished by the shipyard. This certification includes the work center, JSN assigned to the alteration, and the Final Action Taken. The certification will be in the format shown in Figure I-1. The ship shall endorse the shipyard's certification letter and forward to the supporting activity managing the unit's Master CSMP. The endorsement provides authorization for information transmitted to be processed as completed deferrals in the Master CSMP. Refer to Figure I-2. This eliminates the need for documenting multiple configuration changes (OPNAV Form 4790/CK) to close the CSMP deferral. Configuration changes made by the depot in accomplishing the alterations are reported separately from 3-M.
1-4.5 Automated Data Process Between 3-M and SCLSIS
Ships' 3-M automated programs are designed to accept applicable data for file, sort, and display. The alteration information is automatically passed from the Ships' Configuration and Logistics Support Information System (SCLSIS)Configuration Data Manager’s Database – Open Architecture (CDMD-OA) to automated ships via the Automated Shore Interface process. For additional information on SCLSIS CDMD-OA and the ASI process refer to reference (c). Similarly, the MDS information may be transferred to a ship's Current Ship's Maintenance Project (CSMP) via the Master Job Catalog when authorized for accomplishment.
The communication link and interface procedures for processing 3-M and NDE-NM files, and CSMP file processing are contained in reference (b) and TYCOM instructions.
The procedures for adding alteration records to the Master Job Catalog (MJC), and distributing these changes to the TYCOM operating sites are contained in Appendix C and TYCOM instructions.
Downloaded from https://www.everyspec.com
p. 406
NAVSEAINST 4790.8B
I-15
(ACTIVITY LETTERHEAD)
4720 Ser/Orig. Code
Date From: (Originating Activity) To: Ship's Name
Subj: CERTIFICATION OF ALTERATION INSTALLATIONS DURING AVAILABILITY (include date range of availability)
1. The following alterations are certified installed. The listed alterations meet the requirements of the issuing agency as instructed, and include all required Logistics Support Documentation.
3-M WC/JSN ALTERATION NO. DESCRIPTION A/T
(For example only):
DXSA 0054 SADDG 00045 K MISSILE LAUNCH INSTL 5B EXSA 3994 SADDG 01003 K SSTG INSTL 5B EXSA 4007 SADDG 01675 K HPAC RPLCMNT 5B
By direction
Signature block
Copy to: (Cognizant TYCOM) COMNAVSEASYSCOM (Cognizant Code)
Figure I-1 Sample Certification of Alteration Installation Downloaded from https://www.everyspec.com
p. 407
APPENDIX I-16
(SHIP'S LETTERHEAD)
4720 Ser/Orig. Code Date
FIRST ENDORSEMENT on NSY ltr 4720 Ser/Orig Code of (Date of ltr)
From: (Ship's Name) To: (Supporting Activity, e.g., IUC, RSG, etc,)
Subj: CERTIFICATION OF ALTERATION INSTALLATIONS DURING AVAILABILITY (include date range of availability)
Request the alterations reported completed by basic correspondence be processed as completed deferrals in the Master CSMP.
By direction
Signature block
Copy to: (Cognizant TYCOM) COMNAVSEASYSCOM (Cognizant Code)
Figure I-2 1st Endorsement to Alteration Certification Letter Downloaded from https://www.everyspec.com
p. 408
MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL
APPENDIX J
RELIABILITY-CENTERED MAINTENANCE CERTIFICATION PROGRAM
Downloaded from https://www.everyspec.com
p. 409
APPENDIX J-i APPENDIX J
RELIABILITY-CENTERED MAINTENANCE CERTIFICATION PROGRAM TABLE OF CONTENTS
Paragraph Title Page
J-1 PURPOSE .................................................. J-1 J-2 CERTIFICATION LEVELS ..................................... J-1 J-2.1 Level I Certification .................................. J-1 J-2.2 Level II Certification ................................. J-1 J-2.3 Level III Certification ................................ J-1 J-3 ORGANIZATIONAL RESPONSIBILITY ............................ J-2 J-3.1 Naval Sea Systems Command (NAVSEA): .................... J-2 J-3.2 In-Service Engineering Agencies (ISEAs) & Fleet Technical Support Centers (FTSCs) ................................ J-2 J-4 RCM CERTIFICATION PROCESS ................................ J-3 J-4.1 Level I “Navy Backfit RCM for Practitioners” Course .... J-3 J-4.2 Level II “RCM for PMS Developers” Course............... J-4 J-4.3 Level III “Navy Backfit RCM for Trainers” Program ...... J-4
Downloaded from https://www.everyspec.com
p. 410
NAVSEAINST 4790.8B
J-1 APPENDIX J
RELIABILITY-CENTERED MAINTENANCE CERTIFICATION PROGRAM
J-1 PURPOSE To institutionalize Reliability Centered Maintenance (RCM) methodology for Navy maintenance managers and engineers tasked with development, revision and approval of maintenance requirements. This Appendix is directed at technical activities, contractors and engineers involved in answering TFBRs and designing new PMS documents. J-2 CERTIFICATION LEVELS RCM Certification is aligned along three levels to meet the distinctly different maintenance responsibilities that exist. Individual certification level levels include: J-2.1 Level I Certification Level I Certification addresses responsibilities of individuals tasked to develop, review, or approve changes to current maintenance tasks.
J-2.2 Level II Certification Level II Certification applies only to those individuals responsible to develop, review, or approve PMS task requirements on new systems or equipment.
J-2.3 Level III Certification Level III Certification is designed for a very select group of senior In-Service Engineers (ISEs) selected by their commands to teach Level I RCM Certification courses at their In-Service Engineering Agency and to provide a local RCM subject matter expert. Downloaded from https://www.everyspec.com
p. 411
APPENDIX J-2 J-3 ORGANIZATIONAL RESPONSIBILITY Responsibility for RCM Certification is as follows:
J-3.1 Naval Sea Systems Command (NAVSEA): As RCM Certification Program managing agent, NAVSEA is responsible for all aspects of the certification program. Specific responsibilities include:
a. Maintaining certification records;
b. Establishing RCM Certification curriculum;
c. Administering Level II and III courses as required, including recertification;
d. Monitoring of Level I courses;
e. Monitoring maintenance engineering tasks to ensure only certified individuals are assigned responsibility to develop, review or approve scheduled maintenance requirements; and
f. Administering testing requirements including maintaining test question and answer data bases for all RCM Certification levels.
J-3.2 In-Service Engineering Agencies (ISEAs) & Fleet Technical Support Centers (FTSCs) ISEAs and FTSCs are responsible to:
a. Maintain sufficient Level I certified personnel to develop, review, or approve changes to current scheduled maintenance tasks;
b. Maintain sufficient Level II certified personnel to develop review and approve new PMS task requirements;
c. Nominate and assign sufficient Level III certified personnel to conduct Level I RCM Certification courses as required; and
d. Ensure all contractors who develop new PMS tasks participate in the RCM Certification Program. Downloaded from https://www.everyspec.com
p. 412
NAVSEAINST 4790.8B
J-3 J-4 RCM CERTIFICATION PROCESS RCM Certification training comprises three elements:
a. Formal Instruction to develop a fundamental understanding of RCM methodology;
b. Application of principles to enrich the fundamental understanding of RCM principles and to demonstrate the practical application ; and
c. Testing to assess student knowledge and ensure an adequate level of qualification prior to certification. J-4.1 Level I “Navy Backfit RCM for Practitioners” Course Required attendees include ISEs and FTSC Commodity Specialists who develop, review, or approve changes to current maintenance tasks.
Location : ISEA sites.
Periodicity: As required to satisfy certification and recertification requirements.
Purpose: Tailored to cognizant systems and equipment of the host ISEA, each 2-day Level I course focuses on fundamentals necessary to apply the Navy Backfit RCM process to current maintenance tasks. Level I certification is dependant upon successful completion of a written examination administered by NAVSEA. In order to remain proficient, recertification is required every 3 years.
Recertification may be accomplished in one of two ways:
a. Successful completion of a Navy Backfit RCM for Practitioners exam; or
b. Successful participation in a SURFMER session.
All ISEs and Commodity Specialists who have completed a SURFMER session since January 1999 are granted initial Level I certification as of the completion date of their last SURFMER training session. Recertification, as discussed above, is required 3 years from completion of the qualifying SURFMER session. Downloaded from https://www.everyspec.com
p. 413
APPENDIX J-4 J-4.2 Level II “RCM for PMS Developers” Course Required attendees include ISEs tasked with development of, review or approval authority for new PMS task requirements. Contractors with similar responsibilities will also be required by language in acquisition contracts to attend.
Location: As designated by NAVSEA 04RM.
Periodicity : Quarterly or as required.
Purpose: Each 5-day RCM for PMS Developers course focuses on application of Classic RCM as defined in MIL-P-24534A (Navy). Fundamentals taught during this course are necessary to apply RCM principles to the development of PMS tasks for new systems and equipment. Final Level II certification is dependent upon successful completion of a written practical examination administered by NAVSEA. Recertification is required every 3 years.
Recertification is accomplished by successful completion of an RCM for PMS Developers certification exam. J-4.3 Level III “Navy Backfit RCM for Trainers” Program Required attendees include senior In-Service Engineers.
Location : As designated by NAVSEA 04RM.
Periodicity: Annually or as required.
Prerequisites: Successful completion of Level I and Level II certification requirements.
Purpose: The 10-day Navy Backfit RCM for Trainers course serves two functions:
a. To increase the Level III students’ foundation and understanding of RCM theory and methodology; and
b. To train senior ISEs in the techniques needed to effectively teach RCM principles and methodology.
Level III certified ISEs are authorized to provide Level I certifications training to personnel at their parent agencies and other ISEAs that do not have Level III certified individuals. Successful completion of the Level III course is dependent upon passing a written exam in RCM theory and Downloaded from https://www.everyspec.com
p. 414
NAVSEAINST 4790.8B
J-5 practical exercises. Certification is dependant upon successful completion of the Level III course and successful completion of a NAVSEA monitored practice teaching session typically 2 to 3 months after completion of the Level III course.
Recertification is required annually and may be accomplished in one of two ways:
a. Successful completion of a NAVSEA monitored practice teaching session; or
b. Successful completion of the Navy Backfit RCM for Trainers examination.
Downloaded from https://www.everyspec.com